R16PS00041

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Boise ID 83706-1234 1150 N. Curtis Road, Ste. 100

R10

Acquisition Management Division Regional Office Pacific Northwest Region Bureau of Reclamation

06/07/2016003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/03/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Cle Elum Dam Fish Passage Facility, Juvenile Facility - Secant Pile Shaft, Yakima Project, Washington

See attached Amendment No. 003 instructions and replacement pages

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Susan E. Kramer

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation No. R16PS00041 Cle Elum Dam Fish Passage Facility, Juvenile Facility – Secant Pile Shaft

Yakima Project, Washington Amendment 003

A. The time and date for receipt of offers REMAINS 2:00 p.m., local time, June 16, 2016.

B. Acknowledgment: See block 11 above regarding how to acknowledge this amendment. The acknowledgment must be received at the place designated for receipt of offers (see block 8 of "Solicitation, Offer and Award” Standard Form 1442).

C. Offer Modification: See block 11 above if you have submitted your offer and now desire to modify or withdraw it.

D. Third Party: If you have given your copy of the solicitation to someone else, please forward this amendment accordingly.

E. NOTE: The following changes are hereby incorporated into the solicitation. Single-sided replacement pages are provided following this Standard Form 30 and changes are shown with left side bar or shaded text.

F. The solicitation will be amended, prior to the due date for proposals, that addresses the answer to the following question:

Question: Does the secant pile guide wall stay? Or do one or both get removed? Thinking that the interior guide wall won’t stay since there won’t be anything supporting it after excavating the interior (plus the finish won’t be smooth if pouring against earth as shown on 33-D-60278).

Answer: The exterior guide wall is to remain in place. The interior guide wall is to be removed. We will modify the drawings to show removal of the interior guide wall and show a contraction joint between the guide wall and secant piles to make concrete removal easier.

G. In Section C, Description/Specifications/Statement of Work, the following pages are deleted and the attached revised pages are substituted therefore:

Remove Pages Insert Revised Pages 01 33 00-17 and 01 33 00-18 01 33 00-17 and 01 33 00-18 31 23 11-3 through 31 23 11-5 31 23 11-3 through 31 23 11-5 31 56 20-1 through 31 56 20-5 31 56 20-1 through 31 56 20-5 31 56 20-9 and 31 56 20-10 31 56 20-9, 31 56 20-9a, and 31 56 20-10 31 56 20-13 31 56 20-13 31 56 20-15 31 56 20-15 32 92 20-4 and 32 92 20-5 32 92 20-4 and 32 92 20-5

H. In Section J, List of Attachments, the following page is deleted and the attached revised page is substituted therefore:

Remove Pages Insert Revised Pages J-1 J-1 Wage Decision WA160074, Wage Decision WA160074, Dated 1/8/2016, 8 pages Dated 6/3/2016, 8 pages

Attachments

Cle Elum Dam Fish Passage Facility, Juvenile Facility - Secant Pile Shaft

Amendment No. 003

(Revised) 01 33 00 - 17

* Submittal types: A - Action, I - Information.

**Y indicates the submittal shall be shown on the Construction Schedule. Refer to Section 01 32 10 - Construction Program ***CO indicates Contracting Officer, COR indicates Contracting Officers Representative, and TSC indicates Technical Service

Center.

Submittal procedures: SharePoint indicates electronic submittal, numeral indicates number of required hard copy sets.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Responsible code ***

Type

CP

No. of sets to be sent to: **

CO COR TSC

31 32 36-5 Geomembrane Samples At least 28 days before beginning installation

86-68312 A SharePoint

31 32 36-6 Geomembrane Warranty At least 28 days before beginning installation

86-68312 I SharePoint

31 32 36-7 Geomembrane Surveyed As- Built Drawings

Within 2 days of completing installation

86-68312 I SharePoint

31 37 00-1 Riprap Approval Data, Certifications, and Testing Results

At least 28 days before placing riprap

COR A Y SharePoint

31 56 20-1 Secant Pile Shaft Secant Pile Shaft Plans

At least 28 days before beginning secant pile shaft

86-68312 A Y SharePoint

31 56 20-2 Secant Pile Shaft Secant Pile Logs Within 24 hours of completing

86-68312 I SharePoint

31 56 20-3 Secant Pile Shaft Integrity Testing Results and Reports

Within 5 days of testing

86-68312 I SharePoint

31 56 20-4 Secant Pile Shaft Inclinometer Type and Plan

At least 28 days before beginning secant pile shaft

86-68312 A Y SharePoint

31 56 20-5 Secant Pile Shaft Remediation Plans

At least 28 days before beginning secant pile shaft

86-68312 A Y SharePoint

DELETED

Amendment No. 003

(Revised) 01 33 00 - 18

* Submittal types: A - Action, I - Information.

**Y indicates the submittal shall be shown on the Construction Schedule. Refer to Section 01 32 10 - Construction Program ***CO indicates Contracting Officer, COR indicates Contracting Officers Representative, and TSC indicates Technical Service

Center.

Submittal procedures: SharePoint indicates electronic submittal, numeral indicates number of required hard copy sets.

RSN Clause or Section Title

Submittals required

Due date or delivery time

Responsible code ***

Type

CP

No. of sets to be sent to: **

CO COR TSC

31 56 20-6 Secant Pile Shaft Remediation Results Report

Within 5 days of completing tests

86-68312 I SharePoint

31 56 20-7 Secant Pile Shaft Secant Pile Joint Verification

At least 28 days before beginning secant pile shaft and within 5 days of completing tests

86-68312 A Y SharePoint

32 15 10-1 Gravel Surfacing Certification and Laboratory Test Results

At least 28 days before furnishing or placing gravel surfacing

COR A Y SharePoint

32 31 10-1 Chain Link Fence

Design Calculations and Product Data

At least 28 days before beginning installation

86-68120 A Y SharePoint

32 31 10-2 Chain Link Fence

Installation Plans At least 28 days before beginning installation

86-68120 A SharePoint

32 31 10-3 Chain Link Fence

Certifications At least 28 days before delivery

COR A Y SharePoint

32 92 20-1 Seeding Seeding Plan and Certifications

At least 28 days before beginning installation

COR A Y SharePoint

END OF SECTION

Amendment No. 003

(Revised) 31 23 11 - 3

B. Place excavated materials which are too wet for immediate compaction temporarily in stockpiles until moisture content is reduced sufficiently to permit them to be placed.

PART 3 EXECUTION

3.01 EXCAVATION, GENERAL

A. Excavate structure foundations to elevations shown on the drawings or established by

COR.

B. Government reserves the right, during progress of work, to vary slopes, grades, and dimensions of excavations from those specified.

C. Government does not represent that excavation performed under these specifications can be made to or maintained at paylines shown on the drawings or described in these specifications.

D. Perform excavation in the dry.

E. Do not excavate in frozen materials without written approval.

F. Blasting: Not allowed.

G. Take precautions to preserve material below and beyond established lines of excavation in the soundest possible condition.

1. Damage to work due to the Contractor's operations shall be repaired by and at the expense of the Contractor.

2. Material beyond required or prescribed excavation lines which is loosened by the Contractor's operations shall be removed at the expense of the Contractor.

3.02 SURFACES OF EXCAVATION

A. Prepare surface of excavations reasonably even and smooth, free of abrupt indentations and protruding materials (offsets) greater than 2-inches unless otherwise noted in the Specifications.

B. Provide adequate drainage.

C. Surfaces of excavation that are specified for topsoil shall be prepared to form longitudinal depressions at least 2-inches deep, spaced no greater than 12 inches on center. Depressions shall be formed perpendicular to the natural flow of water on the slope in a manner acceptable to the COR to achieve the specified surface prior to placing topsoil.

Amendment No. 003

(Revised) 31 23 11 - 4

3.03 PREPARATION OF SUBGRADE

A. Prepare foundations at feature sites by methods which will provide firm foundations for features.

1. Finish bottom and side slopes of excavation, upon or against which the structure is to be placed, to prescribed dimensions.

2. Moisten and compact prepared surfaces with suitable tools to form firm foundations upon or against which to place the structure in accordance with Section 31 23 02 - Compacting Earth Materials.

B. Where unsuitable material is encountered in the foundation for a structure, the COR will direct performance of additional excavation to remove unsuitable material.

1. Refill additional excavation with compacted backfill in accordance with Section 31 23 02 - Compacting Earth Materials.

C. Prepare areas to receive compacted backfill in accordance with Section 31 23 02 - Compacting Earth Materials.

3.04 OVEREXCAVATION

A. If foundation material is excavated beyond lines required to receive the structure, fill overexcavation with suitable materials and compact in accordance with Section 31 23 02

- Compacting Earth Materials.

B. If foundation material is disturbed or loosened during excavation or otherwise, compact foundation in place or remove and replace it with suitable material and compact in accordance with Section 31 23 02 - Compacting Earth Materials.

3.05 DISPOSAL OF EXCAVATED MATERIALS

A. Dispose of excavated materials which are unsuitable for or are in excess of embankment, backfill, or other earthwork requirements, as determined by COR, as provided in Section 31 23 39 - Disposal of Excavated Materials.

3.06 PLACING BACKFILL

A. Place backfill to the lines and grades shown on the drawings, or as directed by COR, and in accordance with Section 31 24 18 - Compacted Backfill.

3.07 COMPACTING BACKFILL

A. Place, moisten, and compact materials in backfill as provided in Section 31 23 02 - Compacting Earth Materials.

Amendment No. 003

(Revised) 31 23 11 - 5

3.08 SURFACES OF BACKFILL

A. Surfaces of backfill and embankment that are specified for topsoil shall be prepared to form longitudinal depressions at least 2-inches deep, spaced no more than 12 inches on center. Depressions shall be formed perpendicular to the natural flow of water on the slope in a manner acceptable to the COR to achieve the specified surface prior to placing topsoil.

3.09 PROTECTION

A. To provide adequate protection for compacted backfill about a structure, Government reserves the right to direct Contractor to place a sufficient amount of backfill or earthfill material over compacted backfill within 72 hours after completion of compacting backfill.

3.10 CONTRACTOR FIELD QUALITY TESTING

A. Testing: In accordance with Section 31 23 02 - Compacting Earth Materials.

B. Government may perform tests as required to verify contractor quality testing. If Government performs quality assurance testing, provide support as required for Contactor quality testing.

Amendment No. 003

(Revised) 31 56 20 - 1

SECTION 31 56 20

SECANT PILE SHAFT

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Primary Secant Piles:

1. Measurement: Linear feet of primary piles.

a. The top of the pile shall be considered the top of the secant pile guide wall.

b. The length of the pile shall be the difference between the top of the secant pile guide wall elevation as shown on the drawings and the final bottom of pile elevation as shown on the drawings. No measurement will be made for over drilling beyond the elevation shown on the plans unless as directed by the COR. Measurement will be made to the nearest one-tenth of a linear foot.

2. Payment: Linear foot price offered in the Price Schedule.

a. Includes cost of work and materials for primary secant pile shaft including concrete, disposal of excavated material, pressure washing the interior of the secant pile shaft, removing excess concrete within shaft interior not meeting surface tolerances, and remediation of secant piles not meeting minimum contact or verticality tolerances.

b. Does not include additional piles which are not shown on the drawings that are installed to facilitate construction.

B. Secondary Secant Piles:

1. Measurement: Linear feet of secondary piles.

a. The top of the pile shall be considered the top of the secant pile guide wall.

b. The length of the pile shall be the difference between the top of the secant pile guide wall elevation as shown on the drawings and the final bottom of pile elevation as shown on the drawings. No measurement will be made for over drilling beyond the elevation shown on the plans unless as directed by the COR. Measurement will be made to the nearest one-tenth of a linear foot.

c. Includes four (4) inclinometer installations within PVC pipe.

d. Includes ten (10) crosshole sonic logging installations within steel pipe.

e. Includes two (2) secant pile joint verification HQ core holes.

2. Payment: Linear foot price offered in the Price Schedule.

Amendment No. 003

(Revised) 31 56 20 - 2

a. Includes cost of work and materials for secondary secant pile shaft including concrete, reinforcement, disposal of excavated material, pressure washing the interior of the secant pile shaft, removing excess concrete within shaft interior not meeting surface tolerances, and remediation of secant piles not meeting minimum contact or verticality tolerances.

1.02 REFERENCE STANDARDS

A. American Petroleum Institute (API)

1. API 13A-10 Drilling Fluid Materials, Eighteenth Edition

B. ASTM International (ASTM)

1. ASTM A53/ASTM A53M-12 Pipe, Steel, Black and Hot-Dipped, Zinc- Coated, Welded and Seamless

2. ASTM C597/C597M- 04a(2014) Test Method for Pulse Velocity Through Concrete

3. ASTM D6760-14 Integrity Testing of Concrete Deep Foundations by Ultrasonic Crosshole Testing

C. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

D. Federal Highway Administration

1. FLH 521.830 Standard Method for Determining Pulse Velocity Through Concrete in Drilled Shafts

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 31 56 20-1, Secant Pile Shaft Plans:

1. Anticipated production rates, in linear feet per day.

2. Methods and equipment used to construct secant pile shaft.

a. Proposed method of excavation, including equipment, sequence, and drawings showing details of constructing primary and secondary secant piles.

b. Plan for shaft continuity and shaft verticality correction.

1) Methods and frequency of monitoring guide wall trench alignment and verticality in piles including documentation of tools, http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://www.usbr.gov/ssle/safety/RSHS/rshs.html

Amendment No. 003

(Revised) 31 56 20 - 3 equipment, manufacturers’ methodology, and previous experience with verticality quality assurance.

c. Plans for measuring depth, horizontal, and vertical alignment along the entire length of the secant piles.

d. Plan for advancing through oversized material (boulders).

e. Plan for temporary casing installation and removal, and methods of advancing the casing.

f. Plan for installation of the double row secant piles.

3. Details of secant pile guide wall:

a. Methods of constructing secant pile guide wall.

4. Drilling fluid loss contingency plan.

5. Methods of removing loose material from bottom of the pile excavation.

6. Method of installing reinforcement and maintaining reinforcement in proper alignment and location during concrete placement and casing removal.

7. Details of secant pile concrete placement, including proposed equipment and procedures for delivering concrete to pile.

8. Concrete pumping equipment, capacity, and backup equipment.

9. Type of set retarders or other additives to be used and conditions under which they will be used.

10. Method of removing excavated materials, including proposed equipment.

11. Method of operation of tremie system, including cold weather protection of exposed concrete surfaces and prevention of freezing water in lines and pumps.

C. RSN 31 56 20-2, Secant Pile Logs:

1. Submit logs within 24 hours of a secant pile concrete placement.

2. Include for each shaft:

a. Shaft designation.

Amendment No. 003

(Revised) 31 56 20 - 4

b. Location and depth.

c. Starting date and time of reinforcement installation.

d. Starting date and time of concrete placement. Difficulties during concrete placing and times and locations where this occurs.

e. Corrective actions taken.

f. Date and ending time of concrete placement.

g. Volume of neat line and actual concrete in each pile.

h. Verticality monitoring, final deviation and downhole survey.

i. As-built elevation of bottom.

j. As-built survey of installed inclinometers.

k. Description of geology and elevations of contacts between different geologic layers encountered.

D. RSN 31 56 20-3, Integrity Testing Results and Reports:

1. Preliminary Reports - Provide preliminary results to COR for each shaft tested before crosshole sonic logging personnel leave the site. Within 5 days of testing, submit a detailed preliminary crosshole sonic logging report and all test data in ASCII format with a header identifying shaft tested, tube coordinates, and each data column to the COR on a compact disk. Allow 5 days for the COR to conduct a review of the data before issuing the final, written report. Include the following in the crosshole sonic logging report:

a. Project identification and dates of testing: 2 tables and schematic showing shafts tested with identification of tube coordinates and collar elevation.

b. Names of personnel that performed the tests/interpretation and their affiliation.

c. Equipment used.

d. Data logs.

e. XY plots of first arrival times, amplitude, and velocity versus depth.

2. Final Report outlining interpretation, analysis, and results:

Determine the velocity reduction by comparing the velocities achieved in the shaft to the pulse velocity testing on the cylinders constructed from the same concrete and of the same age as the shaft. Where velocity reductions are greater than 20 percent, process the data and construct easy-to-understand two-dimensional cross-sections between tubes and three dimensional volumetric images for the entire shaft. The cross-sections shall be color coded tomographic images indicating velocity variations along the shaft. Identify the location and geometry of defective zones (those with velocity reductions of greater than 20 percent) in three-

Amendment No. 003

(Revised) 31 56 20 - 5 dimensional color images and provide a detailed discussion of each.

Include all information provided in the preliminary reports with the final report.

E. RSN 31 56 20-4, Inclinometer Type and Plan:

1. Type of inclinometers.

2. Installation plan for inclinometers including:

a. Method of installation.

b. Installation equipment and casing.

c. Anchorage of inclinometer.

d. Plan for protecting inclinometer during concrete placement.

F. RSN 31 56 20-5, Remediation Plans:

1. Provide description and plan for techniques to remediate the shaft if the minimum contact between adjacent secant piles are not met and if verticality tolerances are not met prior to placing concrete.

2. If the minimum contact between adjacent piles is not met after concrete placement, the remediation technique shall ensure that the contact between adjacent piles is a minimum of 24-inches based on a concrete compressive strength of 4,500 psi. Provide description and plan for techniques to remediate the shaft if the minimum contact between adjacent secant piles are not met including but not limited to:

a. Vertical methods (i.e. jet grouting).

b. Horizontal methods through the secant pile shaft

c. Provide plan for verifying and reporting contact between adjacent secant piles and effectiveness of remediation.

3. Provide a description and plan for remediating casing that becomes stuck and cannot be removed.

G. RSN 32 56 20-6, Remediation Results Report:

1. Provide a final report outlining the field activities and effectiveness of remediation activities, if required, as outlined in the plan provided in RSN 31 56 20-5.

H. RSN 32 56 20-7, Secant Pile Joint Verification:

1. Provide a plan for supplying drilling equipment to obtain HQ core of two secant pile joints. Describe procedures for utilizing optical tele-viewing equipment to log the entire extent of the borehole.

2. Provide a final report with drill logs, tele-viewing logs, and description of joint conditions. Provide electronic version of optical logs.

Amendment No. 003

(Revised) 31 56 20 - 9

3.02 CONSTRUCTION

A. Construct rigid guides along the alignment of the guide wall prior to drilling secant piles, such that approved design tolerances are achieved as specified in Article for Tolerances below.

B. Installation:

1. In accordance with RSHS.

2. Sequencing:

a. Secant pile shall be constructed in a single phase.

b. Install secant piles in accordance with the drawings.

1) In addition to the required piles shown on the drawings, additional primary piles may be installed at the contractor’s option to facilitate construction in accordance with the approved Secant Pile Shaft Plan submittal. Additional piles are not allowed in the interior of the shaft.

3. Prior to drilling secant pile, adjacent secant pile compressive strength shall be greater than 2,000 psi.

4. Casings:

a. The depth of the secant piles are as shown on the drawings.

b. The use of casing is required for the full depth of the secant pile.

1) Casings are temporary and shall be removed during concreting of the shaft.

2) Casings may be pulled quickly upward a maximum of 4 inches to break the bottom seal, but thereafter removed with a smooth, continuous motion.

3) During concrete placement, the bottom of the tremie shall be kept 10 feet below the top of concrete.

4) During casing removal, the bottom of the casing shall be maintained at least 10 feet below the level of tremie concrete that is being placed.

5) Casings that become bound or fouled during concreting and cannot be practically removed shall constitute a defect in the shaft and shall be remediated in accordance with approved submittal.

a) Contractor shall be responsible to improve the defect to the satisfaction of the COR. Such improvement may consist of removing the concrete or providing a replacement shaft or a series of surrounding replacement shafts.

Amendment No. 003

(Revised) 31 56 20 - 9a

b) Corrective measures shall be performed by the Contractor to the satisfaction of the COR without compensation. No compensation will be made for abandoned casings.

Amendment No. 003

(Revised) 31 56 20 - 10

5. Secant Pile Excavation:

a. General:

1) Remove excavated materials from the working area during drilling operations.

2) Remove drilling tools that are lost in the excavation.

3) Costs due to lost tool removal shall be borne by the Contractor including, costs associated with excavation degradation due to removal operations or the duration the excavation remains open.

4) Liquid displaced during concrete placement controlled, handled, and wasted in accordance with Section 01 57 30 - Water Pollution Control.

b. Primary Secant Piles:

1) Remove excavated materials from primary secant piles and stockpile in spoil areas if suitable for backfill, earthfill, or topsoil in accordance with Section 31 23 39 - Disposal of Excavated Materials.

c. Secondary Secant Piles:

1) Remove excavated materials from secondary secant piles and handle as waste material to be removed in accordance with Section 31 23 39 - Disposal of Excavated Materials.

6. Alignment:

a. Overlap of each secant pile shall be at least 9 inches between primary and secondary piles at all locations along the main alignment of the secant pile shaft or as shown on the drawings.

b. Overlap of each secant pile shall be at least 6 inches between primary and secondary piles at all locations along the outer alignment of the secant pile shaft or as shown on the drawings.

c. Deviations beyond these limits shall be corrected by the Contractor before concrete placement, or remediated as outlined in RSN 31 56 20-5.

7. Bottom Cleaning:

a. Remove loose material from bottom of shafts.

b. Check shaft for loose material immediately prior to placing tremie concrete in shaft.

8. Place reinforcing steel in secondary piles:

a. Install reinforcing steel in secondary piles as shown in the drawings before placing concrete.

b. Stagger splices of adjacent bars.

Amendment No. 003

(Revised) 31 56 20 - 13

Figure 31 56 20A

A. Maintain pile verticality of 0.30 percent from vertical over the entire depth of the pile.

1. Check and record verticality and pile tolerances and verify final as-built location of secant piles using two separate techniques. The following methods or equipment shall be used: mechanical caliper, downhole bi-axial inclinometer, downhole survey equipment, or equivalent methodology as approved by COR.

2. Correct deviations over that specified using a special chisel or other excavation tool, shaft re-excavation, suitable remediation technique or replacement.

B. For the exposed surface of the secant pile shaft, see drawings for the secant pile surface deviation and tolerance requirements and required repairs.

C. Maintain minimum reinforcement cover as shown on drawings.

4.02 SHAFT EXCAVATION

A. In accordance with Section 31 23 11 - Earthwork.

4.03 FINAL FINISH

A. High-pressure water jet wash the entire exposed interior surface of the secant pile shaft to remove all dirt and other foreign substances.

B. Remove excess concrete from the interior of the secant piles that do not conform to surface tolerances outlined in Drawing 33-D-60259.

C. In accordance with Section 09 96 31 - Coating for Concrete Secant Piles.

a. Deleted

Amendment No. 003

(Revised) 31 56 20 - 15

c. Meet ACI 336.3R.

6. Notify COR immediately of test results showing failure of materials to meet specifications. Provide preliminary and final reports of test results to COR as outlined in RSN 31 56 20-3.

B. Secant Pile Joints:

1. Advance two HQ core holes at two secant pile joints up to full depth at locations as determined by the COR.

2. After coring activities are complete, fill core hole with approved grout from the bottom using a tremie.

3. Notify COR immediately of any indication of loose or defective concrete, curing compound, voids, and other contaminated material within the joint.

4. The first core hole shall be advanced at the joint of one of the first three secondary/primary pile contacts, with the additional core hole at the location selected by the COR.

3.07 DOCUMENTATION

A. Record and survey the information on a secant shaft installation log for each hole as outlined in RSN 31 56 20-2.

B. Submit reports of integrity testing as outlined in RSN 31 56 20-3.

C. Submit a report summarizing the secant pile joint conditions as outlined in RSN 31 56 20-7.

Amendment No. 003

(Revised) 32 92 20 - 4

PART 3 EXECUTION

3.01 SEEDBED PREPARATION

A. Complete prior to seeding.

B. For sloped surfaces 4:1 or steeper, prepare surface by forming longitudinal depressions at least 2 inches deep spaced no greater than 12 inches on center. Depressions shall be formed perpendicular to the natural flow of water on the slope in a manner acceptable to the COR or achieve the specified surface prior to seeding.

1. Scarify or harrow and rake other surface soils to minimum depth of 3 inches.

C. Remove stiff clods, lumps, roots, litter, stones, and other foreign material greater than 6 inches in size from the surface. Dispose of removed materials in accordance with Section 01 74 00 - Cleaning and Waste Management.

D. Fill or smooth surface to remove rills, gullies and depressions.

E. Protect prepared surfaces from erosion and washouts. Repair damaged surfaces as required.

3.02 FERTILIZING

A. Apply fertilizer in accordance with seed supplier recommendation and Contractor’s COR approved seeding plan.

3.03 HYDROSEEDING

A. Apply seed mixture at rate specified in Table 32 92 20A - Required Seed Mixture.

B. Hydromulch Slurry:

1. Mix to keep homogeneous.

2. Ingredients:

a. Water.

b. Tackifier.

c. Seed.

d. Wood cellulose fiber mulch:

1) Rate: 4,000 pounds per acre at 10 percent moisture content.

2) Add to water slurry after seed.

e. Fertilizer may be applied with hydroseeding.

3. Maximum time between batching slurry and application: 1-hour.

C. Spray slurry mix uniformly.

Amendment No. 003

(Revised) 32 92 20 - 5

D. Use coloring as metering agent.

E. Seed only between September 15 and November 30 of each year.

3.04 MAINTENANCE

A. Any seeded areas that dies or fails to germinate during the warranty period (FAR 52.246-21) shall be re-hydromulched.

B. Begin maintenance operations immediately after seeding and continue as needed until final acceptance.

C. Keep seeded areas in a healthy growing condition.

D. Inspect seeded areas a least once per week during the establishment period and perform needed maintenance until acceptance is granted.

E. Re-hydromulch as directed by the COR.

3.05 ACCEPTANCE

A. Acceptance of seeded areas will be granted when a uniform stand of acceptable grass is obtained, with a minimum of 70 percent coverage.

B. Portions of the seeded area may be accepted at various times at the discretion of the

COR.

Cle Elum Dam Fish Passage Facility - Juvenile Facility - Secant Pile Shaft

Amendment No. 003

J-1 (revised)

PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J LIST OF ATTACHMENTS

1. Department of Labor General Wage Decision Number WA160074, Dated June 3, 2016, 8 pages

2. Past Performance Questionnaire (PPQ)

3. Bid Bond

4. Small Business Subcontracting Plan Template

5. Federal Non-Disclosure Agreement

6. Drawings

General Decision Number: WA160074 06/03/2016 WA74

Superseded General Decision Number: WA20150074

State: Washington

Construction Type: Heavy including water and sewer line construction

County: Kittitas County in Washington.

HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/08/2016 1 06/03/2016

CARP0770-002 06/01/2015

Rates Fringes

CARPENTER (Including Formwork)...$ 31.94 14.00

MILLWRIGHT.......................$ 41.86 14.49

(HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - ALL

CLASSIFICATIONS EXCEPT MILLWRIGHTS AND PILEDRIVERS

Hourly Zone Pay shall be paid on jobs located outside of the free zone computed from the city center of the following listed cities:

6/7/2016http://www.wdol.gov/wdol/scafiles/davisbacon/WA74.dvb?v=1

Seattle Olympia Bellingham Auburn Bremerton Anacortes Renton Shelton Yakima Aberdeen-Hoquiam Tacoma Wenatchee Ellensburg Everett Port Angeles Centralia Mount Vernon Sunnyside Chelan Pt. Townsend

Zone Pay:

0 -25 radius miles Free 26-35 radius miles $1.00/hour 36-45 radius miles $1.15/hour 46-55 radius miles $1.35/hour Over 55 radius miles $1.55/hour

(HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - MILLWRIGHT

AND PILEDRIVER ONLY)

Hourly Zone Pay shall be computed from Seattle Union Hall, Tacoma City center, and Everett City center

Zone Pay:

0 -25 radius miles Free 26-45 radius miles $ .70/hour Over 45 radius miles $1.50/hour

ELEC0077-001 02/01/2013

Rates Fringes

Line Construction:

LINEMEN.....................$ 45.62 4%+12.90

ELEC0112-014 06/01/2015

Rates Fringes

ELECTRICIAN......................$ 38.80 18.59

ENGI0302-007 06/01/2014

Rates Fringes

Power equipment operators:

Group 1A...................$ 38.39 17.39 Group 1AA..................$ 38.96 17.39

Group 1AAA.................$ 39.52 17.39 Group 1.....................$ 37.84 17.39 Group 2.....................$ 37.35 17.39 Group 3.....................$ 36.93 17.39 Group 4.....................$ 34.57 17.39

Zone Differential (Add to Zone 1 rates):

Zone 2 (26-45 radius miles) - $1.00 Zone 3 (Over 45 radius miles) - $1.30

BASEPOINTS: Aberdeen, Bellingham, Bremerton, Everett, Kent, Mount Vernon, Port Angeles, Port Townsend, Seattle, Shelton, Wenatchee, Yakima

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1AAA - Cranes-over 300 tons, or 300 ft of boom (including jib with attachments)

GROUP 1AA - Cranes 200 to 300 tons, or 250 ft of boom (including jib with attachments); Tower crane over 175 ft in height, base to boom; Excavator/Trackhoe, Backhoes: Over 90 metric tons

GROUP 1A - Cranes, 100 tons thru 199 tons, or 150 ft of boom (including jib with attachments); Loaders-overhead, 8 yards and over; excavator/Trackhoe, backhoes: over 50 metric tons to 90 metric tons

GROUP 1 - Cranes 45 tons thru 99 tons, under 150 ft of boom (including jib with attachments); Crane-overhead, bridge type, 45 tons thru 99 tons; Derricks on building work Excavator/Trackhoe, backhoes: over 30 metric tons to 50 metric tons; Loader- overhead 6 yards to, but not including 8 yards; Dozer D-10

GROUP 2 - Cranes, 20 tons thru 44 tons with attachments;

Crane-overhead, bridge type-20 tons through 44 tons;

Excavator/Trackhoe, backhoe: 15 to 30 metric tons;

Loaders-overhead under 6 yards; Mechanic; Grader (finishing)

GROUP 3 - Cranes-thru 19 tons with attachments; A-frame crane over 10 tons; Dozers-D-9 and under; Roller-Plant Mix;

Excavator/Trackhoe, backhoe: under 15 metric tons;

Forklift: 3000 lbs and over with attachments; Oiler; Grader (non-finishing); Boom Truck over 10 tons GROUP 4 -Cranes-A frame-10 tons and under; Roller-other than plant mix; Forklift: under 3000 lbs with attachments; Boom Truck 10 tons and under

IRON0086-013 07/01/2015

Rates Fringes

IRONWORKER.......................$ 32.76 23.19

* LABO0348-001 06/01/2016

ZONE 1:

Rates Fringes

LABORER

GROUP 2.....................$ 23.42 10.80

GROUP 3.....................$ 25.64 10.80

GROUP 4.....................$ 26.71 10.80

GROUP 5.....................$ 26.71 10.80

ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES):

ZONE 2 - $1.00

ZONE 3 - $1.30

BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT,

TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT.

TOWNSEND, PT. ANGELES, AND BREMERTON

ZONE 1 - Projects within 25 radius miles of the respective city hall ZONE 2 - More than 25 but less than 45 radius miles from the respective city hall ZONE 3 - More than 45 radius miles from the respective city hall

LABORERS CLASSIFICATIONS

GROUP 2: Flagger

GROUP 3: General or Common Laborer; Mason Tender-Cement/Concrete; Chipping Guns (Under 30 lbs)

GROUP 4: Grade Checker; Pipe Layer; Chipping Guns (Over 30 lbs)

GROUP 5: Mason Tender-Brick

PAIN0005-010 04/15/2013

Rates Fringes

Painters: (Brush, Roller and Spray)...........................$ 15.58 10.23

SUWA2009-040 08/07/2009

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 17.21 0.00

LABORER: Landscape..............$ 14.67 0.00

OPERATOR: Drill.................$ 28.15 8.20

PIPEFITTER.......................$ 25.98 3.98

TRUCK DRIVER: Dump Truck........$ 19.67 0.00

TRUCK DRIVER: Water Truck.......$ 24.36 8.30

TRUCK DRIVER: 10 Yard Truck.....$ 24.61 8.34

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION