About this file
FEMA Grant Agreement Summary
This is a FEMA Grant Agreement (Attachment A, Part b - 1st Revision) executed between the Florida Division of Emergency Management and the City of New Smyrna Beach, Volusia County, under the Hazard Mitigation Grant Program (HMGP) DR-4337-373-R for the elevation of six flood-prone single-family residential structures. The project involves raising existing structures a minimum of two feet above the Base Flood Elevation plus three feet for sea level rise, including utility disconnection and reconnection, installation of new open foundations on pilings, elevation of service equipment, and construction of ADA-compliant access features at five of the six properties. The six properties are located at 455 DeSoto Drive, 645 Goodwin Avenue, 647 Goodwin Avenue, 508 South Indian River Road, 529 South Peninsula Avenue, and 640 South Pine Street, all within Special Flood Hazard Areas (SFHA) Zone "AE" in New Smyrna Beach. A non-mandatory pre-bid meeting is scheduled for December 9, 2025, at 2:00 PM via Microsoft Teams, with written questions due by December 18, 2025, at 5:00 PM. Bids are due electronically by January 8, 2026, at 2:00 PM, with bid opening at 3:00 PM the same day. The FEMA award was made on May 11, 2021, the agreement was executed on November 12, 2021, and the Period of Performance extends through November 30, 2026, with a total project duration of 66 months covering state contracting, planning, permitting, construction, and closeout phases. Work must be completed by October 31, 2026.
The project is 75% federally funded through FEMA's Hazard Mitigation Grant Program, with the remaining 25% provided by the City of New Smyrna Beach and homeowners. Sub-Recipient Management Costs (SRMC) are 100% federally funded and cannot exceed 5% of total project costs. Contractors must be qualified, licensed Florida contractors registered with the Florida Department of State and licensed in Volusia County, with current occupational licenses and valid business tax receipts. All contractors and subcontractors must comply with debarment and suspension requirements and maintain active Sam.Gov registration with E-Verify compliance. Bid security of 10% of the total bid amount and specific insurance requirements are mandatory, including Workers' Compensation, Commercial General Liability ($1,000,000 per occurrence), Automobile Liability ($1,000,000 combined single limit), and Professional Liability ($1,000,000). Liquidated damages are assessed at $1,694 per calendar day for work not completed by the deadline. The procurement encourages participation from disadvantaged business enterprises, including minority business enterprises (MBEs), women's business enterprises (WBEs), veteran-owned businesses (VOBs), and labor surplus area firms. Construction must comply with the Florida Building Code, ASCE 24-14 or latest edition, National Flood Insurance Program standards in 44 CFR Part 60, and all applicable local floodplain ordinances. All work must be monitored by qualified professionals, with archaeological monitoring required at specific properties per National Historic Preservation Act (NHPA) requirements, and final Elevation Certificates (FEMA Form FF-206-FY-22-152) must be submitted at closeout to certify code compliance and proper elevation heights.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF PURPOSE:
Attachment A - Part (b)
(1st Revision)
Budget and Scope of Work
The purpose of this Scope of Work is to elevate fiood-prone homes in New Smyrna Beach, Volusia County, Florida, funded through the Hazard Mitigation Grant Program (HMGP) DR-4337-373-R, as approved by the Florida Division of Emergency Management (Division) and the Federal Emergency Management Agency (FEMA).
The Sub-Recipient, City of New Smyrna Beach, agrees to administer and complete the project per the application submitted by the Sub-Recipient and subsequently approved by the Division and FEMA. The Sub-Recipient shall complete the work in accordance with all applicable Federal, State and Local Laws, Regulations and Codes.
PROJECT OVERVIEW:
As a Hazard Mitigation Grant Program project, the Sub-Recipient proposes an elevation project to provide fiood protection to single-family residences listed below, located in New Smyrna Beach, Florida 32169.
The proposed project shall elevate the existing structures a minimum of two feet above the effective Base Flood Elevation (BFE) or the highest known fiood level, whichever is higher, plus three feet to account for sea level rise. The scope of work involves building and site preparation along with disconnection of utilities at each location. The existing structures shall be raised on a new open foundation on pilings to the proposed design elevation. All utilities shall be reconnected, and service equipment shall be elevated to the required height. Appropriate means of ingress and egress shall be constructed to access the elevated living spaces at each property. Additionally, the City of New Smyrna Beach proposes to install ADA-compliant access consisting of a lift platform medically required for homeowners at 455 DeSoto Drive, New Smyrna Beach, Florida 32169; 645 Goodwin Avenue, New Smyrna Beach, Florida 32169; 508 South Indian River Road, New Smyrna Beach, Florida 32169; 529 South Peninsula Avenue, New Smyrna Beach, Florida 32169 and 640 South Pine Street, New Smyrna Beach, Florida 32169. The existing residential properties are located within designated Special Flood Hazard Areas (SFHA) and are at imminent risk of reoccurring fiooding. The proposed elevation project intends to significantly reduce potential future flood damage to these residential properties, thereby enhancing their resilience and ensuring the safety of their occupants.
The habitable living areas of the original structure shall be elevated, and the non-habitable areas (if any) shall be converted to storage or parking. The project shall be designed and constructed in compliance with the Florida Building Code, ASCE 24-14 or latest edition, National Flood Insurance Program (NFIP) standards in 44 CFR, Part 60 and/or local fioodplain ordinances or any other applicable local regulations.
A final Elevation Certificate shall be completed for closeout to certify the structure(s) was elevated to the required height.
Elevation projects must complete an inspection prior starting any construction, conducted by a qualified professional to demonstrate the proposed structures are structurally sound and capable of being elevated safely. A copy of the inspection report shall be provided to the Florida Division of Emergency Management within 12-months of the FEMA award date.
The project shall provide protection against a 100-year storm event. Activities shall be completed in strict compliance with Federal, State and Local applicable Rules and Regulations.
Project Locations:
ID# Address Coordinates 4-) 2Q§ GaAeva Q,i,,e, Removed 01117/25 . ' C' - . '),, ........... , ~ :111 GaReva gFi•1e, Removed 01/17/25 . - n --·--
3) 455 DeSoto Drive, 29.035502, -80.909311 New Smyrna Beach, Florida 32169
-B 9~d GeeBwiR ,AA18Al::le, Removed 01/17/25 ., C - "),., al ea1 GeeawiR .O.veRHe, Removed 01/17/25 . - - . ...- --
61 ea9 GeeawiR AVBRHB, Removed 01/17/25 . ' n n _, ..,,,-1 ,..,..
7) 645 Goodwin Avenue, 29.030993, -80.901401 New Smvrna Beach, Florida 32169
8) 647 Goodwin Avenue, 29.030783, -80.901400 New Smvrna Beach, Florida 32169
9) 1 Hi Qakweea A>1eAHe, Removed 01/17125 .. - n _, ~· ._. ..,,... .. ,..,...
10) 508 South Indian River Road, 29.033696, -80.904341 New Smvrna Beach, Florida 32169
44) BQ~ g91:1lR J=!eAiRSl:lla ,Cw8Rl:l8, Removed 01/17/25 .. - n --·--
12) 529 South Peninsula Avenue, 29.031542, -80.902419 New Smyrna Beach, Florida 32169
~ em SeHIA l>iRe S!Feel, Removed 01117/25 .. n -
44) e18 SeHIA l>iRe SIFeel, Removed 01/17/25 . - - . --·--
15) 640 South Pine Street, 29.031298, -80.901090 New Smyrna Beach, Florida 32169
~ :1e:11 SHASel gFi,•e, Removed 01117/25 . C - . . ' ,.,,., ... --
4-7, :1e:1a SHRSel gFi•Je, Removed 01/17/25 .. - - . . . --. .. --
TASKS & DELIVERABLES:
A) Tasks:
1) The Sub-Recipient shall procure the services of a qualified and licensed Florida contractor and execute a contract with the selected bidder to complete the scope of work as approved by the Division and FEMA. The Sub-Recipient shall select the qualified, licensed Florida contractor in accordance with the Sub-Recipient's procurement policy as well as all federal and state laws and regulations. All procurement activities shall contain sufficient source documentation and be in accordance with all applicable regulations.
The Sub-Recipient shall be responsible for furnishing or contracting all labor, materials, equipment, tools, transportation and supervision and for performing all work per conceptual designs and construction plans presented to the Division by the Sub-Recipient and subsequently approved by the Division and FEMA.
The Sub-Recipient and contractor shall be responsible for maintaining a safe and secure worksite for the duration of the work. The contractor shall maintain all work staging areas in a neat and presentable condition.
The Sub-Recipient shall ensure that no contractors or subcontractors are debarred or suspended from participating in federally funded projects.
The selected contractor shall have a current and valid occupational license/business tax receipt issued for the type of services being performed.
The Sub-Recipient shall provide documentation demonstrating the results of the procurement process.
This shall include a rationale for the method of procurement and selection of contract type, contractor selection and/or rejection and bid tabulation and listing, and the basis of contract price.
The Sub-Recipient shall provide an executed "Debarment, Suspension, Ineligibility, Voluntary Exclusion Form" for each contractor and/or subcontractor performing services under this agreement.
Executed contracts with contractors and/or subcontractors shall be provided to the Division by the Sub Recipient.
The Sub-Recipient shall provide copies of professional licenses for contractors selected to perform services. The Sub-Recipient shall provide a copy of a current and valid occupational license or business tax receipt issued for the type of services to be performed by the selected contractor.
2) The Sub-Recipient shall monitor and manage the installation to provide flood protection.
The project shall be implemented in accordance with conceptual designs and construction plans previously presented to the Division by the Sub-Recipient and subsequently approved by the Division and FEMA. The Sub-Recipient shall ensure that all applicable state, local and federal laws and regulations are followed and documented, as appropriate.
The project consists of the general construction and furnishing of all materials, equipment, labor and fees to minimize recurring flooding and reduce repetitive flood loss to structures and roadways.
The Sub-Recipient shall fully perform the approved project, as described in the submitted documents, in accordance with the approved scope of work, budget line item, allocation of funds and applicable terms and conditions indicated herein. The Sub-Recipient shall not deviate from the approved project terms and conditions.
Construction activities shall be completed by a qualified and licensed Florida contractor. All construction activities shall be monitored by the professional of record. The Sub-Recipient shall complete the project in accordance with all required permits. All work shall be completed in accordance with applicable codes and standards.
Upon completion of the work, the Sub-Recipient shall schedule and participate in a final inspection of the completed project by the local municipal or county official, or other approving official, as applicable.
The official shall inspect and certify that all installation was in accordance with the manufacturer's specifications. Any deficiencies found during this final inspection shall be corrected by the Sub Recipient prior to Sub-Recipient's submittal of the final inspection request to the Division.
Upon completion of Task 2, the Sub-Recipient shall submit the following documents with sufficient supporting documentation, and provide a summary of all contract scope of work and scope of work changes, if any. Additional documentation for closeout shall include:
a) Local Building Official Building Permit.
b) A Copy of the Certificate of Occupancy or copy of the Local Building Official Inspection Report and Final Approval, as applicable.
1. Certifying that the structure is code-compliant.
c) A Copy of the Elevation Certificate before mitigation, if available.
d) A Copy of the Final Elevation Certificate (FEMA Form ff-206-fy-22-152), after mitigation - ensuring the structure has been elevated to the proper elevation.
e) All Product Specification/ Data Sheets (technical standards) satisfying protective requirements on all products utilized.
f) Signed notices from the affected property owner in the Special Flood Hazard Area (SFHA) that the Sub-Recipient shall record a Deed Notice applicable to their property, as described in section (h}, below, and that they shall maintain flood insurance.
g) Verification that the property located within a SFHA is covered by an NFIP flood insurance policy to the amount at least equal to the project cost or to the maximum limit of coverage made available with respect to the particular property, whichever is less.
h) Confirmation that the Sub-Recipient (or property owner) has legally recorded with the county or appropriate jurisdiction's land records a notice that includes the name of the current property owner (including book/page reference to record of current title, if readily available), a legal description of the property, and the following notice of flood insurance requirements:
"This property has received Federal hazard mitigation assistance. Federal Jaw requires that flood insurance coverage on this property must be maintained during the life of the property regardless of transfer ofownership of such property. Pursuant to 42 U.S. C. 5154a, notwithstanding any other provision of law, no Federal disaster relief assistance made available in a flood disaster area may be used to make a payment (including any loan assistance payment) to a person for repair, replacement, or restoration for damage to any personal, residential, or commercial property if that person at any time has received flood disaster assistance that was conditional on the person first having obtained flood insurance under applicable Federal Jaw and subsequently having failed to obtain and maintain flood insurance as required under applicable Federal law on such property.
The property owner is also required to maintain this property in accordance with the floodplain management criteria of 44 CFR Section 60.3 and any city/county ordinance."
i) Verification of compliance that construction vehicles and equipment were stored onsite or at existing access points within the Sub-Recipient's right-of-way during the project.
j) Letter verifying if human remains, intact archaeological features or deposits, or prehistoric or historic artifacts were encountered during project activities and, if so, how they were handled.
k) Verification of compliance with all monitor deliverables and reporting requirements from the Secretary of Interior qualified archaeological monitor and archaeologist.
I) Copy of floodplain permit and verification of compliance; if no permit was needed, a letter stating "No Permit Required" from the local floodplain administrator obtained prior to project commencement.
m) Proof of compliance with Project Conditions and Requirements contained herein.
3) During the course of this agreement, the Sub-Recipient shall submit requests for reimbursement.
Adequate and complete source documentation shall be submitted to support all costs (federal share and local share) related to the project. In some cases, not all project activities may be fully complete prior to requesting reimbursement of costs incurred in completion of this scope of work; however, a partial reimbursement may be requested.
The Sub-Recipient shall submit an Affidavit signed by the Sub-Recipient's project personnel with each reimbursement request attesting to the completion of the work, that disbursements or payments were made in accordance with all agreement and regulatory conditions, and that reimbursement is due and has not been previously requested.
The Sub-Recipient shall maintain accurate time records. The Sub-Recipient shall ensure invoices are accurate and any contracted services were rendered within the terms and timelines of this agreement.
All supporting documentation shall agree with the requested billing period. All costs submitted for reimbursement shall contain adequate source documentation which may include but not be limited to:
cancelled checks, bank statements, Electronic Funds Transfer, paid bills and invoices, payrolls, time and attendance records, contract and subcontract award documents.
Construction Expense: The Sub-Recipient shall pre-audit bills, invoices, and/or charges submitted by the contractors and subcontractors and pay the contractors and subcontractors for approved bills, invoices, and/or charges. Sub-Recipient shall ensure that all contractor/subcontractor bills, invoices, and/or charges are legitimate and clearly identify the activities being performed and associated costs.
Sub-Recipient Management Costs (SRMC) expenditure must adhere to FEMA Policy #104-11-1 HMGP Management Costs (Interim) signed November 14, 2018. FEMA defines management costs as any: Indirect costs, Direct administrative costs, and other administrative expenses associated with a specific project. Administrative costs are expenses incurred by a Sub-Recipient in managing and administering the federal award to ensure that federal, state requirements are met including:
solicitation, development, review, and processing of sub-applications; delivery of technical assistance;
quarterly progress and fiscal reporting; project monitoring; technical monitoring; compliance activities associated with federal procurement requirements; documentation of quality of work verification for quarterly reports and closeout; payment of claims; closeout review and liquidation; and records retention.
Any activities that are directly related to a project are not eligible under management costs. For example, architectural, engineering, and design services are project costs and cannot be included under management costs. Similarly, construction management activities that manage, coordinate, and supervise the construction process from project scoping to project completion are project costs. These activities cannot be included under management costs.
Due to Strategic Funds Management (SFM), SRMC Interim Policy requires management costs to be obligated in increments sufficient to cover Sub-Recipient needs, for no more than one year, unless contractual agreements require additional funding. FEMA has established a threshold where annual increments will be applied to larger awards allowing smaller awards to be fully obligated. Obligations will be handled by the size of the total subaward.
The Sub-Recipient shall pre-audit all SRMC source documentation - personnel, fringe benefits, travel, equipment, supplies, contractual, and indirect costs. A brief narrative is required to identify what the funds will be used for. Documentation shall be detailed and clearly describe each approved task performed, hours devoted to each task, and the hourly rate charged including enough information to calculate the hourly rates based on payroll records. Employee benefits and tasks shall be clearly shown on the Personnel Activity Form, and all Personnel or Contractual SRMC shall be invoiced separate from all other project costs.
Project Management Expenses (only applies to disasters prior to August 1, 2017, all others adhere to FEMA Policy #104-11-1 for SRMC): The Sub-Recipient shall pre-audit source documentation such as payroll records, project time sheets, attendance logs, etc. Documentation shall be detailed information describing tasks performed, hours devoted to each task, and the hourly rate charged for each hour including enough information to calculate the hourly rates based on payroll records. Employee benefits shall be clearly shown.
The Division shall review all submitted requests for reimbursement for basic accuracy of information.
Further, the Division shall ensure that no unauthorized work was completed prior to the approved project start date by verifying vendor and contractor invoices. The Division shall verify that reported costs were incurred in the performance of eligible work, that the approved work was completed, and that the mitigation measures are in compliance with the approved scope of work prior to processing any requests for reimbursement.
Review and approval of any third-party in-kind services, if applicable, shall be conducted by the Division in coordination with the Sub-Recipient.
Quarterly reports shall be submitted by the Sub-Recipient and received by the Division at the times provided in this agreement prior to the processing of any reimbursement.
The Sub-Recipient shall submit to the Division requests for reimbursement of actual construction and managerial costs related to the project as identified in the project application, conceptual designs, and construction plans. The requests for reimbursement shall include:
a) Contractor, subcontractor, and/or vendor invoices which clearly display dates of services performed, description of services performed, location of services performed, cost of services performed, name of service provider and any other pertinent information;
b) Proof of payment from the Sub-Recipient to the contractor, subcontractor, and/or vendor for invoiced services;
c) Clear identification of amount of costs being requested for reimbursement as well as costs being applied against the local match amount.
The Sub-Recipient's final request for reimbursement shall include the final construction project cost.
Supporting documentation shall show that all contractors and subcontractors have been paid.
BJ Deliverables:
Mitigation Activities consist of elevation of single-family residences located in New Smyrna Beach, Florida, including but not limited to raising the residential structures, utilities, and electrical and mechanical equipment to the required height.
The habitable living areas of the original structure shall be elevated, and the non-habitable areas (if any) shall be converted to storage or parking. The project shall be designed and constructed in compliance with the Florida Building Code, ASCE 24-14 or latest edition, NFIP standards in 44 CFR, Part 60 and/or local floodplain ordinances or any other applicable local regulations.
The project shall provide protection against a 100-year storm event. Activities shall be completed in strict compliance with Federal, State and Local applicable Rules and Regulations. A final Elevation Certificate shall be completed for closeout to certify the structure(s) was elevated to the required height.
Provided the Sub-Recipient performs in accordance with the Scope of Work outlined in this Agreement, the Division shall reimburse the Sub-Recipient based on the percentage of overall project completion.
PROJECT CONDITIONS AND REQUIREMENTS:
CJ Engineering:
1) The Sub-Recipient shall submit to the Division an official letter stating that the project is 100% complete and ready for the Division's Final Inspection of the project.
2) The Sub-Recipient shall provide a copy of the Notice of Commencement, and a copy of the Certificate of Occupancy or any local official Inspection Report and/or Final Approval, as applicable.
3) The Sub-Recipient shall provide a copy of the Elevation Certificate prepared before mitigation, if available.
4) The Sub-Recipient shall submit a copy of the Elevation Certificate prepared after mitigation, showing the Base Flood Elevation and the elevation of all components.
5) The Sub-Recipient shall submit all Product Specifications / Data Sheet(s) (technical standards) satisfying protect requirements on all products utilized.
6) All installations shall be done in strict compliance with the Florida Building Code or any local codes and ordinances. All materials shall be certified to exceed the wind and impact standards of the current local codes.
7) The Sub-Recipient shall follow all applicable State, Local and Federal Laws, Regulations and requirements, and obtain (before starting project work) and comply with all required permits and approvals. Failure to obtain all appropriate Federal, State, and Local permits and clearances may jeopardize federal funding.
D) Environmental:
1) Sub-Recipient shall follow all applicable state, local and federal laws, regulations and requirements, and obtain (before starting project work) and comply with all required permits and approvals. Failure to obtain all appropriate federal, state, and local environmental permits and clearances may jeopardize federal funding.
2) Any change, addition or supplement to the approved Scope of Work that alters the project (including other work not funded by FEMA, but done substantially at the same time), regardless of the budget implications, shall require re-submission of the application to FEMA through the Division for National Environmental Policy Act (NEPA) and National Historic Preservation Act (NHPA) re-evaluation before starting project work.
3) The Sub-Recipient shall monitor ground-disturbing activities during construction, and if any potential archeological resources are discovered, shall immediately cease construction in that area and notify the Division and FEMA.
If human remains or intact archaeological features or deposits (e.g., arrowheads, pottery, glass, metal, etc.) are uncovered, work in the vicinity of the discovery shall stop immediately and all reasonable measures to avoid or minimize harm to the finds shall be taken. The Sub-Recipient shall ensure that archaeological discoveries are secured in place, that access to the sensitive area is restricted, and that all reasonable measures are taken to avoid further disturbance of the discoveries.
The Sub-Recipient's contractor shall provide immediate notice of such discoveries to the Sub Recipient The Sub-Recipient shall notify the Florida Division of Historic Resources and FEMA within 24 hours of the discovery. Work in the vicinity of the discovery may not resume until FEMA has completed consultation with SHPO, Tribes, and other consulting parties as necessary.
In the event that unmarked human remains are encountered during permitted activities, all work shall stop immediately, and the proper authorities notified in accordance with Florida Statutes, Section 872.05.
4) If prehistoric or historic artifacts, such as pottery or ceramics, projectile points, dugout canoes, metal implements, historic building materials, or any other physical remains that could be associated with Native American, early European, or American settlement are encountered at any time within the project site area, the permitted project shall cease all activities involving subsurface disturbance in the vicinity of the discovery. The Sub-Recipient shall contact the Florida Department of State, Division of Historical Resources, Compliance Review Section at (850)-245-6333. Project activities shall not resume without verbal and/or written authorization. In the event that unmarked human remains are encountered during permitted activities, all work shall stop immediately and the proper authorities notified in accordance with Section 872.05, Florida Statutes.
5) The Sub-Recipient must obtain a floodplain permit from the local floodplain administrator before work begins. Failure to comply with these conditions may jeopardize FEMA funding; verification of compliance shall be required at project closeout.
6) A professional Secretary of the Interior qualified archaeological monitor shall be present during activities associated with the elevation of 508 S. Indian River Rd (l0#10) and shall follow FEMA's Monitor Deliverables & Reporting Requirements.
7) The activities associated with the elevations of 529 S. Peninsula Ave (10#12), 645 Goodwin Ave (ID#?), 647 Goodwin Ave (10#8), and 640 S. Pine Street (10#15) shall be monitored by a professional Secretary of the Interior qualified archaeologist and shall follow FEMA's Monitor Deliverables & Reporting Requirements.
8) Construction vehicles and equipment shall be stored onsite during the project or at existing access points within the Sub-Recipient's right-of-way.
9) Construction vehicles and equipment used for this project shall be maintained in good working order to minimize pollutant emissions.
E) Programmatic:
1) A change in the scope of work must be approved by the Division and FEMA in advance regardless of the budget implications.
2) The Sub-Recipient must notify the Division as soon as significant developments become known, such as delays or adverse conditions that might raise costs or delay completion, or favorable conditions allowing lower costs or earlier completion.
3) The Sub-Recipient must "obtain prior written approval for any budget revision which would result in a need for additional funds" [44 CFR 13(c)], from the Division and FEMA.
4) Project is approved with the condition that the enclosed list of deliverables shall be submitted, 30 days prior to the Period of Performance date, for review and approval by the Division, for submittal to FEMA for closeout.
5) Any extension of the Period of Performance shall be submitted to FEMA 60 days prior to the expiration date. Therefore, any request for a Period of Performance Extension shall be in writing and submitted, along with substantiation of new expiration date and a new schedule of work, to the Division a minimum of seventy (70) days prior to the expiration date, for Division processing to FEMA.
6) The Sub-Recipient must avoid duplication of benefits between the HMGP and any other form of assistance, as required by Section 312 of the Stafford Act, and further clarification in 44 CFR 206.191.
7) A copy of the executed subcontract agreement must be forwarded to the Division within 10 days of execution.
8) A copy of the recorded deed amendment for each property as required by HMA Guidance.
9) For structures located in the Special Flood Hazard Area (SFHA), the Sub-Recipient shall verify if the proposed project triggers a substantial improvement and confirm that the project will be in compliance with the current local floodplain management ordinance.
10) For structures that remain in the SFHA after implementation, flood insurance must be maintained for the life of the structure to an amount at least equal to the project cost or to the maximum limit of coverage made available with respect to the particular properties.
Confirmation that the Sub-Recipient (or property owner) has legally recorded with the county or appropriate jurisdiction's land records a notice that includes the name of the current property owner (including book/page reference to record of current title, if readily available), a legal description of the property, and the following notice of flood insurance requirements:
"This property has received Federal hazard mitigation assistance. Federal law requires that flood insurance coverage on this property must be maintained during the life of the property regardless of transfer of ownership of such property. Pursuant to 42 U.S.C. 5154a, notwithstanding any other provision of law, no Federal disaster relief assistance made available in a flood disaster area may be used to make a payment (including any loan assistance payment) to a person for repair, replacement, or restoration for damage to any personal, residential, or commercial property if that person at any time has received flood disaster assistance that was conditional on the person first having obtained flood insurance under applicable Federal law and subsequently having failed to obtain and maintain flood insurance as required under applicable Federal law on such property. The property owner is also required to maintain this property in accordance with the floodplain management criteria of 44 CFR Section 60.3 and any city/county ordinance."
11) Prior to project commencement, the Sub-Recipient must identify the source and location of fill material and provide this information to the Division and FEMA. If the borrow pit is privately owned, or is located on previously undisturbed land, or if the fill is obtained by the horizontal expansion of a pre-existing borrow pit, FEMA consultation with the State Historic Preservation Officer shall be required. Failure to comply with this condition may jeopardize FEMA funding; verification of compliance shall be required prior to project commencement AND for project closeout.
12) The Sub-Recipient must obtain a floodplain permit from the local floodplain administrator before work begins. Failure to comply with these conditions may jeopardize FEMA funding; verification of compliance shall be required at project closeout.
13) A certificate of occupancy and the final Elevation Certificate (FEMA Form - Elevation Certificate -ff- 206-fy-22-152) for each structure on the project to certify the structure is code compliant and was elevated to the required elevation.
14) A copy of the recorded deed for each property, including structure elevation project deed requirements for property maintenance and fiood insurance requirements.
15) A signed Acknowledgement of Conditions for Properties Using FEMA Hazard Mitigation Assistance form for each structure.
16) A certification from a building official or licensed design professional verifying that the structure was designed and constructed to the minimum standard of the two most recently published editions of the International Codes, even in locations where no code has been adopted.
17) Front, rear and side photographs of the final structure(s), including the date of the photograph, property address, latitude/longitude to the nearest sixth decimal place and the source of the photograph.
18) Verification offload insurance policy for each structure.
19) Closeout of structural elevation project, the Sub-Recipient shall provide:
a) Updated property information for each location.
b) A Certificate of Occupancy, certifying that each structure is code-compliant.
c) A Final Elevation Certificate (FEMA Form FF-206-FY-22-152) for each structure to ensure the structure has been elevated to the proper elevation.
20) Special Conditions required on implementation of project:
a) EO 11988 CONDITION: The sub-recipient must obtain floodplain permit from the local floodplain administrator before work begins. Failure to comply with these conditions may jeopardize FEMA funding; verification of compliance shall be required at project closeout. Source of condition:
Executive Order 11988-Floodplains (EO 11988) Monitoring Required: No
b) NHPA CONDITION: We agree with the recommendation for a professional Secretary of the Interior qualified archaeological monitor to be present during activities associated with the elevation of 508 South Indian River Road (10#10). Source of condition: National Historic Preservation Act (NHPA) Monitoring Required: No
c) NHPA CONDITION: We also suggest that given the history of burials and observations of mounds in this general area that the activities associated with the elevations of 529 South Peninsula Avenue (10#12), 645 Goodwin Avenue (10#7), 647 Goodwin Avenue (ID#8), and 640 South Pine Street (10#15) be monitored by a professional Secretary of the Interior qualified archaeologist as well.
Source of condition: National Historic Preservation Act (NHPA) Monitoring Required: No
d) NHPA CONDITION: Construction vehicles and equipment will be stored onsite during the project or at existing access points within the sub-recipient's right-of-way. Source of condition: National Historic Preservation Act (NHPA) Monitoring Required: No
e) NHPA CONDITION: If prehistoric or historic artifacts, such as pottery or ceramics, projectile points, dugout canoes, metal implements, historic building materials, or any other physical remains that could be associated with Native American, early European, or American settlement are encountered at any time within the project site area, the permitted project shall cease all activities involving subsurface disturbance in the vicinity of the discovery. The sub-recipient shall contact the Florida Department of State, Division of Historical Resources, Compliance Review Section at (850)-245-6333. Project activities shall not resume without verbal and/or written authorization. In the event that unmarked human remains are encountered during permitted activities, all work shall stop immediately, and the proper authorities notified in accordance with Section 872.05, Florida Statutes. Source of condition: National Historic Preservation Act (NHPA) Monitoring Required:
No
f) NHPA CONDITION: If human remains or intact archaeological features or deposits (e.g., arrowheads, pottery, glass, metal, etc.) are uncovered, work in the vicinity of the discovery will stop immediately and all reasonable measures to avoid or minimize harm to the finds will be taken. The sub-recipient will ensure that archaeological discoveries are secured in place, that access to the sensitive area is restricted, and that all reasonable measures are taken to avoid further disturbance of the discoveries. The sub-recipient's contractor will provide immediate notice of such discoveries to the sub-recipient. The sub-recipient shall contact the Florida Division of Historic Resources and FEMA within 24 hours of the discovery. Work in the vicinity of the discovery may not resume until FEMA has completed consultation with SHPO, Tribes, and other consulting parties as necessary.
In the event that unmarked human remains are encountered during permitted activities; all work shall stop immediately, and the proper authorities notified in accordance with Florida Statutes, Section 872.05. Source of condition: National Historic Preservation Act (NHPA) Monitoring Required: No
21) Per FEMA Hazard Mitigation Assistance Guidance Part VI, D.3.4 - Contingency funds are not automatically available for use. Prior to their release, contingency funds must be re-budgeted to another direct cost category and identified. Post-award changes to the budget require prior written approval from the Division (FDEM). The written request should demonstrate what unforeseen condition related to the project arose that required the use of contingency funds.
22) Sub-Recipient Management Costs (SRMC), implemented under the Disaster Relief and Recovery Act of 2018 (DRRA), amended Section 324 of the Stafford Act, and the Hazard Mitigation Grant Program Management Costs (Interim) FEMA Policy 104-11-1, provides 100% federal funding under HMGP to Sub-Recipients to efficiently manage the grant and complete activities in a timely manner.
a) SRMC must confonm to 2 CFR Part 200, Subpart E, applicable program regulations, and Hazard Mitigation Assistance (HMA) Guidance (2015), ensuring costs are reasonable, allowable, allocable and necessary to the overall project.
b) Funding is for approved indirect costs, direct administrative costs, and administrative expenses associated with this specific project and shall have adequate documentation.
c) SRMC cannot exceed 5% of the total project costs awarded.
d) SRMC is 100% federally funded and will be reimbursed based on actual costs incurred for each individual Request for Reimbursement (RFR) submitted with the required documentation.
e) SRMC shall be reconciled against actual costs on a quarterly basis and annual basis.
f) If the Final Project Reconciliation results in a reduction of total project costs, any resulting SRMC overpayment shall be reimbursed back to the State for return to FEMA prior to FEMA Closeout.
This is FEMA project number4337-373-R. It is funded under HMGP, FEMA-4337-DR-FL and must adhere to all program guidelines established for the HMGP in accordance with the PAS Operational Agreement for Disaster 4337.
FEMA awarded this project on May 11, 2021; this Agreement was executed on November 12, 2021, and the Period of Perfonmance for this project shall end on November 30, 2026.
F) FINANCIAL CONSEQUENCES:
If the Sub-Recipient fails to comply with any term of the award, the Division shall take one or more of the following actions, as appropriate in the circumstances:
1) Temporarily withhold cash payments pending correction of the deficiency by the Sub-Recipient;
2) Disallow all or part of the cost of the activity or action not in compliance;
3) Wholly or partly suspend or terminate the current award for the Sub-Recipient's program;
4) Withhold further awards for the program; or
5) Take other remedies that may be legally available.
SCHEDULE OF WORK
State Contracting: 6 Months
Construction Plan/Technical Specifications: 24 Months
Bidding / Local Procurement: 6 Months
Permitting: 3 Months
Construction/ Installation: 18 Months
Local Inspections/ Compliance: 3 Months
State Final Inspection / Compliance: 3 Months
Closeout Comeliance: 3 Months
Total Period of Performance: 66 Months