Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document contains Questions and Answers related to a competitive solicitation (DES Competitive Solicitation 23723) issued by the Washington State Department of Enterprise Services (DES) for the purchase of prefabricated and modular bridges. The solicitation is intended for use by Washington state agencies and political subdivisions in the state, including counties, cities, and special districts.

The key details include a revision to the delivery lead time, which has been amended to 150 days for all bridge orders, and the removal of the precast concrete backwall requirement from the Category 1 Vehicle Concrete Slab Bridge option. The solicitation covers a range of bridge types and sizes, including both trail and vehicular bridges, with various material and design options. Pricing terms, set-asides, and other financial details are not provided in this document.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DES Competitive Solicitation 23723 – Prefabricated and Modular Bridges Questions and Answers Q: Exhibit B-2 – Performance requirements; #3 -Delivery lead time states:

Delivery Lead Time. The State is seeking a Contractor that can deliver needed products in a timely manner and offer alternative solutions when the ordered products are delayed.

To meet minimum acceptable standard [0%]: At a minimum, the bidders must commit to deliver all orders within 30 days of the order receipt for trail bridges and 150 days for vehicle bridges.

Question: Why not 150 days for both trail and vehicular (steel) bridges? 30 days is not a realistic timeframe to complete design and drafting for submittal drawings, purchaser review and approval of submittals, acquisition of any materials not already on hand, fabrication, and shipping of a bridge. Four of the eight options for the Category 2 bridges listed in exhibit C include wood decking. After the approval of submittal drawings, it often takes more than 30 days to obtain custom milled timber packages for wood decks. Can DES consider changing the lead time to at least150 days for each category? 180 days would be more feasible as it is impossible to predict all market factors that contribute to lead times throughout the term of this contract.

A: Delivery lead time has been amended to 150 days for all bridge orders.

Q: Amended Exhibit C, Category -1 Vehicle, Option #3 concrete slab bridge:

Category 1 Vehicle Concrete Slab Bridge 14 Ft Wide X 20 ft length precast concrete slab, 16" concrete curb, precast concrete footing, precast concrete backwall

Question: Why would there be need for a backwall on a slab style of bridge unless the foundation was other than a simple grade beam? Are bidders to assume a pedestal foundation and if so, can DES provide a dimensional description?

A: Removed “precast concrete backwall” from bridge description.