Performance Based Payment Schedule Transition_In.pdf

PDF 91 KB Posted

Attached to
DHA Enterprise Referral Care Coordination Center Contract (RC3)
Solicitation number
RC3_20261030
Issued by

About this file

This document outlines the Transition-In Milestone Payment Schedule for a Defense Health Agency (DHA) contract involving the implementation of a unified enterprise RC3 (referral, consultation, and coordination) scheduling solution across Military Health System (MHS) facilities worldwide.

The contract contains six sequential gates with cumulative completion requirements and associated payment milestones totaling the Transition CLIN price: Gate 1 (Admin Tasks) due no later than 30 calendar days after contract award at 15% of total transition pricing; Gate 2 (Logistics and Emergency Planning Validation) due no later than 60 days after award at 15%; Gate 3 (Wave 1 Operational Readiness) prior to Wave 1 start at 20%; Gate 4 (Wave 2 Transition and Initial Operating Capability Declaration) at Wave 2 midpoint at 20%; Gate 5 (Clinical Systems Integration Demo) 15 days before Final Operating Capability at 15%; and Gate 6 (Final Operating Capability Tasks) 5 days before full performance start date at 15%. Specific deliverables include submission of transition-in plans, DHA Business Associate Agreements, security background investigation paperwork, continuity of operations and disaster recovery plans, personnel credentialing rosters, quality control and emergency preparedness plans, mandatory HIPAA and cybersecurity training completion, successful issuance of Common Access Cards (CACs) to key personnel, verification of Electronic Health Record (EHR) access, completion of skills verification and EHR simulation dry-runs, live validation of telephony and webchat systems, PowerBI dashboard demonstrations, and formal government acceptance of operational capability. Each gate has interdependent requirements and must be completed before the subsequent milestone payment is released.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sub-Task:

1 Submit Transition-In Plan within 10 DACA.

2 Submit signed DHA Business Associate Agreement (BAA) within 10 DACA.

3 Submit 100% of Wave 1 Security background investigation paperwork within 5 DACA.

4 Complete initial Quality Control Plan (QCP) and Emergency Preparedness Plan (EPP).

5 Complete mandatory HIPAA, Cyber Awareness, And AUP Training

Sub-Task:

2 Submit the Continuity of Operations Plan (COOP) and Disaster Recovery Plan (DRP).

3 Submit B2B Gateway Questionnaire and IT Infrastructure/Interface Design documentations.

Sub-Task:

1 100% of Wave 1 Contractor Key Personnel and staff have been issued CACs.

2 95% of Wave 1 Contractor appointing/referral staff have active, verified access to EHR.

Sub-Task:

Sub-Task:

Sub-Task:

Transition-In Milestone Payments

Gate 1: Admin Tasks NLT 30 calendar Days After Contract Award (DACA) (15% of Total Transition CLIN Price)

Milestone Payment Schedule/Description and associated sub-tasks:

Gate 2: Logistics and Emergency Planning Validation NLT 60 DACA + Must complete Gate 1 (15% of Total Transition CLIN Price)

Deliver the Personnel Location and Credentialing Roster mapping all contract staff to their residential locations and closest DMDC/IDCO RAPIDS sites and MTF.

Gate 6: Final Operating Capability (FOC) Tasks 5 Days before Full Performance Start Date + Must complete Gate 5 (15% of Total Transition CLIN Price)

Gate 5: Clinical Systems Integration Demo Gate Tasks: 15 Days before Final Operating Capability (FOC) + Must complete Gate 4 (15% of Total Transition CLIN Price)

Gate 3: Wave 1 Operational Readiness Gate Tasks (Prior to Wave 1 Start) + Must complete Gate 2 (20% of Total Transition CLIN Price)

Gate 4: Wave 2 Transition and Initial Operating Capability (IOC) Declaration (Wave 2 Midpoint) + Must complete Gate 3 (20% of Total Transition CLIN Price)

Demonstrate that referral processing backlogs are within acceptable limits.

Verify the ability of the system to successfully capture, document, and route patient encounter logs back into MHS GENESIS.

Successfully transition Wave 1 and Wave 2 designated MTFs.

Ingest and document local MTF clinic Business Rules and SOPs.

Successfully complete skills verification and EHR simulation dry-runs.

Real-world live validation of telephony, webchat, and EHR routing pipelines without any degradation to beneficiary Access to Care (ATC) Formal Government acceptance of FOC.

Telephonic Scheduling Average Speed of Answer (ASA) and Live Chat response times meet or exceed PWS Part 5 standards.

Government formally declares IOC.

Successful transition of 100% of scheduled DHA MTFs worldwide into the unified enterprise RC3 solution.

Demonstrate active PowerBI Status Dashboard displaying real-time operational metrics with a data lag of less than 24 hours.

Conduct a live demonstration verifying that electronic and telephonic scheduling systems are fully operational.

Milestones