This is a quotation document from DRL Sales, Inc. for an emergency vault toilet replacement project at Wayne Fitzgerrell State Recreation Area's Sailboat Harbor Boat Ramp in Illinois. The project scope includes supplying and installing a CXT Precast Concrete Tioga Special double vault toilet style restroom with polyethylene lined concrete vaults, simulated barn wood textured walls, and simulated cedar shake textured roof. The work encompasses demolition of the existing vault toilet and concrete apron, excavation to solid ground with placement of 12 inches of compacted CA-6 Aggregate base, crane services for offloading and setting the structure, formation and pouring of a 5-foot wide concrete apron on all sides of the building, formation and pouring of a 5-foot wide sidewalk from the front apron to a handicap accessible detachable warning at the parking lot, and backfill, grading, seeding, and straw application. The quote was submitted on January 15, 2026, and includes pumping out existing vaults by a sanitary waste disposal service.
The base bid total is $110,099, with alternate add options available including an upgrade to two stainless steel toilet risers for an additional $6,900 and the addition of two solar light kits for $3,500. The quotation explicitly excludes necessary permits, power company fees, overtime man hours, errors and omissions, unforeseen conditions, and items not listed in the included scope. The CXT Tioga Standard base features include simulated barnwood texture walls, white plastic toilet risers with lids, stainless steel grab bars, ADA-compliant signage with Braille, toilet paper holders, coat hooks, door stops, and polyethylene lined concrete vaults.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRL Sales, Inc.
P.O. Box 406 St. Libory, Illinois 62282
Phone: (618) 824-6606, Fax: (618) 824-6680 e-mail address: drlsales@egyptian.net
January 15, 2026
Re: Quote / Proposal Wayne Fitzgerrell State Recreation Area Emergency Vault Toilet Replacement at Sailboat Harbor Boat Ramp
DRL Sales, Inc. is pleased to quote all materials, labor and equipment required for construction of the above referenced project. Please note the following clarifications to our bid.
INCLUDES:
1. Supplying and Installing a CXT Precast Concrete – Tioga Special double vault toilet style restroom.
Includes two polyethylene lined concrete vaults, simulated barn wood textured walls, simulated cedar shake textured roof, offloaded and set up on site.
2. Pumping out existing vaults by a sanitary waste disposal service
3. Demo of existing vault toilet, vaults and concrete apron.
4. Removal and disposal of demo debris.
5. Excavate to solid ground and place 12” compacted CA-6 Aggregate base
6. Includes crane for setting off and setting the vaults and building.
7. After installation, backfill all over dig with compacted CA-6 Aggregate rock.
8. Form and pour 5’ wide concrete apron on the front, both sides and the back the building.
9. Form and pour 5’ wide sidewalk from front apron to HC detachable warning at parking lot.
10. Backfill ,grade, seed and straw.
CXT Tioga Standard Included Base Bid Features The Tioga standard features are listed below. Also available are a variety of added cost options available to suit your particular needs. See alternates add options & cost for added Options.
• Simulated barnwood texture walls with simulated cedar shake texture roof.
• White plastic toilet risers with lids.
• Stainless steel grab bars and ADA-compliant signage with Braille.
• Toilet paper holders, coat hooks, and door stops.
• Polyethylene lined concrete vault.
EXCLUDES:
1. The necessary permits
2. Power company fees
3. Overtime man hours
4. Errors and Omissions
5. Any Unforeseen Conditions
6. Anything not listed as included in above
Total Base Bid = $110,099
Alternate Add Options:
Alternate 1 : Upgrade the (2) toilet risers to stainless steel - Add $6,900
Alternate 2 : Add (2) Solar light kits - Add $3,500
Sincerely, Mark Albert Project Manager