Questions and Answer #2.pdf

PDF 73 KB Posted

Attached to
ITB - Janitorial Services Region 5 HQ
Solicitation number
S-73000-00011081
Issued by
Umatilla County, Oregon

About this file

The document appears to be a set of Questions and Answers related to Invitation to Bid (ITB) 73000-00011081 for Janitorial Services at the Oregon Department of Transportation (ODOT) Region 5 Headquarters and Lab buildings. The ITB seeks a qualified contractor to provide janitorial services for two buildings, with Building B having 6 bathrooms and approximately 1,118 square feet of hard floors, and Building C having 1 bathroom and approximately 405 square feet of hard floors. The buildings will require 5 days per week of service for the tasks listed under Exhibit A, with details on the frequency of services provided in the Exhibit.

The ITB requires the contractor to provide janitorial services according to the specifications outlined in the Scope of Work and other exhibits. Pricing terms, set-asides, funding requirements, and other salient information are not directly addressed in the provided document, which focuses solely on answering specific questions related to the square footage, bathroom counts, and service frequencies for the two buildings.

View the file

Other files

File Type Posted
Questions and Answer #1.pdf PDF
11081_bidcover.docx DOCX document
Region 5 HQ Exhibit A.pdf PDF
ITB Janitorial Region 5 HQ.pdf PDF
Request for Quote_final~1.pdf PDF
Sample Contract Region 5 HQ and LAB.pdf PDF
0001181 Preliminary Bid Results~1.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers #2

ITB 73000-00011081

Janitorial Services Region 5 HQ and Lab

Question 1. What is the (square foot) amount of flooring that needs to be stripped and waxed in each building, how many bathrooms are in each building and what is the number of days per week the buildings need to be serviced?

Answer: Building B has 6 bathrooms and approximately 1,118 square feet of hard floors.

Building C has 1 bathroom and approximately 405 square feet of hard floors. The total square footage for each building is listed under Exhibit A, Section 2. Facility Location.

Buildings will be serviced 5 days per week for tasks listed as Daily Services in Exhibit A, Section 18. Task Performance Standards. Information regarding the frequency of services is listed under Exhibit A, Section 7. Contractors Work Schedule and Exhibit A, Section 18. Task Performance Standards.