About this file
The document is a set of general provisions for the Reese Street Caisson Treatment project, issued by the City of Pittsburgh's Department of Mobility and Infrastructure. The project involves stabilizing a sliding earthen slope on the northern slope of Mount Washington, just north of 107 Reese Street, through limited mine grouting, installation of a closely-spaced reinforced concrete caisson slope treatment, and limited rock scaling. Key project tasks include designing and implementing a traffic control plan, construction surveying, installing erosion and sediment controls, limited tree removal, site preparation, selective grouting of the Pittsburgh Coal seam, caisson installation, slope regrading, rock shielding, and site restoration.
The document outlines several administrative and technical requirements for the project, including material control, testing, and certification responsibilities. Noise-producing work is restricted to Monday through Saturday, 7 a.m. to 8 p.m., with specific holiday work prohibitions. Contractors must provide certifications for various materials, including aggregates, concrete, grout, reinforcing steel, and pipes. Subsurface boring sample core boxes are available for inspection, and bidders can contact the Department of Mobility and Infrastructure to arrange a viewing. The City emphasizes that alternative methods will only be considered after bid opening and is not obligated to accept alternative methods or value-engineered solutions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 0030 Page 1 of 1
SECTION 0030
DESCRIPTION OF WORK
REESE STREET CAISSON TREATMENT
19TH WARD � CITY OF PITTSBURGH, ALLEGHENY COUNTY, PENNSYLVANIA
This work consists of limited mine grouting, installation of a closely-spaced reinforced concrete caisson slope treatment, and limited rock scaling on the northern slope of Mount Washington, just north of 107 Reese Street, Pittsburgh, PA 15211.
The existing earthen slope below (north of) the two existing caisson retaining structures, adjacent the Tower base and incorporated building, is sliding. To mitigate the risk of a larger earth slide that might impact the Emerald View Park trail and the railroad tracks far below the trail, the City seeks to stabilize the hillside with a retaining structure. Selective and restricted mine grouting will be required prior to installation of the caissons in order to prevent collapse of the mine opening immediately beneath the caissons installation location.
The work will generally include the following tasks; some necessary tasks may be omitted from this list:
Design and implementation of a traffic control plan.
Construction surveying.
Installation of Limit of Disturbance (LOD) work area boundary stakes.
Installation of inlet filter bags, erosion and sediment controls and rock construction entrance.
Limited tree removal to allow access to the work.
General site preparations for caisson installation including excavation of a temporary bench for the caisson drill rig and/or installation of temporary excavation support and protection system, as needed for the work.
Selective and restricted grouting of the mined-out Pittsburgh Coal seam beneath the caisson location including post-grout verification holes with video records.
Installation of closely spaced caisson retaining structure.
Backfill of the temporary excavation bench and/or removal of the temporary excavation support and protection system as installed for the work.
Regrading of the slope within the project extents.
Installation of rock shielding and selective rock scaling of the several small rock outcrops downslope of the caisson retaining structure. Removal and disposal of the scaled rocks.
Removal of any traffic control measures.
Removal of E&S Controls and restoration of the site.
ALL WORK IS TO OCCUR IN ACCORDANCE WITH THE CONTRACT DRAWINGS
AND SPECIFICATIONS.
ALTERNATIVE METHODS WILL ONLY BE CONSIDERED AFTER THE BID
OPENING. THE CITY OF PITTSBURGH IS NOT OBLIGATED TO ACCEPT
ALTERNATIVE METHODS OR VALUE ENGINEERED SOLUTIONS.
END OF DESCRIPTION OF WORK
Section 0040 Page 1 of 1
SECTION 0040
DEPARTMENT REFERENCES
REESE STREET CAISSON TREATMENT
19TH WARD � CITY OF PITTSBURGH, ALLEGHENY COUNTY, PENNSYLVANIA
Where "Department" is referenced in the Special Provisions, Specifications, Plans or other
Contract documents, unless specifically noted otherwise, the intent of this Project is to reference the Department of Mobility and Infrastructure, City of Pittsburgh.
END OF DEPARTMENT REFERENCES
Section 0050 Page 1 of 1
SECTION 0050
NOISE RESTRICTION
Except as permitted explicitly by the City, restrict noise-producing work to Monday-Saturday, 7a.m. to 8 p.m. and do not work on Sunday�s or City observed Holidays including:
New Year's Day
Martin Luther King's Birthday
Good Friday
Memorial Day
Juneteenth
Independence Day
Labor Day
Veterans' Day
Thanksgiving Day
The day after Thanksgiving Day
Christmas Day
When a holiday falls on a Saturday, observe the Holiday on the preceding Friday. When a holiday falls on a Sunday, observe the Holiday on the following Monday.
END OF NOISE RESTRICTION
Section 0060 Page 1 of 1
SECTION 0060
ADDITIONAL INFORMATION AVAILABLE
Additional Information Made Available to the Bidder (‘User’) by the Department.
Information, data, files, or samples (‘Information’) made available to the User during the advertisement period is provided in accordance with Publication 408 Section 102 and is provided
“AS IS.” The Department makes no warranty or representation, either express or implied, with respect to the quality, accuracy, performance, merchantability or fitness of the Information for a particular purpose. The opinions expressed in the Information may not be those of the
Department. The Department cannot guarantee that the Information provided is in accordance with the Department’s and City’s standards. The User assumes the entire risk as to the quality of the Information and the Department shall not be responsible or liable for any damages, caused, in whole or in part, by use of the Information. The User shall immediately notify the Department in the event that it discovers that the Information contains vague, ambiguous, or contradictory information via the Bid system Questions and Answers function.
The Information is not a substitute for the sound engineering judgment of the User. The User shall indemnify and hold harmless the Department, its officials, and employees for any injury to the person or property of third parties arising out of the use of or any defect in the Information.
In addition to the “Info_Only-“ attachments to the Solicitation, the following Information is available:
• Subsurface Boring sample Core Boxes: Sample material core boxes are available for inspection at in Pittsburgh. Contact Mr. Tom Samstag at the Department of Mobility and Infrastructure 412.915.7312 to arrange for a date and time to inspect the core boxes.
END OF ADDITIONAL INFORMATION AVAILABLE
Section 0106 Page 1 of 1
SECTION 0106
CONTROL OF MATERIAL
In accordance with Section 0106 and as follows:
106.03(b)1 Responsibility.
Add the following to the first paragraph:
The following table identifies some of the materials for the Project and the party(ies) responsible for sampling and testing, or certification. Provide Testing and/or Certification of materials not identified here according to the 408 or Controlling PennDOT criteria.
Item/Section and
Material
Quality Control
Testing by
Contractor
Acceptance
Testing by
Owner/Owner�s
Representative
Manufacturer�s or
Supplier�s
Certification
Aggregate X
- Coarse X
- Subbase X X
Cast-In-Place Concrete X X X
Grout X X X
Reinforcing Steel X
Plastic Pipe X
PVC Pipe X
Geotextile X
Seed and Soil Supplements *
* Certification by the Pennsylvania Department of Agriculture, Bureau of Plant Industry.
Include costs for tests and certifications in the bid price for the bid items on the Schedule of
Prices.
Provide a copy of each certification for each item requiring certification to the City�s representative at the time of material delivery to the site, and one (1) copy of each certification for each item to the Owner�s Engineer for approval at least 2 weeks prior to delivery of material to the site.
END OF SPECIAL PROVISION
Section 0703 Page 1 of 1
SECTION 0703
AGGREGATE
In accordance with Section 0703 and as follows:
703.1(a) 2. Manufactured Sand.
Delete section
703.1(b) Production Testing.
Delete section
703.2(a) 3. Blast Furnace Slag.
Delete section
703.2(a)4. Steel Slag.
Delete section
703.2(a)5. Granulated Slag.
Delete section
703.2(b). Production Testing.
Delete section
703.2(c) 1. Soundness.
Delete the following sentence:
�The LTS may accept aggregate failing the test if it can be demonstrated in writing the aggregate has a satisfactory service record in both pavements and structures�
703.3(a). General.
Delete the following words in the first sentence:
�or slag�
END OF SPECIAL PROVISION
| 0030 - Description of Work |
| 0040 - Department References |
| 0050 - Noise Restrictions |
| 0060 - Additional Informaton available |
| 0080 - Additional Insurance Requirements |
| 0106 - Control of Material |
| 0703 - Aggregates |
| 0080 - Additional Insurance Requirements |
| 0060 - Additional Informaton available |
File details come from the government source that posted it. Updated .