Questions and Answers~11.docx
DOCX document 16 KB Posted
- Attached to
- EMA - GEMS Facility UPS Units - ARG
- Solicitation number
- 25-588IEMA-MGMTA-B-45482
- Issued by
- St. Clair County, Illinois
About this file
This document contains Questions and Answers related to an Open Market Bid issued by the State of Illinois Illinois Emergency Management Agency and Office of Homeland Security for the procurement of UPS Units. The bid, number 25-588IEMA-NCLRF-B-45018, requires the delivery and installation of UPS units at two locations - the Byron Nuclear Generating Station and a facility at 1301 Knotts. The bid specifies that the Knotts location unit will not require external battery modules, while the Byron unit will need two. The bid also confirms that all units will be delivered to the Knotts location, with the Byron unit then transported and installed at the Byron facility by IEMA personnel. The bid does not require any new maintenance bypass panels, as the agency will be utilizing its existing panels.
The document also indicates that the agency is seeking the same startup and maintenance services that were previously provided, referencing specific service codes. No other pricing, set aside, or funding details are provided in this Q&A document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GEMS 15 kVA UPS Technical Specifications - BY_Knotts.xlsx | XLSX spreadsheet | |
| standard terms and conditions~7.pdf | ||
| standard-illinois-certifications-v.23.1~62.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Illinois Illinois Emergency Management Agency and Office of Homeland Security GEMS Facility UPS Units
| Open Market Bid 25-588IEMA-NCLRF-B-45018 |
| Questions and Answers |
| Question: | Please confirm that the unit for 1301 Knotts has “0 EBM”. | |
| Answer: | We do not require an external battery module (EBM) at the Knotts St. Location. We only require the 2 EBMs for the Byron unit. Since the Knotts St unit is a test bed/ready spare and not actually sampling a reactor stack, it is not critical to have the extended runtime. | |
| Question: | Line 1 has delivery and install at the same address. Please confirm that this is correct. | |
| Answer: | Yes. All units will be delivered to 1301 Knotts address, from there the Byron unit will be delivered to the Byron nuclear facility and installed there by IEMA personnel. In the case of the Knotts St. unit, it will be delivered to Knotts St. and then installed at Knotts St. by IEMA personnel. We will require startup services at the Bryon Nuclear Generating Station and at the 1301 Knotts St. address. | |
| Question: | The description doesn’t call out any maintenance bypass. Most often a 9355 is paired with a bypass, does IEMA require or not? | |
| Answer: | We do not. We already have Maintenance Bypass Panels installed at all locations and will be utilizing our existing panels. | |
| Question: | Does IEMA want the same startup & service as previously provided for both locations/startups in this request? | |
| a. | UP05CXXX0015 startup service for 3phase systems | |
| b. | W1FL87NXXX0015 is the maintenance/service portion. |
Answer: Yes.