This statement of work outlines janitorial services requirements for two air traffic control towers located in Allentown and Reading, Pennsylvania. The solicitation seeks pricing for labor, materials, and supplies to provide daily, weekly, monthly, quarterly, semi-annual, and annual janitorial tasks such as emptying trash, vacuuming, mopping, cleaning restrooms and windows, at both sites in accordance with detailed specifications. Interested parties must visit the sites on December 7, 2021 and submit pricing proposals under Section B of the solicitation by January 7, 2022 at 4:00 PM EST to the Department of Transportation Federal Aviation Administration Southern Region. The incumbent contractor is responsible for the dumpster service and supplying items like light bulbs, toilet paper, and plastic trash can liners.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Janitorial services to be performed at the ABE ATCT and RDG ATCT.
PART A:
A.1 FACILITY ADDRESSES The Allentown (ABE) ATCT, located at 135 Fashion Dr. M Allentown, PA 18109; and the Reading (RDG) ATCT, located at Reading Regional Airport 2405 Bernville Rd Reading, PA 19605.
A.2 GOVERNMENT PERSONNEL: Contracting Officer (CO) Bill Lockard; Contract Specialist (CS) Jacqueline T. Jones; Contracting Officer’s Representative (COR) Connie Gingrich
A.3 PRECOMMENCMENT MEETING
Prior to commencement of work, a conference must be held between representatives of the contractor and the Government to discuss contractual obligations, etc. pertinent to this contract.
A.4 SUBMITTALS AND SCHEDULES
Within 5 business days of award, the contractor must submit a working schedule of the proposed operations with which they plan to perform the work required under this contract, and which must set forth specific dates for accomplishment of each periodic item of work. These scheduled dates for performance of each periodic item must be within the first third of the respective period. The contractor will list all manpower and staffing, and will schedule all work assignments, whether performed on a repetitive rotating cycle or on a one-time basis. The schedule must be complete and approved by the Contracting Officer or his/her representative no later than 30 days subsequent to establishment of a Notice to Proceed date.
The above must be strictly adhered to by the contractor and may be changed only by mutual agreement of the parties.
Prior to commencement of work, the contractor must provide the COR with an initial listing of all janitors working at the facility with a schedule of their duty hours. This list must be updated whenever any change in staffing takes place. Unauthorized personnel of the contractor will not be permitted in the facility.
The contractor must utilize a daily assignment sheet for each of its employees indicating daily as well as periodic services to be performed by the specific individual. The employee must indicate accomplishment of the specific item and/or room and the time of the accomplishment. After submission to the contractor’s supervisor for his/her review, inspection and signature, assignment sheets must be furnished periodically or by request to the Contracting Officer’s Representative (COR). Exceptions taken by the COR will be annotated thereon and returned to the contractor’s supervisor for immediate correction.
A.5 SUPERVISION
The contractor must prohibit its employees from disturbing papers on desks, opening desk drawers or cabinets, or using telephone or office equipment provided for official Government use.
The contractor must provide an experienced leading person to supervise the other on duty janitors. This person must serve as a representative of the contractor and must act as liaison between Government representatives and the contractor.
In addition to the above supervision of the janitorial personnel, the contractor must identify an experienced member of its executive staff to provide overall supervision of the janitorial services provided.
The above personnel must be identified by written memo to the SSC Managers with a copy to the contractor’s employees.
The contractor must contact the COR at least monthly by telephone or in person to discuss the services provided.
A.6 .CONDUCT OF CONTRACTOR EMPLOYEES
The contractor and its employees must conform to the following in the performance of this contract:
a. The contractor and all employees must comply with applicable building regulations regarding security, fire, safety, traffic, and parking. Personnel must not linger in areas when performing their duties in that area.
b. The contractor, upon request of the Contracting Officer, must dismiss from the premises any employee who, in the opinion of the Contracting Officer, interferes with proper service, or fails to comply with the terms, conditions, or specifications of the contract, or who is disorderly or abusive or not available on the premises during his/her on-duty time.
c. All misplaced and lost property found by the contractor’s employees in the course of their work will be turned in to the SSC Managers and notification given to the COR.
d. Contractor’s employees will be provided locker space if available. During the term of the contract, the contractor would be responsible for the condition of the lockers and will clean, paint and repair them as required so that they will be returned to the Government in the same condition at the termination of the contract as they were received at the time of commencement of work.
A.7 DEFINITIONS
To comply with the performance requirements of this contract, all work will be accomplished in accordance with the following definitions:
A.7.1 FREQUENCY OF PERFORMANCE DEFINITIONS
Daily Work must be performed each day at the times specified. (5-days/week M-F Administrative space) (7 days/week other areas)
Weekly Work must be performed once each week on whatever day of the week the contractor chooses, provided that the periods between the performances of the work are of approximately equal duration.
Semi-Weekly Work must be performed twice each week. Twice a week services must not exceed 4 days between services, and must be performed at least twice within a 7-day period.
Semi-Monthly Work must be performed twice each month on whatever day the contractor chooses, provided that there are not less than 13 or more than 17 days between the performance of the work.
Monthly Work must be performed once a month on whatever day the contractor chooses, provided that the periods between the performances of the work are of approximately equal duration.
Quarterly Work must be performed once every three months on whatever day of the month the contractor chooses, provided that the periods between the performances of the work are of approximately equal duration.
Semi-Annual Work must be performed once every six months on whatever day of the month the contractor chooses, provided that the periods between the performances of the work are of approximately equal duration.
Annual Work must be performed once as shown in the approved schedule.
As Required Work must be performed at the request of the Contracting Officer’s Representative for miscellaneous tasks of minimal time and value.
A.7.2 FLOOR CLEANING DEFINITIONS
Floors will be cleaned by sweeping, stripping, washing, damp mopping, chemically mopping, re-finishing, and buffing in accordance with the following definitions and in accordance with the work schedules:
(1) Sweeping – Upon completion, floor will have no dust streaks, dirt in corners, behind radiators or doors, under furniture, or show marks where dirt was picked up with dustpan.
All except imbedded dirt must be removed.
(2) Washing – Floor will be cleaned by use of water and cleaning agent applied with brush or scrubbing machine. Imbedded dirt will be loosened from floor surface by deck brush or machine scrubber using water and cleaning agent no stronger than necessary. Scrubbing water will be removed and surface rinsed with plain water and clean mop.
Both scrubbing and rinsing water must be changed frequently. Care must be used not to splash baseboard, furniture, and other equipment while scrubbing and rinsing. Difficult places such as corners, under radiators, behind pipes, etc. must be washed by hand. After washing, floor should have a uniform clean appearance with all imbedded dirt, stains, marks, film, standing water, and cleaning solutions removed.
(3) Damp Mopping – Floors will be cleaned of dirt, dust, film, standing water, and surface marks by using a cotton or sponge mop, a minimum amount of water, and a cleaning agent.
All but imbedded dirt will be removed.
(4) Chemical Mopping – Floor will be cleaned of dirt, dust, film and surface stains by use of chemically treated mop or a chemically treated cloth affixed to a mop.
(5) Stripping – Floor will be cleaned of all wax down to surface of flooring material applying a non-flammable compound appropriate for the area being cleaned with a brush or floor stripping pad, such as “3M’ pads, affixed to a scrubbing machine. Steel wool may not be used anywhere in this building. Floor will be rinsed to remove cleaning solution, loosened wax, dirt, film, and marks.
(6) Finishing – Apply three thin, even coats of water emulsion wax (similar or equal to Astor
Tiger Tuff Floor Finish) with a clean fine-strand coat to be applied six inches from baseboards and stationary objects mopping in a single parallel stroke. Wax to be applied approximately one foot from baseboards and stationary object on second and third applications. Machine buff with soft polishing brush or synthetic polishing pad. Remove wax from baseboards, furniture legs, and bases.
(7) Buffing – A properly buffed floor will show no scuffmarks or surface stains. All surface dirt will be removed by sweeping or mopping prior to buffing.
(8) Sealing – A properly sealed floor will provide a protective coating for the floor from water, abrasion, etc.
A.7.3 DEFINITIONS OF OTHER CLEANING TASKS
Dusting, cleaning, wiping down, and washing must be done on all surfaces, including walls, ceilings, ducts, etc. in accordance with the work schedule and in compliance with the following terms and definitions
(1) Dusting – Dust must be removed from all surfaces to be dusted by using a vacuum cleaner or a treated duster or yarn or cloth. Dust must be gathered up into the duster, not spread by it.
Feather dusters or dusting brushes will not be permitted. A surface is properly dusted when no residue is picked up on a clean cloth wiped across it and when all corners, edges, and crevices yield no dust when wiped.
(2) Clean – On floors, walls, ceilings, furniture, and fixtures visible spots, stains, and other surface blemishes resulting from spilling, splattering, spraying, or other means will be removed by washing the area around the stain in such a manner that the stain is removed without resulting in a noticeable difference between the cleanliness of the area wherein the stain was removed and the rest of the surface. When spotting results in several clean areas surrounded by a dirty surface, the dirty surface must be washed at no additional cost to the Government even though the scheduled washing is not yet due.
(3) Washing – A bright clean surface is left after the removal of all surface dirt by application of water and a cleaning agent using a damp cloth, sponge, or washing appliance. No streaks, smears, or spots may remain after rinsing with a clean damp cloth or sponge. The amount of water used in the washing and rinsing must be controlled so that no loose water runs or is wrung out from the cloth or sponge. When the surface is dry, a clean cloth wiped over it will pick up no dirt and will leave no streaks.
(4) Wiping Down – The surface is wiped with a treated cloth or sponge so that all surface dirt, dust, or moisture is removed and no streaks or marks are left. This operation is generally performed only on tiled or glazed surfaces.
(5) Vacuuming – Loose dirt, paper scraps, crumbs, and other debris, which are not removed by dusting, must be removed by vacuuming. A properly vacuumed surface will have no dirt in corners, along ledge, or in crevices.
(6) Polishing – Surfaces not finished with a crackle paint finish will be polished with a polishing agent appropriate for the surface to be polished. A hard finish wax will be used for all wood surfaces and glossy enameled metal surfaces. Metal polish will be used on natural finish metal surfaces and approved glass polish for glass surfaces. Oily polishes or polishes which leave an oily residue may not be used. A properly polished surface presents a dry shiny surface free of dust and scuff marks.
All smoking receptacles will be serviced by emptying, wiping, and washing in accordance with the work schedules and in compliance with the following definitions:
(1) Emptying – Ash trays and smoking receptacles will be emptied into non-flammable trash containers only after the cleaner has determined that all butts are out. All ashtrays and smoking receptacles will be considered empty when all butts, papers, chewing gum wads, and other objects are removed from them.
(2) Wiping – All residue, dirt, dust, or liquids which stick to the inside or outside of the ash trays, smoking receptacles, or waste receptacles must be removed by wiping with a damp or dry cloth or sponge. If wiping does not produce the desired results, washing must be employed.
(3) Washing – All residue dirt, dust, or liquids are removed from the inside and outside of all smoking receptacles and waste receptacles by washing or scrubbing with water and cleaning agent following with rinsing and drying.
Metal work, plumbing fixtures (limited lavatories only), and glass surfaces (other than windows) will be serviced by cleaning and polishing in accordance with the work schedule and in compliance with the following:
(1) Cleaning – Surfaces are left bright and clean after application of treated cloth or sponge.
Surface dirt, corrosion, and watermarks are removed.
(2) Polishing – Surfaces are left shiny and bright with no streaks, water marks, fingerprints, or other blemishes after application or approved polish. When polish is dry, surface is protected from marks by polish.
Venetian Blinds, when installed, will be serviced by dusting monthly and washing semi- annually in compliance with the following definitions:
(1) Dusting – Slats, tapes, cords, and supporting members will be dusted. Both surfaces of each slat must be clean and free from dirt. Tapes and cords must have no loose dirt on them.
(2) Washing – Wash with damp cloth and mild soap solution.
NOTE 1: “WARNING” Steel wool, metal scouring pads, or any metallic abrasives for use in cleaning or polishing is NOT PERMITTED under this contract.
A.8 SECURITY REQUIREMENTS
For all sites, Individuals working in the facility must obtain an FAA Contractor Badge. If they do not have a badge, an escort with an FAA Contractor badge must be with the workers at all times and in-line of sight of each worker (one escort/worker). In order to gain access to the facility and obtain a key, they must pass a background check. Individuals not badged will not be allowed to be dropped off at the facility and left alone. The FAA will NOT provide an escort.
A.9 GENERAL STANDARDS
Custodial cleaning products required in the performance of this SOW must carry the Environmental Protection Agency Design for the Environment (DFE) label, Green Seal certification, or must meet/exceed South Coast Air Quality Management District (SCAQMD) specifications and/or DFE and Green Seal specifications. Cleaning products must minimize exposure to potentially harmful chemicals (e.g., corrosives, skin irritants, human carcinogens, etc.) and contain biobased solvents, reduced flammability, and low or no volatile organic compounds. Green cleaning program guidance can be found in more detail on the Office of Federal Sustainability website (http://www.sustainability.gov)
If it is determined that such certified products do not meet Government performance requirements, the Contractor must submit a proposed alternative that would meet the performance requirements with the lowest environmental impact for evaluation and acceptance. Products that fall under the Environmental Protection Agency (EPA) Comprehensive Procurement Guidelines (CPG) (http://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program) must meet the minimum recovered (recycled) content levels. Bio-based products must be used in accordance with the U.S. Department of United States Department of Agriculture’s BioPreferred program (http://www.biopreferred.gov). The contractor must purchase and use Energy Star or other energy-efficient items listed on the Department of Energy’s Federal Energy Management Program (FEMP) Product Energy Efficiency Recommendations product list.
PART B:
ABE ATCT JANITORIAL REQUIREMENTS located at 135 Fashion Dr. M Allentown, PA 18109
B.1 ADMINSTRATIVE INSTRUCTIONS
1) Janitor services in rooms containing electronic equipment must be performed during working hours of the ABE SSC Facility Supervisor or his authorized representative.
2) Window washing must be performed during the daylight hours.
3) The work must be approved and accepted by the Facility Supervisor or his authorized representative. The contractor will be required to submit in duplicate all invoices to the Supervisor for his approval prior to submission for payment.
4) A work schedule will be provided by the Supervisor or authorized representative, to the contractor, indicating when work must be performed. All work must be performed satisfactorily within time intervals designated on the work schedule. If work is not completed satisfactorily within the time intervals indicated, a deduction from the monthly payment will be warranted.
5) Adequate toilet, ATCT, break room supplies (white ‘C’ fold towels to fit holders, toilet tissue, bowl deodorants, anti-bacterial hand lotion liquid, and dispensers) must be furnished by the contractor.
6) The supplies furnished by the contractor must be good commercial grade, acceptable to the SSC Supervisor or his authorized representative.
7) The contractor must furnish the necessary labor, tools, equipment, and materials to perform required functions.
8) The contractor must remove all trash from the building covered by this contract. Contractor must provide disposal dumpster service.
9) All work must be performed in a workmanlike manner with a minimum of interference and inconvenience to personnel on duty.
10) Contractor must supply plastic trash liners for all wastebaskets. Liners must be of sufficient size and thickness to prevent any spill over or breakage.
11) The janitorial services must be performed by the contractor in accordance with the following schedule:
12) Supply and replace all light bulbs are required in the following areas:
All administrative and equipment spaces in base building (not included are specialty bulbs found in at operations areas: TRACON, tower cab, parking lot lights, sidewalk lights, or ATCT exterior spotlights.
B.2 DAYS PER WEEK
Work shall be performed during administrative hours unless otherwise coordinated with SCC manager, six day per week- Monday through Saturday, once per day. Janitorial services are required on the 10 legal holidays observed by the FAA.
B.3 WORK SCHEDULE
B.3.1 DAILY TASKS
1) Empty wastepaper baskets in all rooms (including bulky material/cartons) and dispose of refuse away from premises. Liners for wastepaper baskets must be replaced on a timely basis to prevent odors or unsanitary conditions.
2) Vacuum all carpeted and tile floors.
3) Sweep stairs from elevator on the 7th floor to the tower cab.
4) Clean all restrooms thoroughly and replenish necessary supplies.
5) Clean sink, range, refrigerator, and microwave ovens in the break rooms and in the tower cab.
6) Dust consoles, windowsills, and furniture in the tower cab. Clean with damp cloth, as required.
7) Damp mop tiled floors (excluding storage areas)
8) Clean the elevator walls.
9) Spot clean walls as needed.
B.3.2 BI-WEEKLY TASKS
The following work must be performed once every two (2) weeks.
1) Wash and clean windows in the Control Tower, inside and out. Must be cleaned during daylight hours only. The Controller in charge must certify the work as being satisfactory.
2) Sweep and damp mop all concrete floors.
3) Clean inside of all windows.
B.3.3 MONTHLY TASKS
The following work must be performed monthly (every 30 days.)
1) Scrub and wax tile covered floor after 10 pm.
2) Clean HVAC return vents (2) located in Tower CAB, Center Island.
3) Damp mop the equipment room.
B.3.4 QUARTERLY TASKS (every 90 days)
1) Clean stairway shaft from Tower Cab to the ground level.
2) Scrub and wash all tile and grout in tile walls.
3) Dust all high surfaces in TRACON after 10 pm.
4) Vacuum and shampoo TRACON Wall and ceiling tiles after 10pm.
5) Clean all window blinds.
B.3.5 SEMI-ANNUAL TASKS
The following must be performed once every six months on whatever day of the month the contractor chooses, provided the periods between the performance of the semi-annual work are of approximately equal duration.
1) Clean all HVAC return and source vents.
2) Strip, wax, and buff all tile floor areas after 10pm.
3) Shampoo all carpeted areas. Saturday only.
4) Power wash exterior of Tower Landings and exterior floors with appropriate cleaner twice a year after bird migratory season (late October and late May, early June). Vendor will provide the power washer.
B.3.6 ANNUAL TASKS
1) Clean Tower Cab and Base Building roof drains (October/November).
2) Remove, clean, and reinstall MYLAR Shades located in the Tower Cab (July/August).
B.3.7 SQUARE FOOTAGE
ALLENTOWN ATCT
BASE BUILDING
ROOM # ROOM NAME SQ FT FLOOR TYPE
101 VESTIBULE 121 CARPET
103 AF ADMIN AREA 414 CARPET
104 RADAR SET 124 CARPET
105 NAVAIDS SET 131 CARPET
106 SFO MANAGER 178 CARPET
107 COMPUTER 129 CARPET
108 LOGISTICS 154 CARPET
109 TELCO 152 TILE
111 AF WORKROOM 210 TILE
112 AF BULK STORAGE 295 TILE
113 AF TECH ROOM 311 TILE
114 TTG 134 CARPET
115 TRAINING 148 CARPET
116 EQUIPMENT 2004 TILE
117 CORRIDOR 476 TILE
118 TRACON 625 CARPET
120 SPS 130 CARPET
121 LIGHT LOCK 61 CARPET
123 ENGINE GENERATOR 425 TILE
124 JANITOR 48 TILE
125 MECH ROOM 742 N/A CONCRETE
126 UPS/SWITCH ROOM 201 N/A CONCRETE
127 AT AUS LAN OFFICE 191 CARPET
128 LOCKER ROOM 211 TILE
129 BREAK ROOM 905 TILE
130 MEN'S TOILET 198 TILE
131 WOMEN'S TOILET 186 TILE
132 STUDY 147 TILE
133 TOILET 82 TILE
134 CORRIDOR 234 TILE
135 PLAYBACK 78 TILE
136 ADMIN STORAGE 107 TILE
137 TRAINING/CONFERENCE 269 CARPET
138 SUPERVISORS 201 CARPET
139 AT ADMIN AREA 468 CARPET
140 AT OATS 126 CARPET
141 AT MANAGER 181 CARPET
142 AATM 140 TILE
143 PPS 129 TILE
144 VESTIBULE 78 TILE
total 11144
JUNCTION LEVEL
J6 MEN'S TOILET 29 TILE
J7 WOMEN'S TOILET 29 TILE
total 58
CAB
CAB 300 CARPET
grand total 11502
PART C:
RDG Janitorial Requirements located at Reading Regional Airport 2405 Bernville Rd Reading, PA 19605.
C.1 ADMINSTRATIVE INSTRUCTIONS
1) All work must be approved and accepted by the SCC manager, or his authorized representative.
2) Vacuuming and window washing in the cab must be performed during daylight hours.
C.2 DAYS PER WEEK
Janitorial services will be required on a six (6) day week basis (Monday through Saturday) in Tower Cab and fifth floor lavatory and Monday through Friday in other areas, once per day.
C.3 WORK SCHEDULE
C.3.1 DAILY TASKS
The following must be performed once each day.
1) Empty all wastepaper baskets and dispose of refuse (including bulky materials/cartons).
2) Sweep all floor space, corridors and stairways.
3) Dust console surface in tower cab.
4) Clean all sinks and toilet bowls (using disinfectant solution); replenish all toilet supplies
(including paper towels, tissues, liquid soap, deodorant, etc.) in lavatory rooms.
5) Empty all waste receptacles in lavatory rooms, clean mirrors.
6) Mop all lavatory floors (using disinfectant solution).
7) Keep glass doors and entrance clean at all times (interior and exterior foyer area).
8) Vacuum carpet in tower cab and base building and remove spots where necessary.
9) Supply and install light bulbs (fluorescent, exit and regular) when necessary.
10) Supply and service trash dumpster.
CONTRACTOR WILL NOT CLEAN ELECTRONIC DEVICES AND UNDER NO
CIRCUMSTANCES USE FLUIDS OF ANY NATURE CLOSELY THERETO.
C.3.2 WEEKLY TASKS
The following work must be performed each week on whatever day of the week the contractor chooses, provided that the periods between the performance of the work are of approximately equal duration.
1) Damp mop all linoleum floors.
2) Dust all office furniture and horizontal surfaces, excluding electronic equipment.
3) Vacuum carpet in administrative areas and remove spots where necessary.
C.3.4 MONTHLY TASKS
The following must be performed once each month on whatever day of the week the contractor chooses, provided that the periods between the performance of this monthly work are of approximately equal duration (all floors).
1) Polish (machine buff) all linoleum areas.
2) Spray wax as necessary.
3) Wash and polish all chrome fixture around wash basins and toilet bowls in lavatory rooms.
4) Remove splash marks from walls around wash basins and toilet bowls in lavatory rooms.
5) Wash tower cab windows, inside and outside.
6) Wash window sills, doors, railings and electric switch areas.
7) Wash all windows in building.
8) Clean both sides of windbreaks by entrance door
C.3.5 QUARTERLY TASKS
The following work must be performed once every three months on whatever day of the month the contractor chooses, provided that the periods between the performance of this quarterly work are of approximately equal duration.
1) Clean concrete stairs and landings.
2) Clean tiles walls and scrub and clean tile floors, grout in all lavatories.
3) Remove all wax accumulations on kick plates and equipment rack bases
4) Strip and wax (using non-skid wax) all tiled areas. Saturday only.
5) Wash all windows of bookcase sections.
6) Clean all HVAC vents fixtures and grills.
C.3.6 SEMI-ANNUAL TASKS
The following must be performed once every six months on whatever day of the month the contractor chooses, provided the periods between the performance of the semi- annual work are of approximately equal duration.
1) Shampoo all carpeted areas. Saturdays Only
C.3.7 ANNUAL TASKS
1) Clean and wash all lighting fixtures, all rooms and floors.
2) Remove, clean and reinstall MYLAR Shades located in the Tower Cab (July/August)
3) Clean Tower Cab, parapet and base building roof drain (October/November)
C.4 DESCRIPTIONS, SQUARE FOOTAGE, TYPES OF FLOORING
READING ATCT
DESIGNATION APPROX. SQUARE FT TYPE FLOOR FINISH
BASE BUILDING
CONFERENCE/TRAINING 260 CARPET
ATCS RM 120 CARPET
AT MANAGER RM 144 CARPET
SECRETARY RM 178 CARPET
LAVATORY 62 TILE
LAVATORY 62 TILE
HALL 81 CARPET
BREAK RM 199 CARPET
LINK CONNECTION 380 TILE
LINK CONNECTION 42 CARPET
SMOKE RM 50 TILE
STORAGE RM 529 PAINTED
total 2107
FIRST FLOOR
MECHANICAL EQUIP RM 300 PAINTED
ELECTRICAL PANEL RM 91 PAINTED
ENGINE GENERATOR RM 230 PAINTED
TELEPHONE RM 85 TILE
STORAGE RM 75 PAINTED
GROUND EQUIP RM 75 PAINTED
CORRIDOR 320 CARPET
STAIRWAY 70 PAINTED
LAVATORY 40 TILE
total 1286
SECOND FLOOR
AFSFO 835.2
ADMINISTRATIVE SPACE 650 CARPET
CORRIDOR 70 PAINTED
STAIRWAY 65 PAINTED
AFSFO STORE RM 450 CARPET
total 1235
THIRD FLOOR
OFFICE/BREAK RM 750 CARPET
WORKSHOP/EQUIP RM 140 TILE
CORRIDOR 70 PAINTED
STAIRWAY 65 PAINTED
STORAGE RM 140 PAINTED
total 1165
FOURTH FLOOR
ATM ADMIN SPACE 400 CARPET
MECHANICAL EQUIP 324 PAINTED
CORRIDOR 70 PAINTED
STAIRWAY 65 PAINTED
STORAGE RM (ATM) 934 PAINTED
total 1793
FIFTH FLOOR
TOWER CAB 300 CARPET
JUNCTION RM 130 PAINTED
LAVATORY 16 TILE
total 446