This is a Questions and Answers document for a state and local contract opportunity issued by the City of Sun Prairie, Wisconsin's Department of Parks, Recreation & Forestry for lighting design and engineering services at the Wyndham Hills Pickleball Complex. The City is soliciting proposals from qualified vendors to provide design, engineering, and construction administration services for tournament-quality lighting at the facility. A topographic site survey has already been completed prior to the spring 2022 construction of the expanded facility, and LSI Lighting has completed a preliminary layout for the project. Project construction staking will not be part of the consultant's scope of work and can be completed either in-house or assigned as part of the contractor's bid package. Proposals were due on October 21, 2022 at 2:00 PM.
The total project budget is $75,000 and includes all design, engineering, construction documents, construction services, and construction costs. While lights, poles, and lighting controls may be sole-sourced or directly purchased from LSI Lighting, this arrangement has not been confirmed and will depend on identifying an existing contract to piggyback off of. No site visits, bidder conferences, or award dates are specified in this questions and answers document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
22-PRF36 Lighting Design & Engineering for Wyndham Hills Pickleball Complex Questions and Answers
Proposals due 10/21/2022 2:00 PM
1. Is the project budget of $75,000 for the design, engineering, construction documents, construction services? Or does $75,000 include construction costs?
The project budget of $75,000 includes all construction costs.
2. Has a topographic site survey been competed? Or does the consultant need to provide?
A site survey has been completed prior to the construction of the expanded facility in spring of 2022.
If any additional survey work is needed, the City would complete that in-house.
3. Has LSI Lighting completed a preliminary layout for the project?
Yes. LSI Lighting has completed a preliminary layout for the project.
4. Are the lights/poles/ lighting controls going to be sole sourced/direct purchased from LSI Lighting?
This is likely, but not confirmed as we will need to find an existing contract to piggyback off of.
5. Is project construction staking to be part of the consultant’s work?
No. This can be completed either in-house or be assigned as part of the bid package for the contractor.