This is a Notice Inviting Bids issued by the Antelope Valley-East Kern Water Agency for the Quartz Hill Water Treatment Plant Clearwell 1 & 2 Recoating project (Project No. CP 26-01). The project involves the interior and exterior recoating of two 9-million-gallon welded steel potable water tanks located at 6500 West Avenue N, Palmdale, California. Work on Clearwell No. 1 includes interior surface preparation, structural steel repairs, seismic upgrades, ladder and roof hatch replacement, vent screen and tank vent installation, and complete recoating using 100% solids epoxy, along with exterior surface preparation and recoating with epoxy primer and urethane topcoat, including excavation around the tank to repair buried coal tar epoxy coating. Work on Clearwell No. 2 is limited to exterior surface preparation and recoating with epoxy primer and urethane topcoat. Sealed bids must be submitted by 2:00 p.m. on September 2, 2026. A mandatory pre-bid meeting and site visit are required on August 19, 2026 at 11:00 a.m., with failure to attend rendering a bid non-responsive. Written questions must be submitted by 5:00 p.m. on August 26, 2026. The project schedule is 250 calendar days, with work on Clearwell 1 not permitted to begin until November 1, 2026. Bidders may obtain electronic copies of the Contract Documents by emailing Joseph Roberts at jroberts@avek.org.
Each bid must be accompanied by a bid security of no less than 10 percent of the total bid amount in the form of a cash deposit, cashier's check, certified check, or Bidder's Bond from a California-admitted Surety insurer. Upon contract award, the successful contractor must provide faithful performance and payment bonds each equal to the contract price within 15 days or face forfeiture of bid security. Bidders must possess a valid California State Contractors License Board Class A General Engineering Contractor license and Class C-33 Painting and Decorating Contractor license at time of bid submission, and a current City of Palmdale business license. All contractors and subcontractors must be registered with the California Department of Industrial Relations under Labor Code Section 1725.5, and prevailing wage requirements apply. Five percent of progress payments will be withheld as retention, which may be substituted with securities deposited with the Agency or a State or federally chartered bank at the contractor's expense. The Agency reserves the right to reject any or all bids and to waive any irregularities or informalities as deemed in its best interest.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No: CP 26-01 QHWTP Clearwell 1 & 2 Recoating NIB-1 Notice Inviting Bids
July 2026
NOTICE INVITING BIDS
FOR
QUARTZ HILL WATER TREATMENT PLANT CLEARWELL 1 & 2 RECOATING
[the “Project”]
PROJECT NO: CP 26-01
NOTICE IS HEREBY GIVEN that Antelope Valley - East Kern Water Agency (the “Agency”) invites sealed Bids for the Project. The Agency will receive such Bids at its Administrative Office, 6500 West Avenue N, Palmdale, CA 93551 up to 2:00 p.m. on September 2, 2026 at which time they will be publicly opened and read aloud.
SCOPE OF WORK. The Project includes, without limitation, furnishing all necessary labor, materials, equipment, and other incidental and appurtenant Work necessary to satisfactorily complete the Project, as more specifically described in the Contract Documents. This Work will be performed in strict conformance with the Contract Documents, permits from regulatory agencies with jurisdiction, and applicable regulations. The quantity of Work to be performed and materials to be furnished are approximations only, being given as a basis for the comparison of Bids. Actual quantities of Work to be performed may vary at the discretion of the Agency Engineer.
Discrepancies in, and/or omissions from the Bid or Contract Documents or questions as to their meaning shall be immediately brought to the attention of the Agency by submission of a written request for an interpretation or clarification to the Agency. Such submission, if any, must be sent to Joseph Roberts at jroberts@avek.org. Questions must be submitted by 5:00 p.m. on August 26, 2026. Questions received after this date and time may not be answered.
Any interpretation of the Contract Documents will be made only by written addenda duly issued by the Agency. The Agency will not be responsible for any explanations or interpretations provided in any other manner. No person is authorized to make any oral interpretation of any provision in the Contract Documents to any bidder, and no bidder should rely on any such oral interpretation.
In general, the WORK shall consist of interior and exterior recoating of two 9-million-gallon water tanks. The WORK includes but is not limited to the following:
A. Mobilize and demobilize all required equipment and labor required to perform the
WORK.
B. Quartz Hill Clearwell No. 1 – 9-million-gallon Partially Buried Welded Steel Potable Water Tank
a. Interior: Surface preparation, structural steel repairs, seismic upgrades, ladder replacement, replacement of existing roof hatch, replacement of existing vent screens, installation of new tank vents, and recoating of entire tank using 100% solids epoxy.
b. Exterior: Surface preparation and recoat of entire existing tank using epoxy primer and urethane topcoat. Excavating around the tank to repair buried coal tar epoxy coating.
QHWTP Clearwell 1 & 2 Recoating NIB-2 Notice Inviting Bids
July 2026
C. Quartz Hill Clearwell No. 2 – 9-million-gallon Welded Steel Potable Water Tank
a. Interior: None
b. Exterior: Surface preparation and recoat of entire existing tank using epoxy primer and urethane topcoat.
Project Location
Both tanks are located at 6500 W Avenue N, Palmdale, CA, 93551. The two tanks are separated by Avenue N.
Schedule of Construction
WORK inclusive of providing all materials, labor, equipment, ancillary/temporary works, mobilization/demobilization, site cleanup and project close out shall be accomplished in accordance with the following schedules:
A. Baseline Project Schedule 250 calendar days.
B. Due to an ongoing construction project, the CONTRACTOR will not be permitted to start work on Clearwell 1 until November 1, 2026.
OBTAINING BID DOCUMENTS. Bidders may obtain copies electronic of the Plans, Specifications and other Contract Documents by emailing Joseph Roberts, at jroberts@avek.org. Hard copies of Contract Documents will not be provided.
MANDATORY PRE-BID MEETING AND SITE VISIT. A mandatory pre-bid meeting will be held on August 19, 2026 at 11 a.m. at 6500 West Avenue N., Palmdale, CA, followed by a mandatory site visit. Every Bidder is required to attend the pre-bid meeting and Project site visit. Failure of a Bidder to attend will render that Bidder’s Bid non-responsive. No allowances for cost adjustments will be made if a Bidder fails to adequately examine the Project site before submitting a Bid.
REGISTRATION WITH THE DEPARTMENT OF INDUSTRIAL RELATIONS. In accordance with Labor Code Sections 1725.5 and 1771.1, no contractor or subcontractor shall be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, unless currently registered and qualified to perform public work pursuant to Section 1725.5 [with limited exceptions for bid purposes only under Labor Code Section 1771.1(a)].
PREVAILING WAGES. In accordance with Labor Code Section 1770 et seq., the Project is a “public work.” The selected Bidder (Contractor) and any Subcontractors shall pay wages in accordance with the determination of the Director of the Department of Industrial Relations (“DIR”) regarding the prevailing rate of per diem wages. Copies of those rates are on file with the Agency, and are available to any interested party upon request. The Contractor shall post a copy of the DIR’s determination of the prevailing rate of per diem wages at each job site. This Project is subject to compliance monitoring and enforcement by the DIR.
BONDS. Each Bid must be accompanied by a cash deposit, cashier’s check, certified check or Bidder’s Bond issued by a Surety insurer, made payable to the Agency and in an amount not less than ten percent (10%) of the total Bid submitted. Personal or company checks are not
QHWTP Clearwell 1 & 2 Recoating NIB-3 Notice Inviting Bids
July 2026 acceptable. Upon Contract award, the Contractor shall provide faithful performance and payment Bonds, each in a sum equal to the Contract Price. All Bonds must be issued by a California admitted Surety insurer using the forms set forth in the Contract Documents, or in any other form approved by the Agency General Counsel. Failure to enter into the Contract with the Agency, including the submission of all required Bonds and insurance coverages, within fifteen (15) Days after the date of the mailing of written notice of contract award to the Bidder, shall subject the Bid security to forfeiture to the extent provided by law.
LICENSES. Each Bidder shall possess a valid Class A General Engineering Contractor license and a valid Class C-33 Painting and Decorating Contractor license issued by the California State Contractors License Board at the time of the Bid submission, unless this Project has any federal funding, in which case the successful Bidder must possess such a license at the time of Contract award. The successful Contractor must also possess a current business license issued by the City of Palmdale.
RETENTION SUBSTITUTION. Five percent (5%) of any progress payment will be withheld as retention. In accordance with Public Contract Code Section 22300, and at the request and expense of the Contractor, securities equivalent to the amount withheld may be deposited with the Agency or with a State or federally chartered bank as escrow agent, which shall then pay such moneys to the Contractor. Upon satisfactory completion of the Project, the securities shall be returned to the Contractor. Alternatively, the Contractor may request that the Agency make payments of earned retentions directly to an escrow agent at the Contractor’s expense. No such substitutions shall be accepted until all related documents are approved by the Agency General Counsel.
BIDDING PROCESS. The Agency reserves the right to reject any Bid or all Bids, and to waive any irregularities or informalities in any Bid or in the bidding, as deemed to be in its best interest.
By:
07/31/2026
Matthew Knudson General Manager Antelope Valley-East Kern Water Agency
Date
QHWTP Clearwell 1 & 2 Recoating NIB-4 Notice Inviting Bids
July 2026