Requirements_and_Specifications_Final.pdf

PDF 597 KB Posted

Attached to
Landfill Base Liner System, Sideslope Liner Repair Sacramento County, Kiefer Landfill
Solicitation number
2023-RFB-0174
Issued by
Sacramento County, California

About this file

This is a Request for Bid (RFB) document from the County of Sacramento, Department of Waste Management and Recycling (DWMR) soliciting bids for landfill base liner system and sideslope liner repair at the Kiefer Landfill (KLF). The project involves repairing Geosynthetic Clay Liner (GCL) panel separations discovered in Module 4, Phase 1 (M4P1) during routine maintenance. The estimated scope includes 70 seams to be repaired, with an average slope length of 139 feet per repair and a total estimated seam repair quantity of 9,700 feet. The contract term is from the date of execution until June 30, 2024, with a targeted completion time of 60 working days. Key dates include a non-mandatory pre-bid site walk-through on April 10, 2023, the final date to submit questions on April 12, 2023, and the bid submission deadline on April 19, 2023.

Bidders are required to submit pricing for mobilization/demobilization, liner repair costs per linear foot, geosynthetic clay liner costs per square foot, and 60-mil HDPE geomembrane liner costs per square foot. The project will seek FEMA reimbursement and requires bidders to have a California Department of Industrial Relations (DIR) Certification Number. Prevailing wage requirements are in effect, and bidders must agree to specific federal contracting provisions. The award will be determined by the lowest responsive and responsible bid from a qualified bidder meeting the minimum qualifications outlined in Attachment B. Liquidated damages are set at $5,000 for each calendar day of delay, and bidders must have a SAM.gov Unique Entity Identifier (UEI) number to be eligible for potential federal funding reimbursement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR BID (RFB) -- THIS IS NOT AN ORDER

COUNTY OF SACRAMENTO

DEPARTMENT OF GENERAL SERVICES

CONTRACT AND PURCHASING SERVICES DIVISION

2023-RFB-0174

REQUEST FOR BID (RFB) FOR LANDFILL BASE LINER SYSTEM,

SIDESLOPE LINER REPAIR, SACRAMENTO COUNTY, KIEFER

LANDFILL

Background

The County of Sacramento, Department of Waste Management and Recycling

(DWMR) is seeking a firm that is experienced in installing and repairing the geosynthetics components of landfill base liner systems for the purposes of liner repair within Module 4, Phase 1 (M4P1) at Kiefer Landfill (KLF), 12701 Kiefer Boulevard, Sloughhouse, California 95683.

In January 2023, during routine geomembrane liner repair work on the south side slope of M4P1, Geosynthetic Clay Liner (GCL) panel separation was observed. GCL panel separation has since been identified in multiple locations, and the County is contracting to repair the areas where GCL separation exists.

The County is repairing the liner system in stages, and as such, has not performed a complete survey of the areas where the GCL separation has occurred. An estimate of the anticipated scope of work (Work), including number of seams and average seam length are included for bidding purposes.

TERM

This Agreement shall be effective and commence as of the date of execution and shall remain in effect until June 30, 2024

Basis for Award

This bid award will be determined by the lowest responsive and responsible bid by a qualified Bidder, as defined in Attachment B, Installer Company and Minimum Qualifications.

REQUIREMENTS AND SPECIFICATIONS FOR 2023-RFB-0174 FOR LANDFILL BASE LINER

SYSTEM, SIDESLOPE LINER REPAIR, SACRAMENTO COUNTY, KIEFER LANDFILL

Scope of Work

The scope of work for the successful Bidder will include the following:

Procure geomembrane and GCL: A summary of the side slope base liner system component materials required for this work is included as Table 1.

Documentation: All materials assigned for repair services at KLF shall have corresponding manufacturer’s quality control (MQC) certifications with matching roll numbers and/or lot numbers as appropriate for the specific material property testing frequency. Material properties shall meet the material specifications identified in the Module 4, Phase 1 technical specifications (Attachment C).

Coordination: Installer shall coordinate their work schedule with the other parties involved. This includes DWMR’s project manager and the project manager for the third-party CQA Consultant contracted to observe and document liner system repairs. No repair work shall be performed without the

CQA Consultant present.

Repair Work: The Work is located in a contiguous area of M4P1, and consists of cutting open the geomembrane liner at the location of each GCL seam, evaluating the extents of the repairs that are required, and repairing the GCL and the geomembrane seam in accordance with the M4P1 Project Specifications, the M4P1 CQA Plan requirements (Attachment D), and the GCL

Repair Work Plan (Attachment E).

On the coordinated start date, Installer shall mobilize to KLF, to the location of the liner repair work, with repair materials and equipment to meet with the

CQA Consultant. Installer shall perform trial welds on representative geomembrane and perform destructive tests on the trial welds. The test results must pass strength and failure mode requirements prior to beginning repair work.

Worker Safety: All necessary worker health and safety related gear and equipment for Installer to complete the work in a safe manner, including, but not limited to gas monitors and ventilation as conditions warrant, shall be provided by the Installer.

Liner Repair Quantity: The County has not performed a complete survey of the areas where the GCL separation has occurred. The actual number of seams and seam lengths may change based on findings in the field when repair work commences. Based on investigative work conducted to date, the

County has estimated the following liner repair quantities for bidding purposes. These values correspond to the quantities listed in the Bid Form.

Number of seams to be repaired: 70 seams Average slope length per repair: 139 ft./repair

Total estimated seam repair quantity: 9,700 feet Average width of GCL patch: 3 feet

Average width of geomembrane patch: 3 feet

Time of Completion

The time for completion of this contract shall be 60 working days commencing as specified in Section 7-1, “Beginning of Work” of the Standard Construction Specifications. Standard Construction Specifications Sections 7-12, “Delays”, 7-15, “Time of Completion”; 7-16, “Extension of Time Not a Waiver”, 7-17, “Inclement Weather and Contract Time”, and 7-18, “Extension of Time”, shall also apply to the Work.

Waste excavation work will be performed under a separate contract to expose the sections of the M4P1 side slopes that require repair under this contract. It is expected that the waste excavation will remain ahead of the liner repair contract work operations. The County will provide the Installer 48-hour written notification that liner repairs must begin within 5 calendar days. The

Installer must perform all work operations in one continuous operation to the extent possible.

In the event that weather conditions prevent liner repair work, temporary geomembrane patches will be required over any exposed seams.

Note: Hours of liner repair may vary based on need. KLF regular hours of operation are 6:30 am – 4:30 pm Monday - Friday. Liner repair shall occur within that time frame unless an alternate schedule is mutually agreed upon between the DWMR and the successful Bidder.

Liquidated Damages

Liquidated damages shall be $5,000 for each calendar day delay, pursuant to Government Code 53069.85.

Bid Requirements

Bidders shall submit a cost proposal based on the scope of work outlined in this RFB. Bids must be submitted in the OpenGov.com Pricing Table that will include estimated quantities based on specific units of measurement.

Bidders shall provide the following cost items in the Pricing Table:

Mobilization and demobilization (lump sum)

Cost for liner repair (cost per linear foot of composite liner system repair, inclusive of all tasks, labor, and equipment required to complete work in compliance with the GCL Repair Work Plan) Cost for geosynthetic clay liner (cost per square foot)

Cost for 60-mil HDPE geomembrane liner (cost per square foot)

Bidders shall provide company and personnel qualifications in the Vendor

Submission section of the OpenGov.com RFB as outlined in Attachment B, Installer Company and Personal Minimum Qualifications.

COUNTY Sample Agreement

A copy of the County’s Sample Agreement is found in the Attachments section of the OpenGov.com RFB. Bidders will be required to accept the County’s terms and conditions including the insurance requirements in the

Sample Agreement or submit exceptions under Solicitation Exceptions in the Vendor Submission section of the OpenGov.com RFB.

Department of Industrial Relations Certification

Bidders must have a California Department of Industrial Relations (DIR)

Certification Number and submit that number in the Vendor Submissions section of the OpenGov RFB. Having a DIR number is required under the County’s Department of Labor Compliance. For information, call the

California Department of Industrial Relations (DIR) at (844) 522-6734.

Prevailing Wage Requirement

The installation, repair or maintenance work done for the preservation, protection and keeping of any publicly owned or publicly operated facility (plant, building, structure, ground facility, utility system or any real property) for its intended purpose in a safe and continually usable condition for which it has been designed, improved, constructed is subject to prevailing wage requirements. Bidders will be required to acknowledge the

Prevailing Wage requirement in the Vendor Submission section of the OpenGov.com RFB.

MAINTENANCE PREVAILING WAGES:

(California Labor Code, sections 1720, 1725.5, 1770, 1771.1(a), 1771.5)

See Appendix P, Maintenance for Prevailing Wage Requirements.

Firm awarded a contract must attend a “pre-construction” meeting regarding Prevailing Wage requirements with the Sacramento County

Department of Labor Compliance prior to starting work. For additional information, call (916) 875-2711.

Please note, failure to obtain a certification issued by the State of

California Department of Industrial Relations while bidding on a

Prevailing Wage Project shall result in disqualification from this Bid and may result in fines or penalties from the DIR.

FEMA Requirements

The County will be seeking FEMA reimbursement for this project. Bidders must agree to the terms and conditions specified in the Byrd-Anti Lobbying Amendment included as Attachment A, and Exhibit C, Federal Contracting

Provisions. Bidders will be required to agree to these provisions in the Vendor Submission section of the OpenGov.com RFB.

Sam.Gov Requirement

For County to receive Federal funding reimbursement for projects, the

Contractor must have a SAM.gov issued Unique Entity Identifier (UEI) number by the time of award. Bidders will be required to agree to this provision in the Vendor Submission section of the OpenGov.com RFB. The

Contractor's UEI ID number is a 12-digit alphanumeric ID assigned to an entity by SAM.gov found at the URL below:

https://sam.gov/content/entity-information

Attachments:

Attachment A Byrd-Anti Lobbying Amendment

Attachment B Liner Repair Installer Company and Personnel Minimum Qualifications

Attachment C M4P1 Project Specifications https://sam.gov/content/entity-information

Attachment D M4P1 CQA Plan Attachment E GCL Repair Work Plan

Attachment F County Sample Agreement Attachment G RFB Requirements and Specifications

Attachment H Table 1 - Summary of the Side Slope Base Liner System Component Materials

Attachment I Exhibit C - Federal Contracting Provisions

Key Events

Event/Action Dates

Bid Release March 30, 2023

Non-mandatory pre-bid site walk-through Kiefer Landfill, Bldg. B (right of scales)

12701 Kiefer Blvd Sloughhouse, CA 95683

April 10, 2023, 10:00 am

Last day to submit written questions through OpenGov.com

April 12, 2023 by 3:00 pm

Final Date for County to answer questions and submit Addenda to RFB (if necessary)

April 14, by

3:00 pm

Final date to submit Bids April 19, by

3:00 pm

Award at Sacramento County Board of

Supervisors Meeting

Date TBD if necessary