Info_Only-Reese_St_PrebidConstrSched.pdf

PDF 110 KB Posted

Attached to
Reese Street Caisson Treatment
Solicitation number
2023-IFB-219
Issued by
Allegheny County, Philadelphia City, Pennsylvania

About this file

The document is a detailed construction project schedule for the Reese Street Caisson Treatment project in Pittsburgh, Pennsylvania, developed by the City of Pittsburgh's Department of Mobility & Infrastructure. The project schedule spans from October 2023 to June 2024 and outlines a comprehensive timeline of key project phases including preconstruction activities, temporary excavation planning, mine grouting work, caisson installation, construction permits, site mobilization, environmental and safety measures, rock slope scaling, temporary embankment construction, and project closeout. The schedule includes specific tasks such as temporary excavation plan development, city reviews, MPT (Maintenance of Traffic) notices, site installation, grouting, caisson installation, slope reconstruction, and final landscaping and seeding.

The project schedule reveals a total project duration of approximately 9 months, with critical path activities carefully mapped out and interdependent tasks strategically sequenced. The schedule includes buffer periods for city reviews, potential delays, and specific milestones such as achieving 70% vegetation growth. The timeline indicates multiple concurrent and sequential activities, with precise start and end dates for each task, highlighting the complex nature of the infrastructure improvement project. The schedule demonstrates careful planning, including provisions for temporary works, environmental controls, and phased construction approaches typical of urban infrastructure rehabilitation projects.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line Unique Task ID Name Duration Total float Early start Late start Early finish Late finish Predecessors Successors

2023 2024 October November December January February March April MayS June

2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Anticipated Notice to Proceed

Preconstruction Submittals

Temporary Excavation Plan

Mine Grouting Work Plan

City Review Temp Excavation Plan

Caisson Installation Plan

City Review Mine Grouting Work Plan

City Review Caisson Installation Plan

Construction

Permits

MPT Notice

PA-I-Call

Mobilization to Site

Install MPT

Install E&S

Perform Rock Slope Scaling

Construct Temporary Embankment/Access

Perform Mine Grouting

QA mine grouting

Install Caissons

Reconstruct Slope

Temp Seed

Final Inspection and Punchlist

PLANNED HIATUS

Permanent Seed, Mulch, Landscape Planting

Achieve 70% growth

Remove E&S

Project Closeout

Project Completed

40d

15d

10d

10d

30d

10d

10d

102d

15d

10d

3d

1d

1d

3d

5d

15d

15d

5d

40d

5d

3d

5d

33d

5d

42d

1d

10d

148d

173d

14d

5d

14d

14d

14d

5d

12d

3d

81d

Mon 10/02/23

Mon 10/02/23

Mon 10/02/23

Mon 10/02/23

Mon 10/02/23

Mon 10/02/23

Mon 10/16/23

Mon 11/13/23

Mon 10/02/23

Mon 10/02/23

Mon 10/02/23

Mon 10/02/23

Mon 10/23/23

Mon 10/23/23

Tue 10/24/23

Tue 10/24/23

Fri 10/27/23

Fri 11/17/23

Fri 12/08/23

Fri 12/15/23

Fri 02/09/24

Fri 02/16/24

Wed 02/21/24

Wed 02/28/24

Mon 04/01/24

Mon 04/08/24

Wed 06/05/24

Thu 06/06/24

Thu 06/20/24

Mon 10/02/23

Mon 10/09/23

Thu 05/30/24

Fri 10/20/23

Mon 10/09/23

Fri 10/20/23

Fri 11/03/23

Fri 12/01/23

Mon 10/02/23

Mon 10/02/23

Mon 10/09/23

Wed 10/18/23

Mon 10/23/23

Thu 10/26/23

Tue 10/24/23

Wed 02/14/24

Fri 10/27/23

Fri 11/17/23

Fri 12/08/23

Fri 12/15/23

Fri 02/09/24

Fri 02/16/24

Wed 02/21/24

Wed 02/28/24

Mon 04/01/24

Mon 04/08/24

Wed 06/05/24

Thu 06/06/24

Thu 06/20/24

Mon 10/02/23

Fri 11/24/23

Fri 10/20/23

Fri 10/13/23

Fri 10/13/23

Fri 11/10/23

Fri 10/27/23

Fri 11/24/23

Tue 02/20/24

Fri 10/20/23

Fri 10/13/23

Wed 10/04/23

Mon 10/23/23

Mon 10/23/23

Thu 10/26/23

Mon 10/30/23

Thu 11/16/23

Thu 12/07/23

Thu 12/14/23

Thu 02/08/24

Thu 02/15/24

Tue 02/20/24

Tue 02/27/24

Sun 03/31/24

Fri 04/05/24

Tue 06/04/24

Wed 06/05/24

Wed 06/19/24

Thu 06/20/24

Mon 10/02/23

Wed 06/19/24

Wed 06/19/24

Thu 11/02/23

Fri 10/20/23

Thu 11/30/23

Thu 11/16/23

Thu 12/14/23

Tue 02/20/24

Fri 10/20/23

Fri 10/20/23

Fri 10/20/23

Mon 10/23/23

Thu 10/26/23

Thu 10/26/23

Tue 02/20/24

Thu 11/16/23

Thu 12/07/23

Thu 12/14/23

Thu 02/08/24

Thu 02/15/24

Tue 02/20/24

Tue 02/27/24

Sun 03/31/24

Fri 04/05/24

Tue 06/04/24

Wed 06/05/24

Wed 06/19/24

Thu 06/20/24

0011, 0042, 0043, 0370, 0041

0061, 0370, 0360

0062, 0031, 0350

0070, 0032, 0033, 0240, 0340

0073, 0260

0240, 0010

0290, 0280, 0250

0031, 0060, 0032, 0041, 0042, 0043, 0013, 0370

0070, 0350

0062, 0060

0320, 0033

0060, 0360

0061, 0340

0071, 0320

0240, 0010

0270, 0250

0300, 0260

0300, 0290

Symbols Free float Total float Critical Start On Finish On Start After

Milestone Appearances Diamond

File details come from the government source that posted it. Updated .