Questions and Answers-ISF B and G-Electrical Supplies~1.docx
DOCX document 16 KB Posted
- Attached to
- AGR-ISF B and G-Electrical Supplies
- Solicitation number
- 25-406AGR-BLDG4-B-46001
- Issued by
- Illinois
About this file
This is a Questions and Answers document for the Illinois Department of Agriculture's (IDOA) bid for electrical supplies for the Bureau of Building and Grounds. The document addresses vendor inquiries about product substitutions, pricing, and quantity specifications for various electrical equipment and supplies. The document clarifies that vendors can substitute equivalent brands for items that are not marked with an asterisk or grayed out, items showing zero quantity should be priced as quantity of 1, and certain items marked in gray cells do not allow substitutions.
Regarding pricing terms, the document addresses price fluctuations, particularly for commodities like copper wire that experience regular 5-10% price variations. After the initial one-year contract period, vendors may request price adjustments if their costs increase by more than 5% from the previous year. Such adjustments require written proof of the increase and approval from IDOA. The document also addresses concerns about obsolete items, such as metal halide bulbs, indicating that current specifications should be priced as listed, with alternative options to be considered when items are no longer manufactured.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AGR-ISF B and G-Electrical Supplies Questions and Answers
This amendment is to provide questions and answers that have been received thus far.
1. In the excel file, there is a column for "Vendor Alternative". This field can be used to recommend an equivalent brand and model, correct?
1. Yes, they can substitute an equivalent brand for the items that do not contain the asterisk and grayed out.
2. Many items have a quantity of zero listed. Does this indicate that none are needed? Should a price be submitted for these items?
2. Price these out as quantity of 1.
3. A number of items (e.g. Cell "D125", Crouse Hind FD 029) have grayed out cells for "Vendor Alternative". What is intended by this? Are no substitutions allowed?
3. No substitutions allowed.
4. Some items may not be manufactured in the future, such as metal halide bulbs. Would there be options to recommend LED bulbs or new fixtures?
4. Price out what is on the list. When it is not manufactured anymore, we will look at options at that time.
5. While most pricing is pretty static with minor increases by manufacturers, some commodities fluctuate a lot. How shall we consider wire pricing, when copper goes up and down by 5-10% regularly, including in year 1?
5. Section 2.3 of the IFB refers to allowable economic adjustments:
1. After the initial one year contract period, if the Vendor’s cost for any of the Unit prices covered by this contract should increase more than 5% from the previous year’s amount, the Vendor(s) shall, upon submission of written proof of such increase to, and the approval by the Illinois Department of Agriculture (IDOA), be entitled to adjust the price by an amount sufficient to compensate the Vendor(s) completely and precisely for such increase.