This document is a Question and Answer (Q&A) Set #5 related to Invitation for Bid (IFB) DGS 56956 for Alternative Fuel Vehicles issued by the State of California, Department of General Services, Procurement Division (DGS-PD). The IFB covers the requirements of the State of California and is available for use by participating local agencies. The contract resulting from this solicitation will be mandatory for all State of California Departments.

Regarding pricing, bid prices are to be firm fixed for the contract term, including any optional year extensions, unless a price adjustment of up to 3% is granted with each new model year. A price increase of more than 3% may be considered in the event of a major vehicle change or unusual market circumstances. Contractors must price protect the contracted price for the duration between the price increase request and the time the increase is processed. The Contractor's profit margin must remain unchanged through the contract term.

View the file

Other files

File Type Posted
Addendum_1_-_Cover_Sheet.docx DOCX document
Addendum_2_-_Cover_Sheet.docx DOCX document
Attachment_4_-_Technical_Questionnaire_-_Addendum_1.xlsx XLSX spreadsheet
Addendum_3_-_Cover_Sheet.docx DOCX document
Attachment_1_-_Pricing_Workbook_-_Addendum_3.xlsx XLSX spreadsheet
IFB_Event_ID_0000031286_Addendum_3.docx DOCX document
Addendum_4_-_Cover_Sheet.docx DOCX document
Attachment_1_-_Pricing_Workbook_-_Addendum_4.xlsx XLSX spreadsheet
Attachment_2_-_Bid_Specification_2310-BS-0194616-1.pdf PDF
Attachment_5_-_Narrative_Response.docx DOCX document
Q_A_Set__1.docx DOCX document
Attachment_4_-_Technical_Questionnaire_-_Addendum_4.xlsx XLSX spreadsheet
IFB_Event_ID_0000031286_Addendum_4.docx DOCX document
Q_A_Set__3.docx DOCX document
APP_Cover_Page.docx DOCX document
Attachment_1_-_Pricing_Workbook_-_Addendum_1.xlsx XLSX spreadsheet
QA_Set__2.docx DOCX document
Question___Answer_Set__4.docx DOCX document
Attachment_3_-_Bid_Specification_2320-BS-0194616-2.pdf PDF
IFB_Event_ID_0000031286_Addendum_2.docx DOCX document
Attachment_4_-_Technical_Questionnaire_Addendum_3.xlsx XLSX spreadsheet
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP DGS 56956Question and Answer (Q&A) Set #1
DRAFT (rev 4/8/2009)
Event ID #:0000031286Alternative Fuel Vehicles
November 7, 2024

Question and Answer (Q&A) Set # 5

Item
IFB Section
Question
State’s Response
5-1
IFB Section 51, Price Adjustments
Are bid prices fixed unless a model year year change occurs? Also, are price adjustments limited to a 3% unless there is a major vehicle change?

Yes, all prices shall be firm fixed for the contract term, including any optional year extensions, unless a price adjustment is granted.

A price increase may be requested with each new model year and should not exceed 3 percent. In the event of a major vehicle change, or unusual market circumstances, a price increase of more than 3 percent may be considered.

5-2
IFB Section 51, Price Adjustments
If model year 2026 incentives for Government fleet and retail were to be dramatically reduced, meaning the contract price could not be sustained, could the dealer withdraw or make the model unavailable? How does a dealer protect themselves from an OEM’s pricing and incentive fluctuations?
As stated in answer to question 5-1, in the event of a major vehicle change, or unusual market circumstances, a price increase of more than 3 percent may be considered.

Contractor must price protect the contracted price for the duration between the price increase request and the time the increase is processed. If the Contractor is unable to honor the price protection, the Contractor’s vehicle will be unavailable for ordering until the price increases have been evaluated and approved.

Please note, the Contractor’s profit margin shall remain unchanged through the contract term including any extension periods.