R16PS00041
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Boise ID 83706-1234 1150 N. Curtis Road, Ste. 100
R10
Acquisition Management Division Regional Office Pacific Northwest Region Bureau of Reclamation
06/03/2016002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/03/2016
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Cle Elum Dam Fish Passage Facility, Juvenile Facility - Secant Pile Shaft, Yakima Project, Washington
See attached Amendment No. 002 instructions and replacement pages
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Susan E. Kramer
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No. R16PS00041 Cle Elum Dam Fish Passage Facility, Juvenile Facility – Secant Pile Shaft
Yakima Project, Washington Amendment 002
A. The time and date for receipt of offers REMAINS 2:00 p.m., local time, June 16, 2016.
B. Acknowledgment: See block 11 above regarding how to acknowledge this amendment. The acknowledgment must be received at the place designated for receipt of offers (see block 8 of "Solicitation, Offer and Award” Standard Form 1442).
C. Offer Modification: See block 11 above if you have submitted your offer and now desire to modify or withdraw it.
D. Third Party: If you have given your copy of the solicitation to someone else, please forward this amendment accordingly.
E. In Amendment No. 001, the filing instructions for the following replacement pages are corrected:
In Section C, Description/Specifications/Statement of Work, the following pages are deleted and the attached revised pages are substituted therefore:
Remove Pages Insert Revised Pages 31 14 10-1 and 31 14 10-2 31 14 10-1 and 31 14 10-2
F. For use in preparing the Small Business Subcontracting Plan (required to be submitted by large business concerns), the following Department of Interior Subcontracting Goals are provided:
Small Business 44.5% Small Disadvantaged Business 5% Women-Owned Small Business 5% Service-Disabled Veteran-Owned Small Business 3% HubZone Small Business 3%
G. A list of attendees at the site visit on June 2, 2016, is attached.
H. NOTE: The following changes are hereby incorporated into the solicitation. Single-sided replacement pages are provided following this Standard Form 30 and changes are shown with left side bar or shaded text.
I. The FOREWORD page is deleted and replaced with the attached FOREWORD page (all permits have been signed and are included.)
J. In Section A, Solicitation, Offer, and Award (Standard Form 1442), the following pages are deleted and the attached revised pages are substituted therefore:
Remove Pages Insert Revised Pages Pages 1 and 2 Pages 1 and 2
Cle Elum Dam Fish Passage Facility, Juvenile Facility – Secant Pile Shaft
Yakima Project, Washington Amendment 002
K. In Section C, Description/Specifications/Statement of Work, the following pages are deleted and the attached revised pages are substituted therefore:
Remove Pages Insert Revised Pages 01 57 20-3 01 57 20-3 31 56 20-13 31 56 20-13 51 10 50-50 through 51 10 50-56 51 10 50-50 through 51 10 50- 81
Attachments
CLE ELUM DAM FISH PASSAGE FACILITY
JUVENILE FACILITY - SECANT PILE SHAFT
Yakima River Basin Water Enhancement Project - Integrated Plan Yakima Project - Washington
FOREWORD
Work is located at Cle Elum Dam approximately 8 miles northwest of Cle Elum, Washington, in Kittitas County. Work is for constructing the Secant Pile Shaft at Cle Elum Dam. Principal components of the work include earthwork, secant pile wall, cast-in-place reinforced concrete features, access road, cofferdam, and chain link fence.
A pre-offer site visit will be conducted in accordance with the Clause in Section L entitled “Site Visit - Construction.” Offerors are strongly urged to participate in the site visit.
Failure by offerors to inspect the site will not relieve them of the responsibility of properly estimating the difficulty or cost of successfully performing the work in accordance with the specifications and within the allowed time. Attendees are to provide and wear safety boots, hard hats, and safety vests.
FOR DATE AND PLACE OF RECEIPT OF OFFERS, SEE "SOLICITATION, OFFER,
AND AWARD," STANDARD FORM 1442, IMMEDIATELY FOLLOWING THE
"TABLE OF CONTENTS."
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS" (2009 EDITION AS
REVISED, WITH REVISIONS AT http://www.usbr.gov/ssle/safety/RSHS/rshs.html)
WHICH IS APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT
"WBR 1452.223-81 SAFETY AND HEALTH."
http://www.usbr.gov/ssle/safety/RSHS/rshs.htm
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
R16PS00041
Bureau of Reclamation Pacific Northwest Region Regional Office Acquisition Management Division 1150 N. Curtis Road, Ste. 100 Boise, ID 83706-1234
CLE ELUM DAM JUVENILE FACILITY SECANT PILE SHAFT, YAKIMA PROJECT, WASHINGTON
THE ESTIMATED PRICE RANGE OF THE WORK IS $10,000,000-$25,000,000
Bureau of Reclamation Pacific Northwest Region Regional Office; Attn: S. Kramer, PN-3726 Acquisition Management Division 1150 N. Curtis Road, Ste. 100 Boise, ID 83706-1234
R10
Susan Kramer 208-378-5156; email: skramer@usbr.gov
1 205/03/2016
06/16/2016
Clause F.1.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Cle Elum Dam Fish Passage Facility, Juvenile Facility - Secant Pile Shaft
Amendment No. 002
(Revised)
01 57 20 - 3
1.07 NOISE CONTROL
A. Do not exceed 80 decibels (daytime), as measured at noise-sensitive areas such as residences and campgrounds during the hours of 7:00 a.m. to 7:00 p.m. Do not exceed noise levels of 65 decibels (nighttime) during the hours of 7:00 p.m. to 7:00 a.m.
B. Only construction activities approved by COR will be allowed during hours of 7:00 pm to 7:00 am.
C. Provide specialty mufflers for continuously running generators, pumps, and other stationary equipment to meet the decibel requirements above.
D. Compression brakes are not allowed.
E. Perform operations producing high-intensity impact noise only weekdays during the hours of 7:00 a.m. to 7:00 p.m.
F. Noise barriers and equipment mufflers required.
G. Drilling, jackhammering, pile driving, or other operations producing high-intensity impact noise may be performed at nighttime only with prior approval of the CO.
1.08 LIGHT CONTROL
A. Direct stationary floodlights shall shine downward at an angle less than horizontal.
B. Shield floodlights so that floodlights will not be a nuisance to surrounding areas.
C. Direct lighting so that residences are not in direct beam of light.
D. Correct lighting control problems when they occur as approved by COR.
1.09 INVASIVE SPECIES CONTROL
A. Ensure equipment entering the project area, especially which shall be used for within water work, is free of noxious weeds, invasive species and their propagules (such as an egg, bud, seed, spore or other offshoot, that aid in dispersal of the species and from which a new individual may develop) in accordance with State of Washington law. This includes aquatic and terrestrial (i.e., land dwelling) species. Additional information on the specific species can be obtained through the local Washington State Parks and Recreation office.
PART 2 PRODUCTS
Not Used
Amendment No. 002
31 56 20 - 13
Figure 31 56 20A
D. Maintain pile verticality of 0.30 percent from vertical over the entire depth of the pile.
1. Check and record verticality throughout the pile excavation sequence and verify final as-built location of secant piles using two separate techniques. A Koden sonic imaging profile or Sonicaliper downhole survey is required and one of the following additional methods or equipment shall be used to verify tolerances:
mechanical caliper, downhole bi-axial inclinometer, downhole survey equipment, or equivalent methodology as approved by COR.
a. If the shaft is free of water, verify verticality using two separate techniques, as approved by the COR, that do not involve adding water to the cased hole
2. Correct deviations over that specified using a special chisel or other excavation tool, shaft re-excavation, suitable remediation technique or replacement.
E. For the exposed surface of the secant pile shaft, see drawings for the secant pile surface deviation and tolerance requirements and required repairs.
F. Maintain minimum reinforcement cover as shown on drawings.
3.04 SHAFT EXCAVATION
A. In accordance with Section 31 23 11 - Earthwork.
3.05 FINAL FINISH
A. High-pressure water jet wash the entire exposed interior surface of the secant pile shaft to remove all dirt and other foreign substances.
B. Remove excess concrete from the interior of the secant piles that do not conform to surface tolerances outlined in Drawing 33-D-60259.
C. In accordance with Section 09 96 31 - Coating for Concrete Secant Piles.
Amendment No 002
51 10 50 - 50
51 10 50 - 51
1.03 404 PERMIT
51 10 50 - 52
51 10 50 - 53
51 10 50 - 54
51 10 50 - 55
51 10 50 - 56
51 10 50 - 57
51 10 50 - 58
51 10 50 - 59
51 10 50 - 60
51 10 50 - 61
51 10 50 - 62
51 10 50 - 63
51 10 50 - 64
51 10 50 - 65
51 10 50 - 66
51 10 50 - 67
51 10 50 - 68
51 10 50 - 69
51 10 50 - 70
51 10 50 - 71
51 10 50 - 72
51 10 50 - 73
51 10 50 - 74
51 10 50 - 75
51 10 50 - 76
51 10 50 - 77
51 10 50 - 78
51 10 50 - 79
Amendment No 002
51 10 50 - 80
Amendment No 002
(Revised) 51 10 50 - 81
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION