Solicitation No. R17PS00430

View the file

Other files

File Type Posted
R17PS00430_Amendment_0003.pdf PDF
Shadehill_Amendment_2.pdf PDF
Amendment_No._0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior Bureau of Reclamation Great Plains Regional Office March 2017 2021 4th Avenue North Billings, Montana 59101

SOLICITATION No. R17PS00430

Shadehill Dam Service Spillway Stilling Basin Concrete Repairs

Request for Proposal Firm Fixed Price Total Small Business Set Aside

Pick-Sloan Missouri River Basin Program South Dakota

This Page Intentionally Left Blank

SHADEHILL DAM SERVICE SPILLWAY

STILLING BASIN CONCRETE REPAIRS

MISSOURI RIVER BASIN PROJECT

GRAND DIVISION, SHADEHILL UNIT

SOUTH DAKOTA

FOREWORD

The principal components of work to be performed include the following:

1. Construct temporary cofferdam in the Grand River below Shadehill Dam. Unwater and remove fish from area between cofferdam and stilling basin Sta. 7+94.00. Maintain unwatered area to perform concrete repair work in dry conditions.

2. Prepare surface of existing concrete stilling basin between Sta. 7+94 and 8+62 for new concrete overlay.

3. Partial demolition of seven existing concrete chute blocks at Sta. 8+02.

4. Partial demolition of six existing concrete floor blocks at Sta. 8+34.

5. Construct new reinforced silica-fume concrete stilling basin floor overlay.

6. Construct new reinforced silica-fume concrete chute and floor block overlays.

7. Remove temporary cofferdam at conclusion of work.

The work under this solicitation/specifications is located at Shadehill Dam approximately 12 miles south and 3 miles west of Lemmon, South Dakota in Perkins County.

Concrete repairs to the stilling basin shall occur between August 1 and October 31, 2017. During this period, Reclamation will make water releases down the Grand River through the bypass channel approximately 215 feet to the right of the stilling basin. After the concrete repairs have been made, water releases from the Shadehill Dam will be returned to the stilling basin.

POINT OF CONTACT:

The point of contact is Contract Specialist Darlene Dillon. All questions and correspondence concerning this solicitation shall be directed to her via email at ddillon@usbr.gov. Phone calls will not be accepted to ensure all communication will be properly documented for record purposes.

PROPOSAL CLOSING DATE:

See Section “A”: “SOLICITATION, OFFER, AND AWARD, STANDARD FORM 1442” immediately following the “TABLE OF CONTENTS”

METHOD OF SUBMISSION OF PROPOSALS

See Section L of this Solicitation

TYPE OF CONTRACT:

This requirement is solicited as a “Request for Proposal” (RFP) using the Federal Acquisition Regulation Sub Part 15, Contract by Negotiation Procedures. Results from this solicitation will be an anticipated award of a Firm Fixed Price Contract.

COMPETITION REQUIREMENTS:

This acquisition is restricted to Total Small Businesses.

mailto:ddillon@usbr.gov

RECLAMATION SAFETY AND HEALTH STANDARDS (2014 EDITION):

For information regarding the Bureau of Reclamation’s publication “RECLAMATION SAFETY AND HEALTH STANDARDS” (2014 Edition): http://www.usbr.gov/ssle/safety/RSHS/rshs.html) which is applicable to work under this contract. See Clause “WBR 1452.223-81 SAFETY AND HEALTH.

PRE-PROPOSAL SITE VISIT:

A pre-proposal site visit will be held March 30, 2017 at 10:30 AM, (Shadehill, SD Timezone), by meeting at the Shadehill Dam Maintenance Shop. Prospective Offerors should make arrangements by contacting Mr. Scott Jacobson at Telephone Number (701)221-1215 or Mr. George Finnegan at Telephone Number (605)394-9757 X3002. Attendees are to provide and wear safety boots, hard hats and safety vests.

SAM: Effective July 29, 2012, any contractor interested in doing business with the Government must register in the system for award management (SAM) database prior to award of a contract or agreement.

SAM is a Federal Government owned and operated FREE website that consolidates the Central Contractor Registration (CCR), the Online Representations and Certifications Application (ORCA), and the excluded parties list system (EPLS). The vendor’s DUNS and Bradstreet number and banking information are required for registration. Contractors may obtain information on registration and annual confirmation requirements via the SAM website at https://www.sam.gov/portal/public/sam or by the Federal Service Desk at telephone number 1-866-606-8220.

PAYMENTS: Payment requests for the anticipated contract must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform (IPP) System. The IPP website is https://www.ipp.gov. The contractor must use the IPP website to register, access, and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP production helpdesk via email at ippgroup@bos.frb.org or at telephone number 1-866-973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the contracting officer with their proposal.

http://www.usbr.gov/ssle/safety/RSHS/rshs.html https://www.sam.gov/portal/public/sam https://www.ipp.gov/ mailto:ippgroup@bos.frb.org

TOC - 1

TABLE OF CONTENTS

DIVISION 01 - General Requirements 01 11 00 Summary of Work 01 14 10 Use of Site 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 20 Existing Fences 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 - Existing Conditions Not Used

DIVISION 03 - Concrete 03 11 10 Concrete Forming 03 20 00 Concrete Reinforcing 03 20 30 Epoxy Grouted Rebar Dowels 03 30 00 Cast-In-Place Concrete 03 81 10 Concrete Removal

DIVISION 04 THROUGH DIVISION 30

Not Used

DIVISION 31 - Earthwork 31 02 10 Water for Dust Abatement 31 03 10 Diversion & Care of Stream During Const.

31 11 00 Clearing and Grubbing 31 14 10 Stripping

TOC - 2

31 23 39 Disposal of Materials 31 24 10 Embankment, General

DIVISION 32 - Exterior Improvements 32 92 20 Seeding and Soil Supplements

DIVISION 33 THROUGH DIVISION 50

Not Used

DIVISION 51 – Information Available to Offerors 51 00 00 Information Available to Offerors

DIVISION 52 - Drawings 52 00 00 Drawings

DIVISION 53

Not Used

SECTION D – Packaging and Marketing Not Used

SECTION E – Inspection and Acceptance

E.1 Material and Workmanship E.2 Inspection of Construction E.3 Warranty of Construction

SECTION F – Deliveries or Performance F.1 Commencement, Prosecution, and Completion of Work

F.2 Variation in Estimated Quantity F.3 Suspension of Work

SECTION G – Contract Administration Data G.1 Authorities and Delegations G.2 Electronic Invoicing and Payment Requirements G.3 Contractor Performance Assessment Reporting System

SECTION H – Special Contract Requirements H.1 Site Security

PART II – CONTRACT CLAUSES

SECTION I – Contract Clauses I.1 Clauses by Reference I.2 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality

Agreements I.3 Commercial and Government Entity Code Maintenance

TOC - 3

I.4 Order of Precedent – Uniform Contract Format I.5 Minimum Wages Under Executive Order 13658 I.6 Paid Sick Leave Under Executive Order 13706 I.7 Estimate of Percentage of Recovered Material Content for EPA Designated Items I.8 Buy American – Construction Materials I.9 Bid Guarantee I.10 Additional Bond Security I.11 Performance and Payment Bonds – Construction I.12 Payments Under Fixed Price Construction Contracts I.13 Prompt Payment for Construction Contracts I.14 Differing Site Conditions I.15 Accident Prevention I.16 Schedules for Construction Contracts I.17 Specifications and Drawings for Construction Alt II I.18 Changes I.19 Authorized Deviations in Clauses I.20 Restrictions on Endorsements-Department of the Interior I.21 Release of Claims –Department of the Interior I.22 Examination of Records by the Department of the Interior I.23 Liability Insurance – Department of the Interior I.24 Asbestos – Free Warranty I.25 Safety and Health – Bureau of Reclamation I.26 Protecting Federal Employees and the Public From Exposure to Tobacco Smoke in the

Federal Workplace –Bureau of Reclamation I.27 Certification of Representatives for Corporate Sureties – Bureau of Reclamation I.28 Equipment Ownership and Operating Expense – Bureau of Reclamation I.29 Payment for Mobilization and Preparatory Work I.30 Claims Accounting – Bureau of Reclamation I.31 Other Contracts (APR) 1984 (Deviation) I.32 Preservation of Cultural Resources – Bureau of Reclamation I.33 Security Requirements – Bureau of Reclamation Alt III I.34 Modification Proposals – Alternate III-Bureau of Reclamation

PART III – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J – Documents, Exhibits and Other Attachments General Decision Numbers: SD170001 Standard Form 24 - Bid Bond Company Experience Reference List Past Performance Questionnaire Subcontracting Percentage Worksheet

TOC - 4

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K – Representations, Certifications and Other Statements of Offerors K.1 Prohibition on Contracting With Entities That Require Certain Internal Confidentiality Agreements-Representation K.2 Annual Representations and Certifications

SECTION L – Instructions, Conditions and Notices to Bidders L.1 System for Award Management L.2 Commercial and Government Entity Code Reporting L.3 Submission of Offers in the English Language L.4 Submission of Offers in U.S. Currency L.5 Instructions to Offerors—Competitive Acquisition L.6 Type of Contract L.7 Construction Wage Rate Requirements—Secondary Site of the Work L.8 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity For Construction L.9 Notice of Buy American Requirement—Construction Materials L.10 Site Visit (Construction) – Alternate I L.11 Preparation of Proposals—Construction L.12 Authorized Deviations in Provisions L.13 Use and Disclosure of Proposal Information—Department of the Interior L.14 Service of Protest –Department of the Interior (July 1996)(Deviation) L.15 Notice of Intent to Acquire Metric Products and Services—Bureau of Reclamation L.16 Source Evaluation and Selection Procedures---Bureau of Reclamation L.17 General Proposal Instructions – Bureau of Reclamation L.18 Technical Proposal Instructions—Bureau of Reclamation L.19 Pricing Proposal Instructions –Bureau of Reclamation L.20 Notice of Proposed Partnering –Bureau of Reclamation L.21 Instruction for Mobilization and Preparatory Work Schedule Line Item L.22 Authorized Workers Notice to Potential Bureau of Reclamation Contractors

SECTION M – Evaluation Factors for Award M.1 Evaluation Factors for Award – Quality Predominance—Bureau of Reclamation M.2 Notice of World Trade Organization Government Procurement Agreement Evaluations—Bureau of Reclamation

END OF CONTENTS

PART I – THE SCHEDULE

iii

This page intentionally left blank.

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040310849

Bureau of Reclamation

Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

Darlene Dillon 406-247-7820

1x 03/16/2017

R17PS00430

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

YES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

calendar days and complete it within 10 150 calendar days after receiving

12b. CALENDAR DAYS

04/18/2017

NSN 7540-01-155-3212

x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time

120 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected .

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

Shadehill Dam Service Spillway Stilling Basin Concrete Repairs, Missouri River Basin Project Grand Division, Shadehill Unit South Dakota

The estimated price range is between $250,000 and $500,000

The North American Industry Classification System (NAICS) code is 237990.

The Small Business Size Standard for NAICS 237990 is $36.5 Million.

Taxpayer Identification Number (TIN): _______________________________________________

Data Universal Number System (DUNS) ______________________________________________

Commercial and Government Entity Code: ____________________________________________ x Paragraph F.1 x x

Bureau of Reclamation Great Plains Region Regional Office 2021 4th Avenue North Billings, MT 59101

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

Gerri Voto-Braun

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

R17PS00430

00010

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

SECTION B Supplies or Services and Prices FOB: Destination

Shadehill Dam Spillway Stilling Basin Concrete Repair (Price Schedule CLINS 1 through 7).

See following continuation pages.

1 AU $_________________

SECTION B -PRICE SCHEDULE

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

B-1

CONTINUATION OF

SECTION B –PRICE SCHEDULE

SHADEHILL DAM SERVICE SPILLWAY

STILLING BASIN CONCRETE REPAIRS

MISSOURI RIVER BASIN PROJECT

GRAND DIVISION, SHADEHILL UNIT

SOUTH DAKOTA

B.1 PRICE SCHEDULE

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(d) Definitions:

(1) CLIN – Contract Line Item Number

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232

-81

Mobilization and Preparatory Work

For the lump sum of $

2 03 30 00 Construct Reinforced Silica- Fume Concrete Overlay

110 yd3 yd3 $

3 03 30 00 Construct Reinforced Silica- Fume Concrete Chute and Floor Block Overlays

26 yd3 yd3 $

4 03 81 10 Concrete Removal For the lump sum of $

6 31 03 10 Diversion and Care of Stream During Construction

For the lump sum of $

B-2

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

7 32 92 20 Seeding and Soil Supplements

5 acres acres $

TOTAL FOR PRICE SCHEDULE $

END OF PRICE SCHEDULE

SECTION C

THE SPECIFICATIONS

Summary of Work 01 00 00-1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 LOCATION

1.2 The work is located at Shadehill Dam approximately 12 miles south and 3 miles west of Lemmon, South Dakota in Perkins County.

1.3 PRINCIPAL COMPONENTS OF WORK

A. The principal components of work include the following:

1. Construct temporary cofferdam in the Grand River below Shadehill Dam.

Unwater and remove fish from area between cofferdam and stilling basin Sta.

7+94.00. Maintain unwatered area to perform concrete repair work in dry conditions.

2. Prepare surface of existing concrete stilling basin between Sta. 7+94 and 8+62 for new concrete overlay.

3. Partial demolition of seven existing concrete chute blocks at Sta. 8+02.

4. Partial demolition of six existing concrete floor blocks at Sta. 8+34.

5. Construct new reinforced silica-fume concrete stilling basin floor overlay.

6. Construct new reinforced silica-fume concrete chute and floor block overlays.

7. Remove temporary cofferdam at conclusion of work.

1.4 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.5 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

Summary of Work 01 00 00-2

1.6 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Use of Site 01 14 10-1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.1 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.2 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Cleaning Manual-2012 Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at: http://www.usbr.gov/mussels/prevention

1.3 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences.

b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work http://www.usbr.gov/mussels/prevention

Use of Site 01 14 10-2 required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

1.4 PROJECT CONDITIONS

A. Government land as shown in Appendix A may be used for required construction facilities.

B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.

D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.

3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.

Use of Site 01 14 10-3

3.2 RESTORATION

A. Restore Contractor use areas to pre-construction condition.

B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.

C. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

D. Seed disturbed areas of Government land used for construction purposes and not required for completed installation in accordance with Section 32 92 20 - Seeding and Soil Supplements.

Submittals 01 33 00 - 1

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.1 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.2 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-2011 United States National CAD Standards, Version 5

1.3 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittal Types, as listed in Table 01 33 00A – List of Submittals:

1. A – Action:

a. Government will respond as to adequacy of submittal.

b. Action submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.

2. I – Informational:

a. The Government will acknowledge receipt of Informational submittals.

b. The Government may reject an Informational submittal when the submittal does not comply with the contract. The Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.

c. Informational submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by the Government is not required.

01 33 00 - 2

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

1.4 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement units: US Customary Units.

C. Drawings:

1. Minimum identification in title block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Print Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Government Format drawings:

a. Prepare drawings designated as “Government Format” in the specifications as follows:

1) Title block and sheet format:

a) As shown on Drawing 40-D-7102.

b) Government will provide specific title block information to be used.

2) Drawing format:

a) AUTOCAD, Version 2007 or later.

b) In accordance with NIBS NCS.

3) Size: D-size (22-inch by 34-inch) as defined by ASME Y14.1.

4) Government will provide an electronic AutoCAD template.

6. Final drawings:

a. Drawing format: AUTOCAD, Version 2007 or later.

01 33 00 - 3

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

b. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

c. Electronic files: On CD or DVD discs.

d. Original plots: D size (22 inches by 34 inches).

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter except yellow is permitted).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

1.5 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

01 33 00 - 4

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.

G. Electronic submittals shall be submitted in Portable Document Format (PDF).

1.6 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 14 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

01 33 00 - 5

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

C. Return of Submittals:

1. Action Submittals: One set of submittals required for action will be returned either approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.

2. Informational Submittals: The Government will acknowledge Informational submittals.

a. Informational submittals will not be returned when they comply with the specifications.

b. Informational submittals that do not comply with the specifications may be returned for resubmittal or additional information may be requested.

1.7 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Contracting Officer, Bureau of Reclamation, Attention: GP-5000 (Birkland), P.O.

Box 36900, Billings, MT 59107.

2. Contracting Officer’s Representative, Bureau of Reclamation, Attention: DK- 4100 (Jacobson), P.O. Box 1017, Bismarck, ND 58502.

3. Technical Service Center, Bureau of Reclamation, Attn: 86-68530, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Denver Federal Center, Building 56, Room 1430.

B. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A – List of Submittals.

C. Send copy of transmittal letter with appropriate number of sets to offices that are not the responsible code, but show “No. of sets to be sent to” in Table 01 33 00A – List of Submittals.

D. When “No. of sets to be sent to” is 0, send a copy of transmittal letter to that office.

E. Submittals required by the specifications, but not listed in Table 01 33 00A - List of Submittals:

1. Submit in accordance with this section.

2. Submit to Contracting Officer’s Representative, Bureau of Reclamation, Attention: DK-4100 (Jacobson), P.O. Box 1017, Bismarck, ND 58502, unless otherwise specified.

01 33 00 - 6

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 33 00 - 7

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

Table 01 33 00A. - List of Submittals

* Submittal types: A – Action, I – Information ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative and TSC indicates Technical Service Center

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO COR TSC

1 Bonds 52.228- 15 & 52.228-

Performance and Payment Bonds

Revised Bonds (Additional Bond Security)

Within 10 calendar days after award

Within 10 calendar days after execution of any modification that increases contract value

A CO 1

3 Equal Opportunity 52.222-26

Information required by Executive Order

112246 (SF-100)

Within 30 days following award

A CO 1 0 0

4 Insurance-work on a Government Installation 52.228-05

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

At least 10 days prior to arriving at worksite

A CO 1

5 Liability Insurance 1452-228-70

Acceptable Certificate of Liability Insurance

At least 10 days prior to arriving at worksite

A CO 1 0 0

6 Security Requirements

GP-7 & WBR

1452.237-80

List of contractor and subcontractor employees with photo identification

At least 10 days prior to arriving at worksite

A COR 0 2 0

7 Security Requirements

GP-7 & WBR

1452.237-80

List of vehicles and equipment to be brought onsite

At least 10 days prior to arriving at worksite

A COR 0 2 0

8 Labor Standards Data 52.222-

1) List of Subcontractors

2) Statement and acknowledgement Form (SF-1413) for each subcontract

Within 14 days after award of contract/subcontract

A

A

COR

COR

1 paper + 1 electronic

1 paper + 1 electronic

9 Payrolls 52.222-08

Copies of all payrolls

Weekly for each week of onsite contract performance

A COR 1 2 0

Bonds 52.228- 15 & 52.228-02

01 33 00 - 8

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO COR TSC

10 Schedules for Construction Contracts 52.236-15

Practicable schedule:

Blackline prints

Within 7 days after work commences on the contract or another period of time as determined by the COR

A COR 0 2 0

11 Schedules for Construction Contracts 52.236-15

Annotated schedule showing actual progress:

Blackline prints

Monthly or as directed by the CO

A COR 0 2 0

12 Schedules for Construction Contracts 52.236-15

Supplementary schedule or schedules:

Blackline prints

As deemed necessary by the CO.

A COR 0 2 0

13 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10

Certification that executive compensation and subcontract awards were reported

Within 10 days of each report being submitted

A CO 1 0 0

14 Recovered Material Content 52.223-09

Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of postconsumer material content

After completion of the work and prior to final payment

A CO 1 0 0

15 Release of Claims 1452.204-70

Release of Claims (DI-137) against the Government

After completion of the work and prior to final payment

A CO 1 0 0

01 14 10-1 Use of Site Land Use And Landscape Rehabilitation Plan

At least 14 days before use of Government land

A COR 0 1 0

01 35 10-1 Safety Data Sheets

Complete LHM and

SDS

At least 14 days before jobsite delivery of hazardous material

I COR 0 1 0

01 35 10-2 Safety Data Sheets

Updated LHM and

SDS

At least 14 days before jobsite delivery of hazardous material not previously listed

I COR 0 1 0

01 33 00 - 9

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO COR TSC

01 35 20-1 Safety and Health

Resumes Submitted and approved before commencing onsite work

A COR 0 1 0

01 35 20-2 Safety and Health

Safety Program Submitted and approved before commencing onsite work

A COR 0 2 0

01 35 20-3 Safety and Health

Certificates Submitted and approved before commencing onsite work

A COR 0 2 0

01 35 20-4 Safety and Health

Monthly Reports First day of each month I COR 0 2 0

01 46 20-1 Testing Agency Services

Testing Agency Services Plan

At the time of preconstruction conference

A COR 0 2 1

01 46 20-2 Testing Agency Services

Contractor Quality Testing Results

Within 3 days of tests I COR 0 2 1

01 55 20-1 Traffic Control Traffic Control Plan At least 28 days before affecting public traffic.

A COR 0 2 0

01 56 10-1 Protection of Existing Installations

Plan for Protecting Existing Installations

At least 14 days before starting onsite work

A COR 0 2 0

01 57 30-1 Water Pollution Control

Water Management Plan

At least 28 days before commencing construction activities

A COR 0 2 0

01 57 30-2 Water Pollution Control

Spill Prevention Control And Countermeasure Plan

(SPCC)

At least 28 days before delivery or storage of oil

A COR 0 2 0

01 71 20-1 Surveying Surveying Plan At least 21 days before beginning survey work

A COR 0 2 0

01 71 20-2 Surveying Resumes At least 21 days before beginning survey work;

At least 21 days before personnel change

I COR 0 2 0

01 71 20-3 Surveying Accuracy Check Results

At least 14 days before beginning survey work

I COR 0 2 0

01 71 20-4 Surveying Completed And Reduced Survey Notes

Within 2 days of completing and reducing notes

I COR 0 2 0

01 71 20-5 Surveying Quantity Survey Notes And Computations

Accompanying progress payment requests

I COR 0 2 0

01 74 00-1 Cleaning and Waste Management

Waste Production And Disposal Plan

Within 7 days of waste disposal

I COR 0 2 0

01 33 00 - 10

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO COR TSC

01 74 00-2 Cleaning and Waste Management

Waste Production And Disposal Records

Within 7 days after waste disposal

I COR 0 2 0

01 74 00-3 Cleaning and Waste Management

Environmental Consultant Resume

At least 21 days before beginning environmental assessment

I COR 0 2 0

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment

Within 14 days of completion of work

I COR 0 2 0

01 78 30-1 Project Record Documents

Final As-built Drawings

Within 14 days of completion of work

I COR 0 2 0

03 11 10-1 Concrete Forming

Formwork Design And Drawings

At least 28 days before beginning onsite concrete work

A COR 0 2 1

03 20 00-1 Concrete Reinforcing

Reinforcement Diagrams and Lists

At least 21 days before fabrication

A COR 0 2 1

03 20 30-1 Epoxy Grouted Rebar Dowels

Approval Data and Instructions

At least 21 days before bringing material on site

A COR 0 2 1

03 20 30-2 Epoxy Grouted Rebar Dowels

Pull-Out Test Procedures

Within 7 days of pull-out testing

I COR 0 2 1

03 20 30-3 Epoxy Grouted Rebar Dowels

Test Data and Results

Within 14 days of completion of work

I COR 0 2 1

03 30 00-1 Cast-in-Place Concrete

Material Approval Data

At least 21 days before beginning onsite concrete work

A COR 0 2 1

03 30 00-2 Cast-in-Place Concrete

Resume At least 21 days before beginning onsite concrete work

A COR 0 2 1

03 30 00-3 Cast-in-Place Concrete

As-built Repairs Within 14 days of completion of work

A COR 0 2 1

03 81 10-1 Concrete Removal

Concrete Removal Plan

At least 21 days before beginning onsite concrete work

A COR 0 2 1

03 81 10-2 Concrete Removal

Changes to Removal Equipment Settings

At least 21 days before changing

A COR 0 2 1

31 03 10-1 Diversion and Care of Stream During Construction

Water Control Plan At least 14 days prior to beginning work on the diversion and care of the stream.

A COR 0 2 0

31 03 10-2 Diversion and Care of Stream During Construction

Removal of Water Plan

At least 14 days prior to beginning any work for removal of water

A COR 0 2 0

01 33 00 - 11

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO COR TSC

31 24 10-1 Embankment, General

Embankment Construction Plan

At least 21 days prior to beginning any work for embankment construction

A COR 0 2 0

32 92 20-1 Seeding and Soil Supplements

Seeding Plan At least 30 days prior to beginning any work for seeding

A COR 0 2 0

32 92 20-2 Seeding and Soil Supplements

Certifications At least 30 days prior to beginning any work for seeding

A COR 0 2 0

Safety Data Sheets 01 35 10 - 1

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

SECTION 01 35 10

SAFETY DATA SHEETS

PART 1 GENERAL

1.1 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.2 DEFINITIONS

A. LHM: List of Hazardous Materials.

B. SDS: Safety Data Sheet.

1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.

1.3 APPLICATION

A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:

1. Materials delivered to Government.

2. Materials incorporated into work.

3. Materials used by the Contractor during contract performance at the jobsite.

1.4 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 10-1, Complete LHM and SDS.

C. RSN 01 35 10-2, Updated LHM and SDS:

1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.

PART 2 PRODUCTS

Safety Data Sheets 01 35 10 - 2

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

PART 3 EXECUTION

Safety and Health 01 35 20 - 1

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

SECTION 01 35 20

SAFETY AND HEALTH

PART 1 GENERAL

1.1 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.2 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

1.3 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 20-1, Resumes:

1. Contractor’s Onsite Safety Representative(s)

a. Include certifications.

2. Safety Professional (CSP) or Certified Industrial Hygienist (CIH)

a. Include certifications.

C. RSN 01 35 20-2, Safety Program:

1. Comprehensive, detailed information on safe work practices, training, engineering controls and personal protective equipment that will be used for this job.

2. Job specific. Generic company safety program will not be accepted.

3. Include specific language for the policy statement “the contractor is responsible for ensuring the work is in compliance with the Reclamation Safety and Health Standards (RSHS).”

4. Prepared in accordance with RSHS Section 3 and RSHS Appendix B.

a. In addition to the outline in RSHS Appendix B, safety program shall include the following elements concerning the Government’s expectations for some items of the Safety Program:

1) Emergency Response Plans http://www.usbr.gov/ssle/safety/RSHS/rshs

01 35 20 - 2

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

a) The work activities on site could include at least four different types of emergency situations requiring different planning and equipment to address; fall/rescue emergencies, medical emergencies, underwater emergencies, and construction accidents. The Contractor shall submit a plan or plans that details the personnel, equipment, training, medical support, transportation, use and coordination with outside emergency services, and special rescue equipment for each type.

b) Include procedures, facilities and contact numbers to be used during an emergency.

2) Hearing Conservation Program:

a) Work at the facility may be in noisy areas at or above the

OSHA PEL of 90 dBA.

b) Provide program for hearing conservation.

c) Reference: 29 CFR 1910.95.

3) Personal Protective Equipment (PPE):

a) Provide plan for use of personal protective equipment.

i. Identify what specific PPE will be used for the job.

ii. References: RSHS Section 8.

iii. Provide all required PPE for their employees.

4) Fall Protection Plan:

a) Prepare fall protection safety plan for employees working in elevated areas where there is a risk of falling. Identify what specific means will be utilized to prevent falls

b) Reference: 29 CFR 1926.Subpart M - Fall Protection.

5) Job Hazard Analysis:

a) Include, in the safety program, a list of job hazard analyses (JHA) that will be developed for each phase of the work.

b) The JHA’s will be made acceptable to the onsite government representative before starting each phase of work.

6) Materials Handling Safety:

a) Identify means used to handle materials.

b) Include crane operator, forklift operator, rigger, and signal person qualifications as required.

7) Water Safety

01 35 20 - 3

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

a) Prepare water safety plan for employees working on the spillway concrete.

D. The Contractor shall be responsible to insure that any/all Subcontractors comply with the provisions in this specification, including the requirements for the site-specific written safety and health work plans.

E. RSN 01 35 20-3, Certificates:

1. CPR and First Aid training certificates for on-site supervisors and foremen.

F. RSN 01 35 20-4, Monthly Reports:

1. Safety Inspection Reports:

a. List noted deficiencies, their abatement dates, and follow-up action for jobsite activities.

b. Base inspection report on findings of jobsite walk-through with Government personnel.

2. Monthly summary: Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.

1.4 QUALIFICATIONS

A. Contractor’s Onsite Safety Representative(s):

1. Competent supervisory employee with appropriate level of safety related training and experience.

2. Completed OSHA authorized 30 hour training course for Construction. Course completion shall be within last 5 years.

3. Holds current certificates for first aid and adult CPR.

B. Safety Professional:

1. Board of Certified Safety Professionals (BCSP) Certified Safety Professional

(CSP).

2. Completed OSHA authorized 30 hour training course for Construction. Course completion shall be within last 5 years.

3. Holds current certificates for first aid and adult CPR.

1.5 CONTRACTOR’S ONSITE SAFETY PERSONNEL

A. Designate employee(s) as Contractor’s Onsite Safety Representative(s) prior to start of construction.

B. Employ CSP for part-time on the job.

1. CSP requirements may be met by retaining of services of consultant.

01 35 20 - 4

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

C. Contractor’s Onsite Safety Representative(s) authorities, duties, and responsibilities:

1. Implement Safety Program.

2. Full authorization to correct unsafe activity on the spot.

3. At least one Contractor Onsite Safety Representative shall be onsite during construction activities.

D. CSP duties, and responsibilities:

1. Prepare Safety Program.

2. Implement Safety Program.

3. Visit the site on an as-needed basis, but at a minimum of one time per week.

4. Full authorization to correct unsafe activity on the spot.

5. Prepare safety inspection reports.

1.6 SAFETY AND HEALTH

A. Onsite work, including mobilization, shall not begin until the COR has reviewed the Safety Program and replied that the Safety Program is adequate for proceeding with onsite work.

B. Comply with the clause at FAR 52.236-13 - Accident Prevention, the clause at WBR 1452.223-81- Safety and Health, RSHS, local safety programs, referenced safety and health standards, and Safety Program.

1. In the event there is a conflict between requirements contained in these documents, the more stringent requirement shall prevail.

1.7 MEDICAL SERVICES AND FIRST AID

A. Provide medical services and first aid in accordance with RSHS Section 5.

B. Make facilities and services available for emergency aid to employees, subcontractor employees, and Government employees.

1. Provide services free of charge to Government employees injured on job.

2. Government employees not injured on job may be charged fees for rendered services based on reasonable and established fee rates.

C. Ambulance service:

1. Arrange for dependable ambulance service in accordance with RSHS, paragraph 5.4.

2. On site ambulance not required.

3. Ambulance:

01 35 20 - 5

Missouri River Basin Project Grand Division Shadehill Unit South Dakota Solicitation No. R17PS00430

a. Inspected and approved for intended use by State or Federal regulatory agency having jurisdiction, or equivalent entity.

4. Ambulance operators: Certified to render first aid/CPR and competent to operate vehicle.

1.8 QUALITY ASSURANCE

A. Contractor’s Onsite Safety Representative(s):

1. The effectiveness of Contractor’s Onsite Safety Representative(s) in prosecuting the safety program will be subject to continual review by the CO.

2. Should the Contractor’s safety effort be considered inadequate, the CO has the option to require the Contractor to employ a full-time…