Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
This is a pre-bid conference presentation issued by the City of Long Beach Public Works Department for a construction project involving curb and infrastructure repairs at two waterfront locations. The project scope includes joint sealant replacement, concrete spall repair, epoxy injection of cracks, crack sealing, penetrating sealer application, structural steel spot painting, and removal of a solar floral sculpture at the Convention Center Promenade (Specifications B-4840), and concrete coping reconstruction, surface spall repairs, joint sealant installation, and penetrating sealer application at Rainbow Lagoon (Specifications B-4841). The Convention Center Promenade work is scheduled for 85 working days, while Rainbow Lagoon work spans 60 working days across two phases. The mandatory pre-bid conference was held on January 15, 2026, at 11:00 am with an optional job-site walk-through at 12:30 pm. Contractors must submit requests for information by January 27, 2026, at 3:00 pm, with bids due electronically through Long Beach Buys on February 10, 2026, at 3:00 pm. Council award is estimated for May 2026. Attendance at the pre-bid conference is mandatory, requiring contractors to confirm attendance via email to Alma Wagner by 5:00 pm on January 15, 2026, or face bid rejection.
The project requires either a Class A or B contractor license and mandates 10 percent bid security for Division A work and 20 percent self-performance for Division H work. The engineer's estimate is $3 million covering both locations. The project is subject to California prevailing wage rate 2025-2 with weekly certified payroll uploads required in LCPtracker and monthly labor compliance monitoring. A Project Labor Agreement applies, allowing both union and non-union contractors with non-union core workforce permitted at a 1:1 ratio up to 10 employees, requiring a signed Letter of Assent upon award. Local hire goals are set at 40 percent of total hours worked within specified zip codes including Long Beach and Gateway Cities, with apprenticeship goals at 30 percent per craft and disadvantaged/veteran worker goals at 10 percent. Bids must be submitted electronically only through Long Beach Buys, with addendum #1 posted January 12, 2026. The project is funded through Tideland Fund Capital Improvement Programs and is subject to Tier 3 prevailing wage requirements applicable to Los Angeles and Orange Counties.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| R-7243 Addendum 1.pdf | ||
| R-7243 Addendum 3.pdf | ||
| R-7243 Sign In-Sheet~1.pdf | ||
| R-7243 Addendum 2.pdf | ||
| Seller Guidance v4.pdf | ||
| R-7243 CC and RL Plans.pdf | ||
| R-7243 CC and RL Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-BID CONFERENCE
January 15, 2026 11:00 am
CONVENTION CENTER
PROMENADE AND
RAINBOW LAGOON
CURB REPAIRS
(R-7243)
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
1. Introductions
2. Location & Existing Site Photos
3. Project Overview, Scope of Work & Project Phasing
4. Bid Requirements
5. Project Requirements
a. Labor Compliance
b. Project Labor Agreement (PLA)
6. Bid Schedule
7. Submit Bids on LB Buys
8. Pre-Bid Conference Sign-In [Mandatory]
9. Job-Site Walk-Through, Sign-In [Optional]
AGENDA
**Please remember to use the mute button whether joining via a computer or phone to avoid disruption during the meeting.
**IMPORTANT**
Email Alma.Wagner@longbeach.gov to “sign in” & confirm attendance at today’s Mandatory Pre-bid Conference.
More details at end of meeting.
INTRODUCTIONS
Public Works Alma Wagner, Project Manager Alma.Wagner@longbeach.gov
Financial Management Labor Compliance
Margaret Talamantes, Labor Compliance Officer James Vazquez, Labor Compliance Analyst laborcompliance@longbeach.gov
Long Beach Buys Anne Takii, Administrative Analyst LBPurchasing@longbeach.gov
Economic Development Project Labor Agreement
Nicholle Moore, PLA Administrator Nicholle.Moore@longbeach.gov
Dewberry Engineers Inc.
Engineer of Record
Matt Schmitz, P.E.
Curb Repairs (R-7243)
Curb Repairs (R-7243)
• This project will be subject to State of California prevailing wage rage 2025-2.
Division A, A3 - A4 Division H- 7.2 Labor, H25 thru H28 Division D, Sample Contract – Sections 11 thru 13
• Contractor Registration: All contractors and subcontractors must be registered with the DIR before bidding, being listed in a bid, or working on a public works project, pursuant to
LC 1725.5
• Prime is responsible for subcontractor compliance to applicable prevailing wage laws.
• Apprenticeship Compliance: Apprenticeship requirements for the employment of apprentices apply, per LC 1777.5.
• Certified payrolls must be uploaded weekly in LCPtracker.
• The City will assign a Labor Compliance Consultant who will monitor the contract and request ancillary payroll documents on a monthly basis via “Discrepancy Notice”.
• A Pre-construction will be held to review all prevailing wage requirements before work starts.
• Labor Compliance withholds will be held on progress payments when contractors are noncompliant with requested payroll documents.
PROJECT REQUIREMENTS – LABOR COMPLIANCE
PROJECT LOCATION
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
300 E. Ocean Boulevard, Long Beach, CA 90803
Long Beach Convention Center
Entrance
EXISTING SITE PHOTOS
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
Convention Center Promenade
Examples:
Solar Floral SculptureBrick Repairs Crack Repairs
• Specifications and Drawings B-4840
• Scope:
Replacement of joint sealant Concrete spall repair Epoxy injection of cracks Sealing cracks Application of penetrating sealer Spot painting of structural steel Removal of the solar flora sculpture Joint sealant replacement to address water leaks at Hyatt turnaround and back of house
• Engineer's Estimate $3M (including Convention Center & Rainbow Lagoon)
PROJECT OVERVIEW, SCOPE OF WORK & PHASING
Convention Center Promenade and Rainbow Lagoon
Convention Center Promenade
PHASING SCHEDULE
• Duration of Work: 85 Working Days
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
Convention Center Promenade
• Promenade, Terminus Structure, Rainbow Lagoon Staircase, Shoreline Drive Pedestrian Overcrossing (POC), and Seaside Way POC.
PROJECT LOCATION
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
Rainbow Lagoon
400 E. Shoreline Drive, Long Beach, CA 90803
EXISTING SITE PROJECT
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
Rainbow Lagoon
Coping Damage Sidewalk Cracking
• Specifications and Drawings B-4841
• Scope:
Reconstruction of the concrete coping Surface spall repairs along the walkway Installation of joint sealant along the walkway Application of penetrating sealer along full limits of the walkway
• Coastal Development Permit Waiver 2-24-0768 Installation of a temporary debris capture system to prevent demolition debris from falling into the lagoon.
PROJECT OVERVIEW, SCOPE OF WORK & PHASING
Convention Center Promenade and Rainbow Lagoon
PROJECT PHASING
• Duration of Work: 60 Working Days
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
PHASE 1 PHASE 2
Required License
• Class A or B Contractor License
Submission of Bids
• Electronic Submittal through Long Beach Buys ONLY
Note: Give yourself enough time for bid submittal as the system will close at the bid time.
Bid Opening, Location, Day, Time
• Electronic through Long Beach Buys, February 10, 2026, 3:00pm
Bid Security
• 10% - Division A
Self-Performance
• 20% - Division H
Contractor Minimum Qualifications
BID REQUIREMENTS
PROJECT REQUIREMENTS – PROJECT LABOR AGREEMENT (PLA)
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
Tideland Fund Projects are only subject to Tier 3, which include LA and Orange Counties.
1. UNION VS. NON-UNION CONTRACTORS
• Both Union and Non-Union Contractors are eligible to bid and win the award of Public Works Contracts that are subject to the PLA. Non-Union Contractor Core workforce may still be used on a 1:1 ratio per craft. (1st worker from Core, 2nd from Union, 3rd from Core, 4th From Union, and so on up to 10 employees. Employee #11 and on must be dispatched from the Union Halls.
2. LETTER OF ASSENT
• Upon award, a Letter of Assent must be signed by the Prime and all subs before work can be performed on this project.
The Letter of Assent is an agreement to abide by the terms and conditions contained within the PLA and the Union Schedule A’s for each craft employed.
PROJECT REQUIREMENTS – PROJECT LABOR AGREEMENT (PLA)
Convention Center Promenade and Rainbow Lagoon Curb Repairs (R-7243)
3. LOCAL HIRE GOAL
• The Local Hire Goal established for this project is 40% of the total hours worked within the zip codes specified within Attachment B (including the City of Long Beach and Gateway Cities).
4. APPRENTICES
• There is a 30% Apprentice goal for each craft/workforce.
5. DISADVANTAGED/VETERAN WORKERS
• The Disadvantaged Worker goal for this project is 10%. This category includes low-income and veterans and requires the completion of a form to determine qualification for each worker.
6. PRE-CON/ PRE-JOB CONFERENCE
• A PLA Administrator will be assigned to the project after award which will review the PLA in detail to assist with compliance.
• Each Primary Contractor which is awarded a Construction Contract by the City for Project work shall conduct a Pre-Job Conference with the appropriate affected Union prior to commencing work, which additionally requires that you notify the Trades Council and the PLA Administrator.
KEY DATES
December 30, 2025Bid Advertisement Date
January 15, 2026 11:00 amMandatory Pre-Bid Conference
January 15, 2026 12:30 pmOptional Job-Site Walk-Through
January 27, 2026 3:00 pmRequest for Information (RFI) due
February 10, 2026 3:00 pm (electronically through Long Beach Buys)
Bid Due Date & Bid Opening
Posted January 12, 2026Addendum #1 Other Addenda (as required)
Estimated May 2026Council Award
BID SCHEDULE
• Please send any questions or Requests for Information (RFI) to Alma Wagner, Project Manager at
Alma.Wagner@longbeach.gov by Tuesday, January 27, 2026, 3:00 pm
• CC: TidelandsCIP@longbeach.gov
• The City will not respond to questions or RFIs after the Tuesday, January 27, 2026 deadline.
REQUEST FOR INFORMATION (RFI) DEADLINE
• Long Beach Buys https://longbeachbuys.buyspeed.com/bso/
• Many available written and video guides in multiple languages
• Contact LBPurchasing@longbeach.gov for questions
Long Beach Buys
• You do not need to sign in to search
• Keyword: R-7243 or Convention or Rainbow
Long Beach Buys – Registration and Search
• Be sure you are in the Seller role to create quotes
• Scroll to the bottom of the solicitation and press “Create Quote”
Long Beach Buys – Creating Quotes longbeach.gov/pw
Jayson Lacno-Musngi Jayson.Lacno-Musngi@longbeach.gov
562-570-5578
Thank You!
IMPORTANT:
• Pre-bid Conference Sign-In Mandatory: The contractor attending today’s pre-bid conference is responsible for confirming his or her attendance by sending an email to Alma Wagner, Project Manager, at Alma.Wagner@longbeach.gov.
• Due: TODAY, Thursday, January 15, 2026 before 5:00 pm
SIGN IN EMAIL SHOULD INCLUDE:
• Contractor (Company Name), Address, City, State, Zip Code and Phone Number
• Company Representative who attended the Teams pre-bid meeting
• Indicate whether Prime or Subcontractor
• Failure to send the Pre-Bid Conference “Sign-In” e-mail will result in your bid being rejected as the Pre-Bid Conference is mandatory. See Notice Inviting Bids – Division A.
PRE-BID MEETING REQUIREMENTS
Convention Center @ Stairs
Rainbow Lagoon @ Swan Boats
Convention Center Promenade and Rainbow Lagoon
JOB-SITE WALK-THROUGH, SIGN-IN (OPTIONAL)
longbeach.gov/pw
Alma Wagner Alma.Wagner@longbeach.gov
562-570-5589
Thank You!