R-7243 Addendum 3.pdf

PDF 333 KB Posted

Attached to
R-7243 Convention Center Promenade and Rainbow Lagoon Curb Repairs
Solicitation number
PW-26-690
Issued by
California

About this file

This is Bid Addendum No. 3 issued by the City of Long Beach, Department of Public Works, for Plans and Specifications No. R-7243 covering Convention Center Promenade and Rainbow Lagoon Curb Repairs. The addendum provides revisions to Division H—General Requirements, specifically updating specifications for temporary security/construction fencing. The contractor is required to install temporary project site security/construction fencing as indicated on drawings or as required for safety. The fencing specifications include 6-foot high chain link fencing with a 6-foot high windscreen, posts spaced not to exceed 10 feet on centers, and galvanized materials meeting specific gauge requirements. Fencing must be set on pedestal bases, factoring in coastal wind conditions with additional weights and sandbags at each post. Gates must be fabricated of steel pipe with welded corners, and each gate requires a chain and padlock with two keys provided to the Owner's Authorized Representative. At substantial completion, the contractor is responsible for removing the barricade, backfilling and compacting fence footing holes, and patching and sealing existing surface paving. Communications regarding this work must be directed to Alma Wagner at the City of Long Beach, Department of Public Works, Project Management Bureau, prior to bid opening.

The addendum includes revisions to multiple construction phase plan sheets for both the Convention Center Promenade Repairs and Rainbow Lagoon Repairs, replacing references to "Temporary High Visibility Fence (THVF)" with "Temporary Security/Construction Fence" in legends, plans, and order of work sections. Specific sheets revised include C-21 through C-26 for Convention Center Promenade Repairs (Phases 1 through 5) and Sheets W-15, SP-16, and SP-17 for Rainbow Lagoon Repairs (Overall Plan and Phases 1-2). The addendum contains no attachments and requires contractor acknowledgment by company name, printed name, title, signature, and date prior to bid submission.

View the file

Other files

File Type Posted
R-7243 Addendum 1.pdf PDF
R-7243 Sign In-Sheet~1.pdf PDF
R-7243 Addendum 2.pdf PDF
Seller Guidance v4.pdf PDF
R-7243 Pre-Bid Presentation~1.pdf PDF
R-7243 CC and RL Plans.pdf PDF
R-7243 CC and RL Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R-7243 Addendum 3

February 6, 2026

BID ADDENDUM NO. 3

PLANS AND SPECIFICATIONS NO. R-7243

CONVENTION CENTER PROMENADE AND RAINBOW LAGOON CURB REPAIRS

NOTICE TO HOLDERS OF PLANS AND SPECIFICATIONS

Please note the following changes, clarifications, and additions:

SPECIFICATIONS:

1. DIVISION H – GENERAL REQUIREMENTS

o Revision: Revise paragraph as follows:

7-10.6.1 Temporary Security/Construction Fence. Add the following to this subsection: The Contractor shall install temporary Project site security/construction fence(s) indicated on Drawings or as required for safety and as specified herein. New or used material may be furnished. Security of Project site and contents is a continuous obligation of Contractor. Unless otherwise indicated or specified, security fence shall be constructed of 6-foot high chain link fencing with a 6-foot high windscreen that is stable through inclement weather conditions. Space posts not to exceed 10 feet on centers. Posts shall be of following nominal pipe dimensions:

terminal, corner, and gatepost 2 ½-inch, line posts 2-inch. Chain link fence shall be not less than #13 gauge, 2-inch mesh, and in one width. Posts, fence, and accessories shall be galvanized and as follows:

a) Shall be set on pedestal bases, unless required otherwise in writing by Construction Manager. Factor in wind conditions, note bracing and strapping of fencing as required in coastal environment. Additional weights and sandbags expected at each post/and or footer.

b) Fence fabric shall be attached to posts with #14 gauge tie wire at 16 inches on center. A #6 gauge steel tension wire with turnbuckles shall be installed at top and bottom of barricade fencing. Wire tie fabric to tension wires at 18" centers.

c) Windscreen/Graphic Fence Wrap shall be attached to fence fabric and steel tension wires at 18-inch centers with a minimum of #14 gauge tie wire.

Windscreen shall be maintained and all rips, tears, missing sections shall be corrected upon notification by the Construction Manager. Refer to section 7-

10.6.2 for the “Graphic Fence Wrap” guidelines.

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

d) Chain link fencing shall be free from barbs, icicles or other projections resulting from galvanizing process. Fence having such defects will be replaced even if it has been installed.

e) Gates shall be fabricated of steel pipe with welded corners, and bracing as required. Fence and fabric to be attached to frame at 12-inch centers. Provide all gate hardware of a strength and quality to perform satisfactorily until barricade is removed upon Substantial Completion of the Work. Each gate shall have a chain and padlock. Provide two gate keys to the Owner’s Authorized Representative (OAR). At Substantial Completion of the Work, remove barricade from Project site, backfill and compact fence footing holes.

Existing surface paving that is cut into or removed shall be patched and sealed to match surrounding areas.

f) At Contractor’s expense and without limitation remove or relocate fencing, fabric and barricades or other security and protection facilities as rapidly as required in order to provide for progress of the Work.

PLANS:

The applicable specifications to item TEMPORARY SECURITY/CONSTRUCTION FENCE are referenced in DIVISION H – GENERAL REQUIREMENTS Section 7-10.6.1 and Section 7- 10.6.2.

CONVENTION CENTER PROMENADE REPAIRS

1. Sheet C-21 – OVERALL CONSTRUCTION PHASE PLAN

a. Revision: LEGEND: Replace TEMPORARY HIGH VISIBILITY FENCE (THVF) with TEMPORARY SECURITY/CONSTRUCTION FENCE.

2. Sheet C-22 – CONSTRUCTION PHASE 1

a. Revision: LEGEND, PLAN and PHASE 1 – ORDER OF WORK: Replace

TEMPORARY HIGH VISIBILITY FENCE (THVF) with TEMPORARY

SECURITY/CONSTRUCTION FENCE.

3. Sheet C-23 – CONSTRUCTION PHASE 2

a. Revision: LEGEND, PLAN and PHASE 2 – ORDER OF WORK: Replace

4. Sheet C-24 – CONSTRUCTION PHASE 3

a. Revision: LEGEND, PLAN and PHASE 3 – ORDER OF WORK: Replace

5. Sheet C-25 – CONSTRUCTION PHASE 4

a. Revision: LEGEND, PLAN and PHASE 4 – ORDER OF WORK: Replace

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

6. Sheet C-26 – CONSTRUCTION PLAN PHASE 5

a. Revision: LEGEND, PLAN and PHASE 5 – ORDER OF WORK: Replace

RAINBOW LAGOON REPAIRS

1. Sheet W-15 – OVERALL CONSTRUCTION PHASE PLAN

a. Revision: LEGEND: Replace TEMPORARY 6’ HIGH VISIBILITY FENCE (THVF) with TEMPORARY SECURITY/CONSTRUCTION FENCE.

2. Sheet SP-16 – CONSTRUCTION PHASE 1

a. Revision: LEGEND and PLAN: Replace TEMPORARY HIGH VISIBILITY

FENCE (THVF) with TEMPORARY SECURITY/CONSTRUCTION FENCE.

3. Sheet SP-17 – CONSTRUCTION PHASE 2

a. Revision: LEGEND and PLAN: Replace TEMPORARY HIGH VISIBILITY

FENCE (THVF) with TEMPORARY SECURITY/CONSTRUCTION FENCE.

CONTACT: Before the Bid opening, prospective Bidders shall direct any communications regarding this Work to:

City of Long Beach, Department of Public Works Project Management Bureau 5th Floor, City Hall 411 W. Ocean Boulevard Long Beach, CA 90802 Attention: Alma Wagner / TidelandsCIP E-mail: Alma.Wagner@longbeach.gov / TidelandsCIP@longbeach.gov

Communications may be written or oral, but the City is not bound by any oral interpretation of the Contract Documents made by any City employee, nor does the City guarantee the accurate transcription of oral questions.

PREPARED BY: Alma Wagner

ACKNOWLEDGED BY:

Company Name

Print Name Title

Signature Date

Attachments:

None