This document is a Question and Answer (Q&A) Set #1 DRAFT related to RFP DGS 56956 for Alternate Fuel Vehicles. The solicitation is being issued by the State of California Department of General Services (DGS). The RFP seeks bids for various categories of alternate fuel vehicles, including medium-duty and heavy-duty trucks, with delivery required by October 14, 2024. Multiple awards are not part of this solicitation; instead, awards will be made to the single responsive and responsible bidder with the lowest cost for each individual line item. Addendums have been issued to revise certain technical requirements, such as decreasing the GCWR for medium-duty and heavy-duty trucks. This solicitation does not include a bidder's conference, and all questions must be directed to the Procurement Official in writing no later than four working days prior to the bid due date.

Regarding pricing, the State will allow contractors to option up any line item, but the included options cannot cause the vehicle to conflict with any other line on any other vehicle contract. Bidders that desire to propose multiple vehicles for a specific line-item must submit separate Pricing Workbooks for each vehicle. The resulting contracts from this solicitation will not replace the existing Alternate Fuel/Electric contracts, which will remain in effect. Bidders are not required to bid CARB-aligned vehicles, but the resulting contracts are subject to Vehicle Manufacturer Purchasing Restrictions per the State Administrative Manual.

View the file

Other files

File Type Posted
Attachment_2_-_Bid_Specification_2310-BS-0194616-1.pdf PDF
Attachment_5_-_Narrative_Response.docx DOCX document
Attachment_4_-_Technical_Questionnaire_-_Addendum_4.xlsx XLSX spreadsheet
IFB_Event_ID_0000031286_Addendum_4.docx DOCX document
Q_A_Set__3.docx DOCX document
Addendum_1_-_Cover_Sheet.docx DOCX document
Addendum_2_-_Cover_Sheet.docx DOCX document
Attachment_4_-_Technical_Questionnaire_-_Addendum_1.xlsx XLSX spreadsheet
Addendum_3_-_Cover_Sheet.docx DOCX document
Attachment_1_-_Pricing_Workbook_-_Addendum_3.xlsx XLSX spreadsheet
IFB_Event_ID_0000031286_Addendum_3.docx DOCX document
Addendum_4_-_Cover_Sheet.docx DOCX document
Attachment_1_-_Pricing_Workbook_-_Addendum_4.xlsx XLSX spreadsheet
Question___Answer_Set__5.docx DOCX document
APP_Cover_Page.docx DOCX document
Attachment_1_-_Pricing_Workbook_-_Addendum_1.xlsx XLSX spreadsheet
QA_Set__2.docx DOCX document
Question___Answer_Set__4.docx DOCX document
Attachment_3_-_Bid_Specification_2320-BS-0194616-2.pdf PDF
IFB_Event_ID_0000031286_Addendum_2.docx DOCX document
Attachment_4_-_Technical_Questionnaire_Addendum_3.xlsx XLSX spreadsheet
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP DGS 56956Question and Answer (Q&A) Set #1
DRAFT (rev 4/8/2009)
Event ID #:0000031286Alternate Fuel Vehicles
October 14, 2024

Question and Answer (Q&A) Set # 1

Item
IFB Section
Question
State’s Response
1-1
IFB Section 4 – Method of Award
On prior State Contracts, similar to this, there have been multiple awardees per line, giving end users a choice. Will that be the case on this bid?
Awards will be made to the single responsive and responsible Bidder with the lowest cost, including all applicable preference and incentive calculations for each individual line item. Multiple awards are not part of this solicitation.
1-2
Attachment 4 – Technical Questionnaire
Attachment 4 -Technical Questionnaire, MD-HD Trucks CLIN 12, shows a requirement for GVWR (Gross Vehicle Weight Rating) while Attachment 1 – Contract Pricing shows a requirement for GCWR (Gross Combined Weight Rating). Which is the actual requirement for this line item?

The requirement for MD-HD Trucks CLIN 12 is for GCWR.

See Attachment 4 – Technical Questionnaire – Addendum 1 for revised requirement.

1-3
Attachment 1 – Pricing Workbook
Would the State consider decreasing the GCWR for MD-HD Trucks CLIN 12 to 66,000lbs?
Yes, the State has decreased the GCWR requirement for MD-HD Trucks CLIN 12 to 66,000lbs.

See Attachment 1 – Pricing Workbook – Addenedum 1 for revised requirements.

1-4
Attachment 1 – Pricing Workbook
For MD-HD Trucks CLIN 23, did the State intend to solicit for a Turck Cab and Chassis or a Truck Tractor?
The State’s intent for MD-HD Trucks CLIN 12 was to solicit for a Truck Tractor.

See Attachment 1 – Pricing Workbook – Addenedum 1 for revised requirements.

1-5
IFB Section 62 – Delivery Locations
Would it be possible to amend the mileage on the CNG cab and chassis to 2500 miles as many of this are now driven from the OEMs to the dealership, and may need additional transportation to body companies for upfitting.
Mileage requirements for delivered vehicles will remain the same.

Unless pre-arranged between the dealer and the ordering agency, vehicles delivered with more than 50 miles on the odometer may be charged 50 cents per mile in excess of 50 miles. Vehicles with more than 500 miles on the odometer may not be accepted.

Cab and Chassis trucks that require driving from an out-of-state factory may exceed the 500 mile or less expectation. The Contractor shall notify the ordering Department at the time of purchase order execution.

1-6
IFB Section 65 – Free on Board (F.O.B.) Destination
Should the price of delivery within a certain radius of Sacramento be included in the cost of the vehicle?
Dealers shall deliver vehicles to State or local agencies located in Sacramento County at no additional cost for delivery. If the Purchase Order indicates delivery outside Sacramento County, the dealer and agency may negotiate delivery costs.
1-7
Attachment 1 – Pricing Workbook
Would the State consider the addition of a light duty cargo van category?
Yes, an electric cargo vans category has been added.

See Attachment 1 – Pricing Workbook – Addenedum 1 for added line items.

1-8
IFB Section 4 – Method of Award
What is the protocol for the EVs available on contracts 1-22-23-10B-E, 1-22-23-20B-K, 1-22-23-23B-I, and 1-23-23-22A-D & F-G?

· Are current contractors allowed to re-bid?

· Are they ineligible since they’re on an active contract?

· Will they be amended from the current contract and transferred to this one?

Current Contractors can participate in the solicitation, however, the State will not accept bids for vehicles already on Statewide Contracts 1-22-23-10B-E, 1-22-23-20B-K, 1-22-23-23B-I, and 1-23-23-22A-D & F-G.

All line items associated with these contracts will remain under their respective agreements.

1-9
IFB Section 4 – Method of Award
Will the State accept vehicle models for this bid that are already on the existing state contract?
The State will not accept bids for vehicles already on Statewide Contracts 1-22-23-10B-E, 1-22-23-20B-K, 1-22-23-23B-I, and 1-23-23-22A-D & F-G.
1-10
N/A
Will the resulting contracts be replacements for the existing Alternate Fuel/Electric contract?

No, the existing contracts will continue to remain in effect.

1-11
IFB Cover Page
Can the timeline for this comprehensive solicitation be extended to more than 20 days?

At this time, the bid due date will remain the same.

1-12
Attachment 1 – Pricing Workbook
Would the state consider reducing the minimum kWh requirement for CLIN 15 – MD-HD Trucks? This will allow for increased competition.

Yes, the kWh minimum requirement for MD-HD Trucks CLIN 15 has been updated.

See Attachment 1 – Pricing Workbook – Amendment 1 for revised requirements.

1-13
IFB Section 13 – Bidder Questions
Will there be any formal bidders conference or opportunity for Q&A in advance of the submission due date?
This solicitation does not include a Bidder’s Conference.

All questions, comments, and concerns should be immediately directed to the Procurement Official, in writing, no later than four working days prior to bid due date. All questions and/or concerns shall be directed to Eugene.Shemereko@dgs.ca.gov.

1-14
IFB Section 52 - Options
Do we need to submit a separate bid for all iterations of our vehicle?

The State allows Contractors to option up any line item (e.g., larger battery pack, dual motor). However, the included options cannot casuse the vehicle to conflict with any other line on any other vehicle contract.

Bidders that desire to propose multiple vehicles for a specific line-item, must submit separate Pricing Workbooks for each vehicle.

1-15
IFB Section 21 – Proposed Products
Can bidders submit bids for vehicles manufactured by these OEMs listed above? OR are dealerships still able to submit bids for vehicles manufactured by non-CARB Aligned OEMs and be eligible for award?

Bidders are not required to bid CARB-aligned vehicles, however, the resulting contracts are subject to Vehicle Manufacturer Purchasing Restrictions State Administrative Manual (SAM) Section 4121.8.

1-16
N/A
If we awarded a contract to supply Alternative Fuel Vehicles manufactured by non-CARB Aligned OEMs, do the dealerships have to be independently owned and not associated with an OEM that is not considered "CARB Aligned"?
The solicitation does not include any restrictions regarding whether dealerships must be independently owned or associated with an OEM that is not considered "CARB Aligned." Therefore, dealerships that are associated with non-CARB Aligned OEMs are not prohibited from participating in this soliciation.