This is a Question and Answer document for Illinois Department of Human Services' Invitation for Bid (IFB) for carpet removal and epoxy flooring installation at the Alton Forensic Center, 4500 College Ave., Alton, IL. The project encompasses approximately 16,230 square feet across patient and non-patient areas, with work organized in multiple phases: Units A and C will each require two phases, Unit B will be completed in one phase, and remaining areas will be divided into several phases. Work hours are Monday through Friday, 7:00 AM to 4:30 PM, with additional hours requiring facility approval. The scope includes comprehensive substrate preparation, crack filling for cracks 1/16 inch or larger, mechanical profiling, and installation of seamless epoxy flooring with a finished thickness of 50 MILS and integral cove base (3/4 inch) extended 4 inches up walls in all designated areas. The epoxy system consists of a primer, base coat, and matte-finish topcoat with a standard flake formula applied to all areas except patient rooms. A board sample will be required for approval. The contractor must attend the mandatory pre-bid conference; bids are due November 5, 2026, with questions due by 5:00 PM on October 23, 2026. The contract term extends from the last-dated signature through June 30, 2027.
The project is subject to Illinois prevailing wage requirements. Bidders must attend the pre-bid conference in person; sub-contractors cannot sign in on behalf of the bidding vendor, and this attendance requirement is a condition of bid responsiveness though not part of the formal contract scope. A Business Enterprise Program (BEP) utilization goal of 5% applies, requiring submission of a completed BEP Utilization Plan with documented BEP-certified subcontractor participation or good faith efforts as a condition of responsive bid status. Contractors must perform a minimum of 51 percent of total contract work with permanent, full-time W-2 employees employed for at least 30 consecutive days prior to bid submission; temporary labor, 1099 contractors, and staff augmentation do not qualify toward self-performance. General Commercial Liability insurance of $1,000,000 per occurrence and $2,000,000 annual aggregate, plus $1,000,000 Auto Liability per occurrence, are required, with the State named as additionally insured. A surety bond in an amount not less than the bid amount from a company rated at least A is mandatory. AMHC will be responsible for moving furniture as needed. Bidders should estimate all costs related to substrate preparation defects, moisture concrete readings outside system specification, and crack filling; the document directs contractors to bid the amount necessary for these contingencies rather than accepting predetermined limits.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BEP Utilization Plan v.26.1~11.pdf | ||
| vendor-disclosure-formerly-forms-a-v27-1-2026-0624~10.docx | DOCX document | |
| RMO150~28.docx | DOCX document | |
| ipg-active-registered-vendor-disclosure-formerly-forms-b-v-26-1-8-26-2025-1~46.docx | DOCX document | |
| invitation-for-bid-vendor-instructions-and-requirements-B-54468.docx | DOCX document | |
| B-54468 Pre-Bid Meeting Sign In Sheet.pdf | ||
| AFC Floor Prints.pdf | ||
| invitation-for-bid-offer-to-the-state-of-illinois-B-54468.pdf | ||
| DHS IFB AMHC AFC Flooring B-54468.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMHC Carpet Removal and Epoxy Flooring Install Questions and Answers B-54468
1. How many phases?
a. A and C Units will be done in 2 phases each. B Unit will be one phase. The remaining areas will be broken into several phases.
2. What are the hours to be worked?
a. Work hours will be Monday thru Friday 7am -4:30pm. Additional work hours outside these hours will need to be approved by facility.
3. There are 3 coats listed in the specs. Do we want two topcoats or primer, base and topcoat? How are the coats to be applied?
a. Primer, base, and topcoat.
4. Will we have a mock-up in place or a board sample?
a. Board sample
5. Will this be a standard flake formula?
a. Yes
6. Is the topcoat to be a gloss or matte finish?
a. Matte finish.
7. Who is responsible for the movement of furniture out of the work area?
a. AMHC will move the furniture as needed.
8. Is the project subject to prevailing wage?
a. Yes
9. Per scope of work Sec 1.2: 3/4'' cove with epoxy extended 4 inches up the wall with a finish thickness of 50 MILS is required in designated areas. Can you provide which of the following areas are considered designated and shall receive integral cove base?
a. All areas will require the integral cove.
10. Per scope of work Sec 1.2: Comprehensive substrate preparation including defects. Would it be acceptable to include a limit of 500 sqft in Bid?
a. Bid the amount that you estimate would be necessary.
11. Per scope of work Sec 1.2: Cracks 1/16'' or larger in width shall be filled in with concrete filler prior to floor finishing. Would it be acceptable to include a limit of 1,000LF in Bid?
a. Bid the amount that you estimate would be necessary.
12. Can a propane grinding machine be used (machine specs will be provided)?
a. Yes, proper ventilation of area will be required if continuously running.
13. If moisture concrete reading is out of system specification how should this be priced?
a. Bid the amount that you estimate would be necessary.
14. What kind doorway transition strip should be installed where epoxy flooring meets VCT flooring?
a. Moisture resistant Heavy Duty T-Moulding
15. According to Bid Solicitation Pre Conference Notes- Bidding vendor must attend. Sub-Contractors cannot sign in for bidding vendor- Is this requirement to be included in Scope of Work Document Sec 1.3 Milestones and Deliverables?
a. This requirement doesn’t need to be added as part of the contract. It is a requirement that will determine a responsive quote.
| 16. | Please post sign-in attendance sheet in amendment. | |
| a. Sign-in sheet will be posted. |
File details come from the government source that posted it. Updated .