Info_Only-Reese_St_PrebidConstrSched.pdf
PDF 110 KB Posted
- Attached to
- Reese Street Caisson Treatment
- Solicitation number
- 2023-IFB-219
- Issued by
- Allegheny County, Philadelphia City, Pennsylvania
About this file
The document is a detailed construction project schedule for the Reese Street Caisson Treatment project in Pittsburgh, Pennsylvania, developed by the City of Pittsburgh's Department of Mobility & Infrastructure. The project schedule spans from October 2023 to June 2024 and outlines a comprehensive timeline of key project phases including preconstruction activities, temporary excavation planning, mine grouting work, caisson installation, construction permits, site mobilization, environmental and safety measures, rock slope scaling, temporary embankment construction, and project closeout. The schedule includes specific tasks such as temporary excavation plan development, city reviews, MPT (Maintenance of Traffic) notices, site installation, grouting, caisson installation, slope reconstruction, and final landscaping and seeding.
The project schedule reveals a total project duration of approximately 9 months, with critical path activities carefully mapped out and interdependent tasks strategically sequenced. The schedule includes buffer periods for city reviews, potential delays, and specific milestones such as achieving 70% vegetation growth. The timeline indicates multiple concurrent and sequential activities, with precise start and end dates for each task, highlighting the complex nature of the infrastructure improvement project. The schedule demonstrates careful planning, including provisions for temporary works, environmental controls, and phased construction approaches typical of urban infrastructure rehabilitation projects.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Line Unique Task ID Name Duration Total float Early start Late start Early finish Late finish Predecessors Successors
2023 2024 October November December January February March April MayS June
2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Anticipated Notice to Proceed
Preconstruction Submittals
Temporary Excavation Plan
Mine Grouting Work Plan
City Review Temp Excavation Plan
Caisson Installation Plan
City Review Mine Grouting Work Plan
City Review Caisson Installation Plan
Construction
Permits
MPT Notice
PA-I-Call
Mobilization to Site
Install MPT
Install E&S
Perform Rock Slope Scaling
Construct Temporary Embankment/Access
Perform Mine Grouting
QA mine grouting
Install Caissons
Reconstruct Slope
Temp Seed
Final Inspection and Punchlist
PLANNED HIATUS
Permanent Seed, Mulch, Landscape Planting
Achieve 70% growth
Remove E&S
Project Closeout
Project Completed
40d
15d
10d
10d
30d
10d
10d
102d
15d
10d
3d
1d
1d
3d
5d
15d
15d
5d
40d
5d
3d
5d
33d
5d
42d
1d
10d
148d
173d
14d
5d
14d
14d
14d
5d
12d
3d
81d
Mon 10/02/23
Mon 10/02/23
Mon 10/02/23
Mon 10/02/23
Mon 10/02/23
Mon 10/02/23
Mon 10/16/23
Mon 11/13/23
Mon 10/02/23
Mon 10/02/23
Mon 10/02/23
Mon 10/02/23
Mon 10/23/23
Mon 10/23/23
Tue 10/24/23
Tue 10/24/23
Fri 10/27/23
Fri 11/17/23
Fri 12/08/23
Fri 12/15/23
Fri 02/09/24
Fri 02/16/24
Wed 02/21/24
Wed 02/28/24
Mon 04/01/24
Mon 04/08/24
Wed 06/05/24
Thu 06/06/24
Thu 06/20/24
Mon 10/02/23
Mon 10/09/23
Thu 05/30/24
Fri 10/20/23
Mon 10/09/23
Fri 10/20/23
Fri 11/03/23
Fri 12/01/23
Mon 10/02/23
Mon 10/02/23
Mon 10/09/23
Wed 10/18/23
Mon 10/23/23
Thu 10/26/23
Tue 10/24/23
Wed 02/14/24
Fri 10/27/23
Fri 11/17/23
Fri 12/08/23
Fri 12/15/23
Fri 02/09/24
Fri 02/16/24
Wed 02/21/24
Wed 02/28/24
Mon 04/01/24
Mon 04/08/24
Wed 06/05/24
Thu 06/06/24
Thu 06/20/24
Mon 10/02/23
Fri 11/24/23
Fri 10/20/23
Fri 10/13/23
Fri 10/13/23
Fri 11/10/23
Fri 10/27/23
Fri 11/24/23
Tue 02/20/24
Fri 10/20/23
Fri 10/13/23
Wed 10/04/23
Mon 10/23/23
Mon 10/23/23
Thu 10/26/23
Mon 10/30/23
Thu 11/16/23
Thu 12/07/23
Thu 12/14/23
Thu 02/08/24
Thu 02/15/24
Tue 02/20/24
Tue 02/27/24
Sun 03/31/24
Fri 04/05/24
Tue 06/04/24
Wed 06/05/24
Wed 06/19/24
Thu 06/20/24
Mon 10/02/23
Wed 06/19/24
Wed 06/19/24
Thu 11/02/23
Fri 10/20/23
Thu 11/30/23
Thu 11/16/23
Thu 12/14/23
Tue 02/20/24
Fri 10/20/23
Fri 10/20/23
Fri 10/20/23
Mon 10/23/23
Thu 10/26/23
Thu 10/26/23
Tue 02/20/24
Thu 11/16/23
Thu 12/07/23
Thu 12/14/23
Thu 02/08/24
Thu 02/15/24
Tue 02/20/24
Tue 02/27/24
Sun 03/31/24
Fri 04/05/24
Tue 06/04/24
Wed 06/05/24
Wed 06/19/24
Thu 06/20/24
0011, 0042, 0043, 0370, 0041
0061, 0370, 0360
0062, 0031, 0350
0070, 0032, 0033, 0240, 0340
0073, 0260
0240, 0010
0290, 0280, 0250
0031, 0060, 0032, 0041, 0042, 0043, 0013, 0370
0070, 0350
0062, 0060
0320, 0033
0060, 0360
0061, 0340
0071, 0320
0240, 0010
0270, 0250
0300, 0260
0300, 0290
Symbols Free float Total float Critical Start On Finish On Start After