U.S. Department of the Interior Bureau of Reclamation

May 2016

Solicitation No. R16PS00041 Cle Elum Dam Fish Passage Facility Juvenile Facility-Secant Pile Shaft Yakima River Basin Water Enhancement Project - Integrated Plan Yakima Project - Washington

CLE ELUM DAM FISH PASSAGE FACILITY

JUVENILE FACILITY - SECANT PILE SHAFT

Yakima River Basin Water Enhancement Project - Integrated Plan Yakima Project - Washington

FOREWORD

Work is located at Cle Elum Dam approximately 8 miles northwest of Cle Elum, Washington, in Kittitas County. Work is for constructing the Secant Pile Shaft at Cle Elum Dam. Principal components of the work include earthwork, secant pile wall, cast-in-place reinforced concrete features, access road, cofferdam, and chain link fence.

A pre-offer site visit will be conducted in accordance with the Clause in Section L entitled “Site Visit - Construction.” Offerors are strongly urged to participate in the site visit.

Failure by offerors to inspect the site will not relieve them of the responsibility of properly estimating the difficulty or cost of successfully performing the work in accordance with the specifications and within the allowed time. Attendees are to provide and wear safety boots, hard hats, and safety vests.

FOR DATE AND PLACE OF RECEIPT OF OFFERS, SEE "SOLICITATION, OFFER,

AND AWARD," STANDARD FORM 1442, IMMEDIATELY FOLLOWING THE

"TABLE OF CONTENTS."

FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION

"RECLAMATION SAFETY AND HEALTH STANDARDS" (2009 EDITION AS

REVISED, WITH REVISIONS AT http://www.usbr.gov/ssle/safety/RSHS/rshs.html)

WHICH IS APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT

"WBR 1452.223-81 SAFETY AND HEALTH."

NOTE: SOME OF THE PERMITS IN THIS SOLICITATION ARE FURNISHED IN

UNSIGNED FORMAT. SIGNED PERMITS WILL BE ADDED BY AMENDMENT.

http://www.usbr.gov/ssle/safety/RSHS/rshs.htm

Solicitation No. R16PS00041 Cle Elum Dam Fish Passage Facility - Juvenile Facility - Secant Pile Shaft Yakima Project, Washington i

PART I THE SCHEDULE

SECTION A SOLICITATION/CONTRACT FORM ..................................................................... A-1

SECTION B SUPPLIES OR SERVICES AND PRICES/COSTS ...................................................B-1

SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ........................... C-1

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 20 Reservoir Operations and Conditions 01 31 13 Project Coordination 01 31 19 Project Management 01 32 10 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 21 Removal from Work 01 35 22 First Aid 01 35 30 Contractor’s Onsite Safety and Health Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

Yakima Project, Washington ii

DIVISION 02 - EXISTING CONDITIONS

02 41 07 Removal and Reinstallation of Existing Log Boom Anchor

DIVISION 03 - CONCRETE

03 11 10 Concrete Forming 03 20 00 Concrete Reinforcing 03 20 30 Grouted Anchor Bars 03 30 00 Cast-In-Place Concrete

DIVISION 09 - FINISHES

09 96 31 Coating for Concrete Secant Piles

DIVISION 31 - EARTHWORK

31 02 10 Dust Abatement 31 03 23 Cofferdam Construction 31 03 33 Removal and Control of Water 31 09 21 Abandoning Piezometers 31 11 00 Clearing and Grubbing 31 13 13 Remove and Salvage Trees 31 14 10 Stripping 31 23 02 Compacting Earth Materials 31 23 11 Earthwork 31 23 39 Disposal of Excavated Materials 31 24 18 Compacted Backfill 31 32 32 Geotextile 31 32 36 Geomembrane 31 37 00 Riprap 31 56 20 Secant Pile Shaft

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 15 10 Gravel Surfacing 32 31 10 Chain Link Fence 32 92 20 Seeding

DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors 51 10 10 Final Environmental Impact Statement 51 10 20 Hydrographs, Exceedance Curves, and Reservoir Time History

Yakima Project, Washington iii

51 10 40 Cle Elum Dam Annual and Seasonal Diversion Hydrographs 51 10 50 Cle Elum Dam Permits

DIVISION 52 - DRAWINGS

52 00 00 Drawings

DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS

53 10 00 Geotechnical Baseline Conditions 53 10 01 Geotechnical Supporting Documentation 53 20 00 Geologic Investigations 53 30 00 Records of Geologic and Subsurface Investigations

SECTION D PACKAGING AND MARKING ................................................................................. D-1

SECTION E INSPECTION AND ACCEPTANCE ..........................................................................E-1 E.1. 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984) ........................................ E-1 E.2. 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)...................................... E-1

E.3. 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994) - ALTERNATE I

APR 1984) ....................................................................................................................... E-3

SECTION F DELIVERIES OR PERFORMANCE ......................................................................... F-1

F.1. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984) ......................................................................................................... F-1 F.2. 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEPT 2000) ................... F-1 F.3. 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984) ........................... F-1 F.4. 52.242-14 SUSPENSION OF WORK (APR 1984) ........................................................ F-1

SECTION G CONTRACT ADMINISTRATION DATA ................................................................ G-1

G.1. GOVERNMENT POINT OF CONTACT--BUREAU OF RECLAMATION--PN

REGION (OCT 2010) ..................................................................................................... G-1

G.2. 1452.201-70 AUTHORITIES AND DELEGATIONS--DEPARTMENT OF THE

INTERIOR (MAY 2010) ................................................................................................ G-1

G.3. ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS-INVOICE

PROCESSING PLATFORM (IPP) (APRIL 2013) ........................................................ G-2

SECTION H SPECIAL CONTRACT REQUIREMENTS ............................................................. H-1

H.1. KEY PERSONNEL REQUIREMENTS--BUREAU OF RECLAMATION--PN

REGION (FEB 1995) ..................................................................................................... H-1

H.2. AUTHORIZED WORKERS NOTICE TO POTENTIAL BUREAU OF

RECLAMATION CONTRACTORS (SEP 2002).......................................................... H-1

H.3. CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

(DEC 2015) ..................................................................................................................... H-3

Yakima Project, Washington iv

PART II CONTRACT CLAUSES

SECTION I CONTRACT CLAUSES ................................................................................................ I-1 I.1. 52.202-1 DEFINITIONS (NOV 2013) ............................................................................. I-1 I.2. 52.203-3 GRATUITIES (APR 1984) ............................................................................... I-1 I.3. 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)........................ I-2

I.4. 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE

GOVERNMENT (SEPT 2006)......................................................................................... I-2 I.5. 52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014) .......................................... I-2

I.6. 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS

FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) ........................................... I-4

I.7. 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER

ACTIVITY (MAY 2014) .................................................................................................. I-5

I.8. 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN

FEDERAL TRANSACTIONS (OCT 2010) .................................................................... I-6

I.9. 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT

(MAR 2016) .................................................................................................................... I-10 I.10. 52.203-14 DISPLAY OF HOTLINE POSTER(S) (OCT 2015) .................................... I-14

I.11. 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND

REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER

RIGHTS (APR 2014) ...................................................................................................... I-15

I.12. 1452.203-70 RESTRICTION ON ENDORSEMENTS--DEPARTMENT OF THE

INTERIOR (JUL 1996) .................................................................................................. I-15

I.13. 52.203-99 PROHIBITION ON CONTRACTING WITH ENTITIES THAT

REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS

(MAR 2015) .................................................................................................................... I-15

I.14. 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER

FIBER CONTENT PAPER (MAY 2011) ...................................................................... I-16

I.15. 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR

PERSONNEL (JAN 2011) ............................................................................................. I-16

I.16. 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER

SUBCONTRACT AWARDS (OCT 2015) .................................................................... I-17

I.17. 52.204-12 DATA UNIVERSAL NUMBERING SYSTEM NUMBER

MAINTENANCE (DEC 2012)....................................................................................... I-20

I.18. 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE. (JUL

2013) ............................................................................................................................... I-21

I.19. 52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (JAN 2014) ..... I-23

I.20. 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE

MAINTENANCE (JUL 2015) ........................................................................................ I-24

I.21. 1452.204-70 RELEASE OF CLAIMS -- DEPARTMENT OF THE INTERIOR

(JUL 1996) ...................................................................................................................... I-25

Yakima Project, Washington v

I.22. 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS

AND CERTIFICATIONS (DEC 2014) .......................................................................... I-25

I.23. 52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN

SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED,

OR PROPOSED FOR DEBARMENT (OCT 2015) ...................................................... I-25

I.24. 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION

REGARDING RESPONSIBILITY MATTERS (JUL 2013) ......................................... I-26

I.25. 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED

DOMESTIC CORPORATIONS (NOV 2015) ............................................................... I-27

I.26. 52.210-1 MARKET RESEARCH (APR 2011) .............................................................. I-28 I.27. 52.215-2 AUDIT AND RECORDS--NEGOTIATION (OCT 2010) ............................. I-28

I.28. 52.215-8 ORDER OF PRECEDENCE--UNIFORM CONTRACT FORMAT

(OCT 1997) ..................................................................................................................... I-30

I.29. 1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF

THE INTERIOR (AUG 1996) (DEVIATION) ............................................................... I-30

I.30. 52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA

AND DATA OTHER THAN CERTIFIED COST OR PRICING DATA—

MODIFICATIONS (OCT 2010) .................................................................................... I-31

I.31. CONTRACTOR'S TECHNICAL PROPOSAL INCORPORATED INTO

CONTRACT - BUREAU OF RECLAMATION - PN REGION (MAR 2001) ............. I-32

I.32. 52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE

SMALL BUSINESS CONCERNS (OCT 2014) ............................................................ I-32

I.33. 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2014) ............ I-34

I.34. 52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN (OCT 2015)

ALTERNATE II (OCT 2001) ......................................................................................... I-36

I.35. 52.219-16 LIQUIDATED DAMAGES--SUBCONTRACTING PLAN (JAN

1999) ............................................................................................................................... I-46

I.36. 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM

REREPRESENTATION (JUL 2013) ............................................................................. I-46 I.37. 52.222-3 CONVICT LABOR (JUNE 2003) .................................................................. I-48

I.38. 52.222-4 CONTRACT WORK HOURS AND SAFETY

STANDARDS -OVERTIME COMPENSATION (MAY 2014) ................................... I-49

I.39. 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014) ............ I-50

I.40. 52.222-7 WITHHOLDING OF FUNDS (MAY 2014) .................................................. I-52 I.41. 52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014) ..................................... I-53 I.42. 52.222-9 APPRENTICES AND TRAINEES (JULY 2005) .......................................... I-54

I.43. 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB

1988) ............................................................................................................................... I-56 I.44. 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) ....................... I-56 I.45. 52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014) ................... I-57

I.46. 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE

REQUIREMENTS AND RELATED REGULATIONS (MAY 2014) .......................... I-58

Yakima Project, Washington vi

I.47. 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988) .............. I-58 I.48. 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014) .................................... I-58 I.49. 52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015).................. I-58 I.50. 52.222-26 EQUAL OPPORTUNITY (APR 2015) ........................................................ I-59

I.51. 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR

CONSTRUCTION (APR 2015) ..................................................................................... I-61 I.52. 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015).......................... I-66

I.53. 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES

(JUL 2014) ...................................................................................................................... I-67 I.54. 52.222-37 EMPLOYMENT REPORTS VETERANS (FEB 2016) ............................... I-67

I.55. 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE

NATIONAL LABOR RELATIONS ACT (DEC 2010) ................................................ I-68 I.56. 52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015) ...................... I-70 I.57. 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015) ................. I-77

I.58. 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC

2015) ............................................................................................................................... I-80

I.59. 52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL

SAFETY DATA (JAN 1997) ALTERNATE I (JUL 1995) ........................................... I-84

I.60. 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW

INFORMATION (MAY 2011)....................................................................................... I-86 I.61. 52.223-6 DRUG-FREE WORKPLACE (MAY 2001) ................................................... I-86

I.62. 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL

CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008) ....................................... I-88

I.63. 52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS

IN SERVICE AND CONSTRUCTION CONTRACTS (MAY 2008) .......................... I-89

I.64. 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT

MESSAGING WHILE DRIVING (AUG 2011) ............................................................ I-89

I.65. WBR 1452.223-80 ASBESTOS-FREE WARRANTY--BUREAU OF

RECLAMATION (OCT 1992) ....................................................................................... I-90

I.66. WBR 1452.223-81 SAFETY AND HEALTH -- BUREAU OF RECLAMATION

(JUNE 2015) ................................................................................................................... I-90

I.67. WBR 1452.223-82 PROTECTING FEDERAL EMPLOYEES AND THE

PUBLIC FROM EXPOSURE TO TOBACCO SMOKE IN THE FEDERAL

WORKPLACE–BUREAU OF RECLAMATION (DEC 2009) .................................... I-91

I.68. 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER

TRADE AGREEMENTS (FEB 2016) ........................................................................... I-91

I.69. 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUNE

2008) ............................................................................................................................... I-96

I.70. 52.227-1 AUTHORIZATION AND CONSENT (DEC 2007) ...................................... I-97

I.71. 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND

COPYRIGHT INFRINGEMENT (DEC 2007) .............................................................. I-97

Yakima Project, Washington vii

I.72. 52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC

2007) ............................................................................................................................... I-97

I.73. 52.227-17 RIGHTS IN DATA - SPECIAL WORKS (DEC 2007) ................................ I-98 I.74. 52.228-1 BID GUARANTEE (SEP 1996) ..................................................................... I-99 I.75. 52.228-2 ADDITIONAL BOND SECURITY (OCT 1997) ......................................... I-100

I.76. 52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION

(JAN 1997).................................................................................................................... I-100 I.77. 52.228-11 PLEDGE OF ASSETS (JAN 2012) ............................................................ I-101

I.78. 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS

(MAY 2014).................................................................................................................. I-101 I.79. 52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014) .............................. I-101

I.80. 52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION

(OCT 2010) ................................................................................................................... I-105

I.81. 1452.228-70 LIABILITY INSURANCE-DEPARTMENT OF THE INTERIOR

(JUL 1996) .................................................................................................................... I-106

I.82. WBR 1452.228-84 CERTIFICATION OF REPRESENTATIVES FOR

CORPORATE SURETIES--BUREAU OF RECLAMATION (SEP 1996) ................ I-107

I.83. 52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013) ............................ I-107

I.84. WBR 1452.231-81 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE

-- BUREAU OF RECLAMATION (JUL 1998) ........................................................... I-109

I.85. 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (MAY 2014) ......................................................................................... I-111 I.86. 52.232-17 INTEREST (MAY 2014) ............................................................................ I-114 I.87. 52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014) ............................................... I-115

I.88. 52.232-27 PROMPT PAY FOR CONSTRUCTION CONTRACTS (MAY 2014) ..... I-115

I.89. 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER-SYSTEM FOR

AWARD MANAGEMENT (JUL 2013) ...................................................................... I-124

I.90. 52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS

(JUN 2013).................................................................................................................... I-125

I.91. 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL

BUSINESS SUBCONTRACTORS (DEC 2013) ......................................................... I-126

I.92. WBR 1452.232-80 LIMITATION OF FUNDS (FIXED-PRICE CONTRACT) --

BUREAU OF RECLAMATION (SEPT 2003) ............................................................ I-126

I.93. WBR 1452.232-81 PAYMENT FOR MOBILIZATION AND PREPARATORY

WORK --BUREAU OF RECLAMATION (MAY 2000) ALTERNATE I (MAY

2000) ............................................................................................................................. I-128

I.94. WBR 1452.232-82 OTHER INVOICE REQUIREMENTS -- BUREAU OF

RECLAMATION (DEC 2002) ..................................................................................... I-130

I.95. 52.233-1 DISPUTES (MAY 2014) ALTERNATE I (DEC 1991) ............................... I-130 I.96. 52.233-3 PROTEST AFTER AWARD (AUG 1996) ................................................... I-132

I.97. 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT

2004) ............................................................................................................................. I-133

Yakima Project, Washington viii

I.98. 52.236-2 DIFFERING SITE CONDITIONS (APR 1984) ........................................... I-133

I.99. 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE

WORK (APR 1984) ...................................................................................................... I-133 I.100. 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984) ................. I-134 I.101. 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991) ................................... I-134 I.102. 52.236-8 OTHER CONTRACTS (APR 1984) ............................................................. I-134

I.103. 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,

EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984) ........................... I-134 I.104. 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984) ............................. I-135 I.105. 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984) ......... I-135 I.106. 52.236-12 CLEANING UP (APR 1984) ...................................................................... I-136

I.107. 52.236-13 ACCIDENT PREVENTION (NOV 1991) - ALTERNATE I (NOV

1991) ............................................................................................................................. I-136 I.108. 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984) ....... I-137 I.109. 52.236-16 QUANTITY SURVEYS (APR 1984) - ALTERNATE I (APR 1984) ....... I-137 I.110. 52.236-17 LAYOUT OF WORK (APR 1984) ............................................................. I-138

I.111. 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB

1997)- ALTERNATE I (APR 1984)............................................................................. I-138 I.112. 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995) ................................ I-139

I.113. WBR 1452.236-84 PRESERVATION OF CULTURAL RESOURCES –

BUREAU OF RECLAMATION (FEB 2000) .............................................................. I-139

I.114. WBR 1452.237-80 SECURITY REQUIREMENTS – BUREAU OF

RECLAMATION (FEBRUARY 2011) ....................................................................... I-141 I.115. 52.242-13 BANKRUPTCY (JUL 1995)....................................................................... I-152 I.116. 52.243-4 CHANGES (JUNE 2007) .............................................................................. I-152

I.117. WBR 1452.243-80 MODIFICATION PROPOSALS -- BUREAU OF

RECLAMATION (DEC 2001) ALTERNATE III (JUL 1998) .................................... I-153 I.118. 52.244-2 SUBCONTRACTS (OCT 2010) ................................................................... I-154 I.119. 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (FEB 2016) .................. I-156

I.120. 52.248-3 VALUE ENGINEERING—CONSTRUCTION (OCT 2015) -

ALTERNATE I (APR 1984) ........................................................................................ I-158

I.121. 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT

(FIXED-PRICE) (APR 2012)-ALTERNATE I (SEP 1996) ........................................ I-161 I.122. 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)................... I-164 I.123. 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984) ........................ I-165 I.124. 52.253-1 COMPUTER GENERATED FORMS (JAN 1991) ...................................... I-166

PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J LIST OF ATTACHMENTS ......................................................................................... J-1

PART IV REPRESENTATIONS AND INSTRUCTIONS

Yakima Project, Washington ix

SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS

OF OFFERORS OR RESPONDENTS ....................................................................... K-1

K.1. 52.203-98, PROHIBITION ON CONTRACTING WITH ENTITIES THAT

REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS—

REPRESENTATION (FEB 2015) - DEVIATION ........................................................ K-1

K.2. 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (APR

2016) ............................................................................................................................... K-1

K.3. 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL

2013) ............................................................................................................................... K-5

K.4. NOTICE TO HUBZONE SMALL BUSINESS CONCERNS REGARDING

WAIVER OF PRICE EVALUATION PREFERENCE ADJUSTMENT -

BUREAU OF RECLAMATION - PN REGION (APR 2001) ....................................... K-6

SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS ............................................................................................................L-1

L.1. 52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013) ................................ L-1

L.2. 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE

REPORTING (JUL 2015)................................................................................................ L-3

L.3. 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA

INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND

COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) ............. L-4

L.4. 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA

INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND

COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) .................................................. L-4

L.5. 52.211-6 BRAND NAME OR EQUAL (AUG 1999) (DEVIATION) ........................... L-4

L.6. WBR 1452.211-80 NOTICE OF INTENT TO ACQUIRE METRIC PRODUCTS

AND SERVICES - BUREAU OF RECLAMATION (MAR 1993) ............................... L-5

L.7. 52.215-1 INSTRUCTIONS TO OFFERORSBCOMPETITIVE ACQUISITION

(JAN 2004)....................................................................................................................... L-6

L.8. 52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR

INFORMATION OTHER THAN CERTIFIED COST OR PRICING DATA

(OCT 2010) .................................................................................................................... L-10

L.9. 1452.215-71 USE AND DISCLOSURE OF PROPOSAL

INFORMATION--DEPARTMENT OF THE INTERIOR (APR 1984) ....................... L-11

L.10. WBR 1452.215-80 SOURCE EVALUATION AND SELECTION

PROCEDURES--BUREAU OF RECLAMATION (MAY 2005) ................................ L-13

L.11. WBR 1452.215-81 GENERAL PROPOSAL INSTRUCTIONS--BUREAU OF

RECLAMATION (JAN 1998) ...................................................................................... L-15

L.12. WBR 1452.215-82 TECHNICAL PROPOSAL INSTRUCTIONS--BUREAU OF

RECLAMATION (APR 2001) ...................................................................................... L-17

L.13. WBR 1452.215-83 PRICING PROPOSAL INSTRUCTIONS--BUREAU OF

RECLAMATION (JAN 1998) ...................................................................................... L-19

Yakima Project, Washington x

L.14. FACSIMILE ACKNOWLEDGMENT OF AMENDMENTS, MODIFICATIONS

TO OFFERS, AND WITHDRAWALS OF OFFERS-BUREAU OF

RECLAMATION--PN REGION (APR 2007) .............................................................. L-19

L.15. NOTICE OF INTENT TO INCORPORATE CONTRACTOR'S TECHNICAL

PROPOSAL - BUREAU OF RECLAMATION - PN REGION (MAR 2001) ............. L-20

L.16. 52.216-1 TYPE OF CONTRACT (APR 1984) ............................................................. L-20

L.17. NOTICE TO HUBZONE SMALL BUSINESS CONCERN OF A PRICE

EVALUATION ADJUSTMENT - BUREAU OF RECLAMATION - PN

REGION (APR 2001) .................................................................................................... L-21

L.18. 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY

SITE OF THE WORK (MAY 2014) ............................................................................. L-21

L.19. 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO

ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION

(FEB 1999)..................................................................................................................... L-21

L.20. NON-DISCRIMINATION NOTICE TO U.S. DEPARTMENT OF THE

INTERIOR CONTRACTORS, SUBCONTRACTORS, AND LESSORS --

BUREAU OF RECLAMATION -- PN REGION (JAN 2000) ..................................... L-22

L.21. 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—

CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY

2014) .............................................................................................................................. L-23

L.22. 52.233-2 SERVICE OF PROTEST – DEPARTMENT OF THE INTERIOR

(SEPT 2006) (DEVIATION) ......................................................................................... L-24

L.23. 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB

1995) .............................................................................................................................. L-24

L.24. 52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997) ....... L-25

L.25. WBR 1452.236-85 INSTRUCTION FOR MOBILIZATION AND

PREPARATORY WORK SCHEDULE LINE ITEM -- BUREAU OF

RECLAMATION (MAY 2000) .................................................................................... L-25

L.26. 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984) ................... L-25

SECTION M EVALUATION FACTORS FOR AWARD .............................................................. M-1

M.1. WBR 1452.215-85 EVALUATION FACTORS FOR AWARD - QUALITY

PREDOMINANCE--BUREAU OF RECLAMATION (MAY 2005) ........................... M-1

M.2. WBR 1452.225-82 NOTICE OF WORLD TRADE ORGANIZATION

GOVERNMENT PROCUREMENT AGREEMENT EVALUATIONS--

BUREAU OF RECLAMATION (MAY 2005) .............................................................. M-2

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

Bureau of Reclamation

Pacific Northwest Region

Regional Office Acquisition Management Division

R10

1150 N. Curtis Road, Ste. 100

Boise ID 83706-1234

Susan Kramer 208-378-5156

1x 05/03/2016

R16PS00041

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

CLE ELUM DAM JUVENILE FACILITY SECANT PILE SHAFT, YAKIMA PROJECT, WASHINGTON

THE ESTIMATED PRICE RANGE OF THE WORK IS $10,000,000-$25,000,000

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 900 calendar days and complete it within ________________ ________________ calendar days after receiving

Clause F.1.

06/16/2016

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Pacific Northwest Region

Regional Office Acquisition Management Division

R10

1150 N. Curtis Road, Ste. 100

Boise ID 83706-1234

Susan E. Kramer

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

R16PS00041

SECTION B

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price

Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only. Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated

Quantity, no claim shall be made against the

Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in

Estimated Quantity does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 10.

(e) Definitions:

CLIN - Contract Line Item Number

AU - Activity Unit (equals Lump Sum)

AC - Acre

LF - Lineal Foot

Legacy Doc #: BOR

Delivery: 900 Days After Notice to Proceed

FOB: Destination

00010 Mobilization and Preparatory Work - section WBR 1 AU

1452.232-81

00020 Removal and Reinstallation of Existing Log Boom 1 AU

Anchor - section 02 41 07

00030 Reinforced Concrete Walers, Intake Brace, and 1 AU

Capping Beam - section 03 30 00

00040 Secant Pile Guide Wall - section 03 30 00 1 AU

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

4 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

R16PS00041

00050 Coating for Concrete Secant Piles - section 09 96 1 AU

00060 Cofferdam Construction - section 31 03 23 1 AU

00070 Removal and Control of Water - section 31 03 33 1 AU

00080 Clearing and Grubbing - section 31 11 00 16 AC

00090 Remove and Salvage Trees - section 31 13 13 1 AU

00100 Earthwork for Access Road - section 31 23 11 1 AU

00110 Earthwork for Juvenile Structure Platform to El. 1 AU

2244.0 - section 31 23 11

00120 Earthwork for Interior of Secant Pile Shaft - 1 AU section 31 23 11

00130 Primary Secant Piles - section 31 56 20 10000 LF

00140 Secondary Secant Piles - section 31 56 20 10000 LF

00150 Chain Link Fence - section 32 31 10 1 AU

00160 Seeding - section 32 92 20 10 AC

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Yakima Project, Washington

C-1

SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

DIVISION 01 - GENERAL REQUIREMENTS

Cle Elum Dam Fish Passage Facility, Juvenile Facility - Secant Pile Shaft

Yakima Project, Washington

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located at Cle Elum Dam, approximately 8 miles northwest of Cle Elum, Washington, in Kittitas County.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Secant Pile Shaft:

1. Elliptical Secant Pile Shaft.

2. Reinforced Concrete.

3. Coating.

4. Earthwork.

B. Cofferdam.

C. Access Road.

D. Chain Link Fence.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

1.04 DEFINITIONS

A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 53:

1. CO: Contracting Officer.

Yakima Project, Washington

Summary of Work 01 11 00 - 2

2. COR: Contracting Officer’s Representative.

3. Reclamation: United States Bureau of Reclamation.

4. USBR: United States Bureau of Reclamation.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Yakima Project, Washington

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition; Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences.

b. Describe methods to preserve, protect, and repair if damaged, vegetation (such as trees, shrubs, and grass) and other landscape features on or

01 14 10 - 2 adjacent to the jobsite, which are not to be removed and which do not interfere with the work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

1.04 PROJECT CONDITIONS

A. Contractor use areas for required construction facilities shown on drawings.

B. Maintain existing Government access to spillway throughout life of contract.

C. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

D. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.

E. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

F. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.

01 14 10 - 3

3. The COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment onsite.

3.02 RESTORATION

A. Restore Contractor use areas to pre-construction condition.

B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

C. Seed disturbed areas of Government land used for construction purposes and not required for completed installation in accordance with Section 32 92 20 - Seeding.

Work Restrictions

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Association of State Highway and Transportation Officials (AASHTO)

1. AASHTO LRFD-12 Bridge Design Specifications

1.03 WORK RESTRICTIONS

A. Contractor vehicles crossing the bridge across the spillway chute shall be limited to highway loading HL-93 in accordance with AASHTO LRFD.

B. Contractor shall not cross the dam spillway bridge or the top of the dam.

C. Contractor may utilize Government roads and trails outside of the Contractor use area shown on the drawings with prior approval of COR.

D. An existing flume is in the spillway for fish passage. Work shall not damage or disrupt the flume and its operations.

E. Vehicle and equipment loads are not permitted within ten feet of the outside of the spillway walls.

F. Preventative measures shall be placed in advance of construction to prevent sediment from excavation, backfill, and earth material transport from entering the reservoir, spillway, and stilling basin.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Yakima Project, Washington

Reservoir Operations and Conditions 01 14 20 - 1

SECTION 01 14 20

RESERVOIR OPERATIONS AND CONDITIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 PROJECT CONDITIONS

A. Hydrological and Operational References:

1. Data for the Reservoir and Cle Elum River are provided in Division 51.

2. Hydrological and operational references are solely for the information of the Contractor in timing construction operations to prepare for reservoir operations, flood storage or flow bypassing.

3. The hydrological and operational references and information are available to evaluate flow magnitude and frequency for Cle Elum River and to assess reservoir inflows, reservoir elevations, and tailwater elevations during construction.

4. The Government assumes no responsibility for deductions, interpretations, or conclusions made by the Contractor based on information made available by the Government, in accordance with the clause at FAR 52.236-3 “Site Investigations and Conditions Affecting the Work.”

1.03 TYPICAL RESERVOIR OPERATIONS

A. Cle Elum Dam and Reservoir is owned and operated by Reclamation.

B. The Government will operate Cle Elum Dam and Reservoir facilities during construction periods to comply with water rights and contract obligations to deliver stored water.

Reservoir operations will not be materially altered to accommodate construction.

C. Large and maximum floods for this facility have large snowmelt components. In event of flooding, Reclamation will strive to notify the Contractor of an impending flood and the expected operation as soon as possible.

D. Reservoir Water Surface Elevations (RWSE):

1. Top of Active Conservation RWSE: 2240.0.

E. Reservoir inflows and release rates vary throughout the year and depend upon:

1. Hydrological and seasonal variation throughout the storage basin.

2. Irrigation demands and discharges.

Yakima Project, Washington

Reservoir Operations and Conditions 01 14 20 - 2

3. Outlet works capacity and discharge, and spill operations.

4. Environmental and fish requirements.

F. Refer to Reservoir area capacity, inflow, and discharge information in Division 51 - Information Available to Offerors.

G. Inflow Frequency Floods:

1. Refer to Section 51 10 20 - Hydrographs, Exceedance Curves, and Reservoir Time History and Section 51 10 40 - Cle Elum Dam Annual and Seasonal Diversion Hydrographs.

H. Gated Spillway:

1. The gated spillway at Cle Elum Dam, located at the right abutment, consists of an unlined approach channel and concrete inlet; a gated crest structure 201 feet wide, controlled by five 17-foot-high by 37-foot-wide radial gates with invert elevation 2223 feet; a concrete-lined chute; a combined spillway and outlet works stilling basin; and a discharge channel.

2. Spillway Crest Elevation: 2223.0.

3. Spillway Discharge Capacity at RWSE 2240.0: 40,000 cubic feet per second (cfs).

I. Outlet Works:

1. The outlet works, located to the left of the spillway, consists of an inlet channel with sill elevation 2110.0; a trashrack-protected intake structure; a 690-foot-long 14-foot-diameter upstream conduit; a gate chamber housing two emergency high-pressure slide gates, two regulating high-pressure slide gates, and a low flow bypass system consisting of two 12-inch diameter bypass pipes; a vertical gate chamber access shaft with an elevator and a spiral staircase for access; and an 898-foot-long, 14-foot-diameter downstream conduit which discharges into the left side of the combined spillway and outlet works stilling basin.

2. Maximum discharge capacity at RWSE 2240.0 is approximately 4,900 cfs.

3. Refer to Section 51 10 20 - Hydrographs, Exceedance Curves, and Reservoir Time History for additional outlet works discharge information.

1.04 RESERVOIR WATER SURFACE ELEVATIONS

A. Offerors and the Contractor are alerted and cautioned that construction of the required features may not interfere with the normal operations of Cle Elum Reservoir. The reservoir serves primarily as storage for irrigation.

B. Releases from Cle Elum Reservoir are directed by the Bureau of Reclamation. Irrigation, fisheries, and flood control are the authorized functions of Cle Elum Dam and water conservation is the primary operating criteria.

Yakima Project, Washington

Reservoir Operations and Conditions 01 14 20 - 3

C. Section 51 10 20 - Hydrographs, Exceedance Curves, and Reservoir Time History provides information on historic water surface elevations for Cle Elum Reservoir.

1.05 RESERVOIR OPERATIONS DURING CONSTRUCTION

A. Reservoir levels are directly dependent upon reservoir inflow, downstream flow requirements, and outlet works discharge capacity.

B. Each year, filling and release schedules is based on a study of the entire Yakima Field Office…