07-12-2016_Pre-proposal_Conference_(both_sessions).pdf
PDF 162 KB Posted
- Solicitation number
- QTA0016GBA0002
- Issued by
-
GSA Federal Acquisition Service
About this file
07-12-2016 Pre-proposal Conference (both sessions)
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES OF AMERICA
GENERAL SERVICES ADMINISTRATION
ALLIANT 2 SMALL BUSINESS PRE-PROPOSAL CONFERENCE
Washington, D.C.
Tuesday, July 12, 2016
1 PARTICIPANTS:
2 Welcome:
3 DEAN COLE
Business Management Specialist, ITS
GWAC Success and Overview:
MICHAEL McFARLAND
6 Director of Acquisition Operations, ITS
7 GWAC Program:
8 CASEY KELLEY
Acting GWAC Program Director & A2/A2SB Project
9 Manager, ITS
10 A2SB RFP Overview:
11 GREG BYRD
Alliant 2 Small Business Procuring Contracting
12 Officer
14 * * * * *
1 P R O C E E D I N G S
2 (8:02 a.m.)
3 MR. COLE: We just got the thumbs up
4 from out front. It looks like the line is
5 dwindling down, so we'll go ahead and get started.
6 We've got a lot of stuff to cover and only a few
7 hours to do it in.
8 But thanks for showing up. I know it's
9 not easy to get here, and then it's even harder to
10 get in the building, so we do appreciate your
11 being here.
12 The seats, I mean, the registration
13 filled up, but I'm still seeing a few empty seats.
14 Hopefully, we will have some people wandering in a
15 little bit later.
16 Now, just some administrative stuff to
17 cover. You know, we're scheduled for four hours, 18 so if you need a break, out the room, turn right, 19 right again, go down about 20 feet, and there's
20 restrooms down the hall.
21 We do have, I do want to bring to
22 everybody's attention that we do have a certified
7/12/16 PRE-PROPOSAL CONFERENCE Page: 1 (1 - 4)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 court reporter here taking transcript of today's
2 session, and that session will be made available
3 on FedBizOops a few days after we wrap up the
4 event and we get the transcript and post it.
5 I'll just go ahead and introduce the
6 group that came with me from Kansas City. By the
7 way, I'm Dean Cole. I'm the Business Management
8 Specialist out of The Small Business GWAC Division
9 at Kansas City, Missouri. We run the VETS
10 contract, 8(a) Stars 2 contract, and Alliance
11 Small Business.
12 We're currently evaluating the VETS 2
13 GWAC. As you know, the RFP (inaudible) for A2SB
14 or you wouldn't be here. And we're also doing the
15 on-ramp evaluations for Stars 2, so we're quite
16 busy, but we wanted to make sure that we got out
17 and had a chance to talk to everybody regarding
18 the A2SB Proposal.
19 With me today, we've got Matt Verhulst.
20 He's the Director of GWAC Acquisitions. Greg Byrd
21 will be talking to you a little bit later. He's
22 going to be covering the meat and potatoes of the
1 pre-proposal conference.
2 As you can see, the agenda is up on
3 screen. So we do have a couple of guest speakers.
4 I'll introduce them as they come up, but I just
5 want to make sure I cover everything here.
6 Oh, yeah. You guys when you checked in, 7 you received index cards. That's for the question
8 and answer session. I don't know if they told you
9 outside, I'm sure they probably mentioned it, but
10 we don't have mics out here, and in the interest
11 of time, and making sure we get every question in
12 our hands, we ask that everybody write their
13 questions down on the index cards. We'll be
14 having folks wander around picking those up
15 throughout the presentation, or you can just wait
16 until we, we will have a break a little bit later
17 on. You may hold off until Greg does his part
18 because he'll probably answer a lot of the
19 questions you have.
20 But go ahead. You know, if you're like
21 me and I forget things if I don't write them down
22 right away, so it might not be a bad idea to at
1 least jot them down.
2 I think I pretty much covered the agenda
3 and everything I'm going to cover, so without
4 further ado, I want to bring up the Director of
5 Acquisitions Operations, Michael McFarland. He's
6 going to say a few words about our GWAC successes
7 over the years.
8 Thank you very much. Michael.
9 (Applause)
10 MR. McFARLAND: Thank you, and welcome
11 to the Alliant 2 Small Business Pre-Proposal
12 Conference.
13 Alliant Small Business is and continues
14 to be one of GSA's premiere small business
15 information technology vehicles. We're proud that
16 Alliant Small Business suppliers are providing
17 flexible access to customized IT solutions
18 throughout the government.
19 Alliant Small Business allows for
20 long-term planning for large-scale program
21 requirements due to its long -- thank you, Paul --
22 due to its long period of performance and
1 multi-year options.
2 Alliant Small Business solutions
3 encompass all components of an integrated IT
4 solution, including new technologies.
5 The GSA Small Business GWAC Center
6 currently operates three contracts with
7 specialized socioeconomic designations. As Dean
8 indicated, we are under recompetition or open
9 season for all of them at once. So we're very
10 busy right now.
11 Each contract is designed to provide a
12 streamlined method for agencies to utilize highly
13 qualified small businesses to meet their IT needs
14 while achieving their agency socioeconomic
15 contracting goals.
16 Premier among our small business GWACs
17 is Alliant Small Business. The Alliant Small
18 Business GWAC focuses on providing government
19 contract opportunities to a wide range of
20 highly-qualified small businesses.
21 This small business contract provides
22 flexible access to customized IT solutions from a
7/12/16 PRE-PROPOSAL CONFERENCE Page: 2 (5 - 8)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 diverse pool of nearly 50 industry partners. With
2 availability through 2024, Alliant Small Business
3 allows for long-term planning of large-scale
4 program requirements while strengthening
5 opportunities for small businesses.
6 In FY15 alone, Alliant Small Business
7 received 90 task orders, and over 1.2 billion in
8 obligations, which was an increase of 8 percent
9 over the previous year.
10 Alliant Small Business has been a
11 remarkable success for agencies, for you, our
12 industry partners, and for GSA. Alliant Small
13 Business has quickly become one of the most
14 successful small business GWACs in the government.
15 For six-and-a-half years of Alliant
16 Small Business, 30 or more federal agencies have
17 awarded nearly 5 billion in task orders. Alliant
18 Small Business has taught us the importance of
19 partnerships, education, and training for both our
20 agency customers, and our industry partners, and
21 customer service in developing and delivering
22 successful contract vehicles.
1 The Navy selected Alliant, Alliant Small
2 Business as a mandatory use contracts for IT
3 services, which is just one example of how
4 agencies value the Alliant portfolio of contracts.
5 As a pre-computed vehicle, Alliant Small
6 Business is streamlining the acquisition process
7 for many government agencies. And through this
8 streamlining, agencies save taxpayer dollars, and
9 they can more quickly and efficiently procure
10 needed IT solutions.
11 One thing that has always impressed me
12 since I've gotten here about the Alliant Small
13 Business, and the GWAC Program here at GSA in
14 general, is the amount of collaboration that goes
15 on between all the parties.
16 Success on projects through Alliant
17 Small Business is a three-part partnership - GSA, 18 procuring agencies, and the companies performing
19 the work under the Alliant task orders.
20 The GSA GWAC Program operates using
21 three C's for success: Communication, 22 collaboration, and competition. We will continue
1 this for Alliant 2, and Alliant 2 Small Business.
2 The relationships we've built with our
3 government and industry partners have been, and
4 will continue to be, critical to the program's
5 success.
6 I want to thank you for everything all
7 of you have done for both Alliant Small Business, 8 and to help us with this new GWAC, Alliant 2 Small
9 Business.
10 Now, the GSA GWAC Program, leader in
11 government- wide acquisition contracts, having
12 established one of the very first GWACs in the
13 government, the answer contract in 1999, in
14 creating more GWACs than any other federal agency
15 has developed the Alliant 2 and Alliant 2 Small
16 Business solicitations, which were the sequel, the
17 very prominent and successful Alliant Small
18 Business GWACs.
19 ITS couldn't be more excited about the
20 future of our GWAC Program. Alliant 2 and Alliant
21 2 Small Business have been developed to continue
22 to provide support to federal agencies that have
1 mission critical complex IT service requirements, 2 especially for long-term programs.
3 Alliant 2 and Alliant 2 Small Business
4 presolicitation phase has raised the bar in
5 transparency and collaborative processes involving
6 both federal agency and industry partners.
7 The Alliant 2 and Alliant 2 Small
8 Business team performed thorough market research, 9 and laid significant groundwork in the preplanning
10 phase with efforts including an interact group
11 with more than 7,000 members, a publicly- reviewed
12 business case on OMB MAX, meetings with the
13 Coalition for Government Procurement, FSEA
14 (inaudible) Northern Virginia
15 Chapter, the Alliance for Public
16 Sector, Defense Procurement and
17 Acquisition Policy, the Office of
18 Federal Procurement Policy, Small
19 Business Administration, U.S.
20 Department of State, and ACT-IAC.
21 We've had numerous presentations through
22 interested agencies. We have a customer working
7/12/16 PRE-PROPOSAL CONFERENCE Page: 3 (9 - 12)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 group of 30 members from 11 agencies. We have an
2 industry working group with more than 500
3 participants. We've put out two RFIs for industry
4 comments through FedBizOops.
5 We've had two industry days with more
6 than 500 attendees. We've had face-to-face, 7 one-on-one meetings between industry and Alliant
8 2, Alliant 2 Small Business staff with more than
9 350 registrants.
10 The collaborative input and feedback
11 toward the development of Alliant 2 and Alliant 2
12 Small Business this past year has been a major
13 contribution to what we believe is an outstanding
14 final product. Notable enhancements between
15 Alliant and Alliant Small Business, and Alliant 2, 16 Alliant 2 Small Business include scope
17 improvements, standardized information technology, 18 service labor categories, new cyber security
19 standards which are a focus of our administrator, 20 and OMB, new environmental standards, increasing
21 competition for orders which provide savings for
22 agencies, and more opportunities for our industry
1 partners, and the incorporation of required DFARS
2 clauses and provisions into the master contract so
3 that they automatically flow down to task orders
4 issued by DOD agencies.
5 We recognize your contributions and your
6 providing insights to the changes we've made since
7 the first draft RFPs. I'm confident that you will
8 be pleased with the final product and the role
9 you've each played in it.
10 We at GSA cannot overemphasize how the
11 collaboration within GSA with our customer
12 agencies, and with our industry partners while
13 doing market research, and in planning future
14 solicitations and innovations is key to being sure
15 what we want to do is vetted, is on the right
16 track, and considers all viewpoints.
17 The Alliant 2, Alliant 2 Small Business
18 collaborative process is the lodestar by which ITS
19 is guiding the development of our other contract
20 offerings. ITS is committed to keep our
21 contracts, including Alliant 2 Small Business, 22 with sharing, growing, and evolving in the new
1 marketplace.
2 And now, I'd like to turn you over to
3 Casey Kelley, the Director of the GWAC Program at
4 ITS. Thank you.
5 (Applause)
6 MR. KELLEY: Good morning everybody. My
7 name is Casey Kelley. I'm the current acting
8 Director for the GWAC Program for (inaudible) GSA.
9 Part of that I was the Enterprise GWAC Division
10 Director in San Diego, and also the Program
11 Manager for Alliant, the current Alliant contract.
12 So since then, I've been the program
13 manager for the Alliant 2, Alliant 2 Small
14 Business GWACs, and have worked with this team
15 that has gotten us to this stage today.
16 So I was flattered when Greg and Matt
17 asked me to come and say a few words. So those of
18 you who know me know I can talk, so I committed
19 that I would only talk for less than five minutes.
20 I brought it down a little, some notes what I
21 wanted to say yesterday morning at the airport, 22 and so I want to just speak from this which I
1 traditionally don't do. I much prefer speaking
2 extemporaneously, but I guess I'm, through me what
3 you'll see, hopefully see is the conduit that I
4 present the passion to the team that represents
5 the GWAC Program, both contracting and
6 programming.
7 So with that, I just want to share my
8 words here. So, first, I want to thank industry
9 for their participation today and for attending.
10 I want to thank Michael and GSA leadership for
11 their support, specifically, Tom Sharpe, Kevin
12 Youl-Page, Mary Davie, Kay Ealy, Bill Zelinski, 13 Michael McFarland, Maynard Crumm, and Randy
14 Burleson. That's the leadership that has
15 supported us to get to this point here today.
16 A special thanks to John Cavadias, and
17 Greg Byrd, the procuring contracting officers, for
18 their leadership. If not for their leadership, 19 you don't have the collaboration, the transparency
20 that you've seen through this process to date.
21 And, finally, a special thanks to all
22 A2, Alliant 2, Alliant 2 Small Business team
7/12/16 PRE-PROPOSAL CONFERENCE Page: 4 (13 - 16)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 members who I'm not going to list, but you know
2 who they are, and the impact that they've had to
3 this, this whole acquisition to this, for this
4 process.
5 There's a saying in business, in
6 investing that goes something like this. Past
7 performance is no indicator of future success.
8 That may be if there is no coincidence why there
9 are so many people here today and tomorrow, and
10 also on the virtual call that this team has set up
11 for next Monday.
12 The expectation for Alliant 2, Alliant 2
13 Small Business to be as successful, if not more
14 successful, than the current Alliant, Alliant
15 Small Business GWACs, which have done $34 billion
16 to date by over 60 agencies combined are high, and
17 that they should be.
18 Those expectations were high when this
19 team began market research in the acquisition
20 planning process over three years ago. And this
21 team has delivered in creating what I believe
22 personally is an even better contract from the
1 current Alliant, Alliant Small Business contracts, 2 and that's saying a lot because there was a lot of
3 blood, sweat, and tears in those contracts for any
4 of you incumbent small businesses out there on
5 those know firsthand.
6 The team didn't construct, 7 quote/unquote, construct, this contract, Alliant 2
8 Small Business, or Alliant 2. What they did was
9 they created these contracts. And it's very
10 important to know the difference between those two
11 words, create and construct.
12 When you create something, your love for
13 what you are doing begins at inception, and it's
14 constant throughout. Whereas, when you construct
15 something, your love is contingent upon what that
16 final outcome is.
17 This culture within the GSA GWAC
18 organization is one of creativity, passion, and
19 excellence. Everyone here loves the mission of
20 the GSA GWAC organization, and the opportunity to
21 make a difference by serving our country, by
22 helping all agencies acquire the greatest IT
1 service solutions better, faster, and cheaper.
2 It is that came passion that leads to an
3 acquisition process in customer service that is
4 unprecedented in terms of engaging with customers
5 and industry to create an excellent product in the
6 end.
7 As Michael alluded to, internet posts, 8 RFIs, draft RFPs, industry days, face-to-face, 9 one-on-ones, and now having these pre-proposal
10 conferences have all resulted in a very thoughtful
11 final product that has taken into consideration
12 input and feedback from thousands of questions of
13 which all were considered, and more than some even
14 implemented.
15 I personally have never been more proud
16 of working with such a fine group of men and women
17 who are all committed to excellence and making a
18 difference. Knowing myself firsthand how
19 successful Alliant, Alliance Small Business have
20 done after a rocky start seven-and-a-half years
21 ago, with nowhere near the collaboration with
22 industry that we've seen today under these two
1 contracts, nor the collaboration with government, 2 and knowing how committed our team is to
3 continuing improving our performance, I have zero
4 doubt that Alliant 2, Alliant 2 Small Business
5 will even be more successful than the current
6 Alliant, Alliant Small Business GWACs.
7 Yes, it is true that past performance is
8 no indicator of future success. However, I have
9 no doubt that Alliant 2 and Alliant 2 Small
10 Business will be successful.
11 I personally wish each of you could
12 decide to compete on this GWAC here, or on the
13 unrestricted Alliant 2 GWAC. I wish each of you
14 to join us for this journey, and the best of luck, 15 and I look forward to working with those of you
16 who are successful in helping you best meet the
17 needs of our customers working together for the
18 next several years.
19 So as I said, I hate reading. It's
20 really not my style. You out there in this
21 audience, you're the difference makers. At the
22 end of the day, it's you that are delivering the
7/12/16 PRE-PROPOSAL CONFERENCE Page: 5 (17 - 20)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 solutions to our customers that we're trying to
2 attract.
3 Hopefully, what we've put together to
4 date is something that you'll respect and honor, 5 the effort that's been put into it, and I'm hoping
6 those of you who are successful, those 80-plus
7 primes, plus ties continue that same passion that
8 the current incumbents under Alliant 2, I'm sorry, 9 that the current incumbents under Alliant Small
10 Business have performed to day to help us continue
11 that same legacy that we started seven-and-a-half
12 years ago. So thank you.
13 (Applause)
14 MR. BYRD:: : Yeah, I don't want to
15 drink your water. Good morning, everyone. Well, 16 this portion -- I'm actually going to only be
17 spending about 30 minutes, and what I'm going to
18 focus on in that 30 minutes is probably what's
19 most interesting to you guys is I am going to
20 concentrate on Section L and the proposal
21 requirements.
22 But before I get started, there is, I'm
1 going to give an opening statement, and I'm going
2 to just read it verbatim.
3 Today, in response to questions, I will
4 be speaking -- and I don't have my reading
5 glasses. Left them in the hotel. I will be
6 speaking about the A2SB RFP. If there is a
7 difference between what is said today and the
8 written language of the RFP, the written language
9 of the RFP governs.
10 Only an RFP amendment posted on
11 FedBizOops can change the RFP.
12 Now I'm very pleased to be visiting with
13 you today at this pre-proposal conference -- I'm
14 so sorry. As has been illustrated by previous
15 speakers, GSA has been successfully and
16 thoughtfully partnering with industry on GWACs and
17 A2SB in leading the way with the future for
18 federal information technology acquisition.
19 As the procuring contracting officer for
20 A2SB, what I want to accomplish today is to share
21 an overview of the RFP structure, to reply to some
22 of the questions asked today and were sent to
1 A2SB@gsa.gov, and to also reply to some of the
2 questions that will be submitted on index cards
3 here in this meeting.
4 Regarding questions and responses, 5 please recall that GSA reserves the right to
6 publicly discuss, and publish, or simply consider
7 questions and comments regarding the RFP.
8 That said, in the time available today, 9 it is not possible to address every question
10 asked, but I will touch on some that have been
11 asked frequently or stand out.
12 You can expect one or more rounds of
13 questions and responses to be published on
14 FedBizOops, including those that are covered
15 today. Please remember, the A2SB procuring
16 contracting officer is the sole point of contact
17 for the procurement, and can be reached at
18 A2SB@gsa.gov. Boy, that was painful.
19 So, as I said earlier, I can't walk
20 around because I got to stay in front of this
21 microphone. But as I said earlier, I'm going to
22 be focusing on Section L. A little bit of Section
1 M at the end, but mostly on L.
2 So as far as the A2SB contract is
3 concerned, or the solicitation, it is a multiple
4 award indefinite delivery, indefinite quantity
5 contract for IT services, and IT services- based
6 solutions. It is a total small business
7 set-aside. The NIACS code is 541512, and the
8 associated small business side standard is 27.5
9 million.
10 Now, what I would like to say about that
11 is that this is -- what I'm going to do throughout
12 this is I'm going to weave answers to questions
13 that I have gotten already since the issuance of
14 the RFP. So I'll do it conversationally as I'm
15 giving this presentation.
16 And here is one of the questions
17 actually. As far as the NIACS code is concerned, 18 you know, we have, there were huge changes between
19 the draft RFPs and the final RFP. Probably one of
20 the biggest changes in that is because of the NDAA
21 of 2016 allowing for a contract teaming
22 arrangements, and the members of those teams
7/12/16 PRE-PROPOSAL CONFERENCE Page: 6 (21 - 24)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 whether JVs, or prime, and a team of
2 subcontractors to be able to use their individual
3 experience for members of the joint venture, or
4 the prime and team of subcontractors.
5 As you know, each one of those members
6 of those CTAs have to be small businesses, and the
7 NAICS code that counts to those small businesses
8 is 54152. So you can't use other NAICS codes that
9 the contract is not using to determine whether
10 they're a small business.
11 For instance, employee counts, other
12 NAICS codes that use employee accounts, they have
13 to be small under the NAICS under the contract.
14 It is a base period of five years, one
15 five-year option, so it'd be a, the code, the
16 total term of the contract will be ten years. It
17 is worldwide geographic scope, and allows for all
18 contract types, which as you see in the
19 evaluations because of the types of contracts, 20 especially our experience on Alliant Small
21 Business, you know, you'll see some emphasis on
22 some types of contracts, especially cost
1 reimbursement contracts, primarily because upwards
2 of more than 30 percent of our task order awards
3 on Alliant Small Business have been cost
4 reimbursement contracting. And that is
5 by-the-book cost reimbursement contracting. It
6 doesn't include time and materials, or labor hour, 7 any of that.
8 So if we go to the next slide. All
9 right. There you will see the proposal format as
10 it's laid out in the RFP. What I would like to
11 say first is that you will see in the RFP that we
12 expect all of this to come into one package
13 actually on one CD, all seven volumes.
14 There is one exception that we've made
15 to this that you can't have separate CDs in the
16 proposal. The only exception to this is, as we'll
17 get into later with responsibility, is the fact
18 that GSA Form 527, that form can actually be
19 submitted by CTA partners whether, either JV or
20 subcontractors to a prime. They can be sealed in
21 individual envelopes in the proposal by
22 themselves. Actually, the prime contractor
1 doesn't have to even see them.
2 But having said that, we will not accept
3 them separately. They have to be part of the
4 offeror's proposal. In other words, they can't be
5 sent in separately.
6 All right. Okay. First, I'm going to
7 go, the way that I'm going to do this is I'm to
8 just go through each volume just to kind of hit
9 some of the highlights, hopefully answer some of
10 the questions.
11 The first one on there is the Standard
12 Form 33. I'm sure all of you guys saw that there
13 was a mistake on that 33. It was the due date.
14 It said August the 22nd. That is not the due
15 date. The due date is August the 29th at 4:00
16 p.m. Central Time.
17 Just immediately after that was posted, 18 I saw that, and I subsequently uploaded to
19 FedBizOpps the corrected Standard From 33. So in
20 the announcement, look for the corrected 33 on
21 there that has the due date for the solicitation.
22 The document, probably, the most
1 important document for us to see is the Document
2 Verification and Self-Scoring Worksheet. I think
3 it's J.P-1. The one thing I want to highlight
4 there is that we not only want as part of the
5 package the Excel spreadsheet of the J.P-1 as part
6 of the CD, but we also want to see one hard copy
7 of it on paper, and it can be just in the package.
8 That's the first thing that we're going to look at
9 as you'll see when we talk about in Section M of
10 how this is actually going to be evaluated.
11 The first thing we're actually going to
12 pull out of the package before we look at anything
13 is we're going to look at that paper score sheet
14 to see what your score is on that, and then we're
15 going to start lining them up from top to bottom, 16 so make sure it matches.
17 The next thing on there is the
18 meaningful relationship commitment letters. It
19 could apply to small business, but it's mostly
20 probably going to be applying to A2. The one way
21 that I could see it applying to small businesses
22 especially would be the ANCs. That's a
7/12/16 PRE-PROPOSAL CONFERENCE Page: 7 (25 - 28)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 possibility. But what that is, is that, if an
2 offeror is using resources of another part of the
3 organization whether it's a subsidiary, a
4 division, if they're going to be using resources
5 of that other part of the organization, that's
6 what required in that is the meaningful
7 relationship commitment letters, and the RFP
8 actually spells out what those should be.
9 And as I mentioned earlier, the
10 contractor teaming arrangements, the two types of
11 CTAs that are now allowed on the contract would be
12 a partnership, or a joint venture. You'll
13 remember in the previous iterations of the first
14 couple of drafts, it had to be existing.
15 Well, that's because of the NDAA 2016.
16 That's not the case anymore. They can be new JVs, 17 and they can be new prime contractors proposing
18 with a team of subcontractors.
19 There is, as far as CTAs, there is
20 another one. This has caused a little bit of
21 confusion and asked a number of questions about
22 it. And that's the third one, the claiming prime
1 contractor relevant experience from an existing or
2 previous joint venture or a partnership. What
3 that means, and I think that the RFP is actually
4 clear on it, is that a prime contractor that's not
5 part of the JV, that's just offering as
6 themselves, they can use experience where they
7 performed as a member of a joint venture, and
8 that's only if they were the only contractor that
9 performed under that specific work for that joint
10 venture.
11 There's some verification requirements.
12 There's a document that majority of the members of
13 the JVs sign off on and say, yes, this contractor
14 performed 100 percent of the work under this work
15 for the JV.
16 So that's one. That's the, that's also
17 the only exception to the prime contract rule that
18 we have, and I'll get into that just a little bit
19 later.
20 And then the other ones are just, you
21 can just read them for yourself up there. I'm not
22 really going to, I haven't had any questions on
1 them. It's just the Professional Employee
2 Compensation Plan, Uncompensated Overtime Policy, 3 and the reps and certs.
4 One thing I will say about the reps and
5 certs is that if you're offering as a CTA, whether
6 a prime with subs, or a joint venture, all the
7 members of that CTA are going to have to submit
8 their representations or certifications, which is
9 pretty clear in the RFP.
10 Okay. Moving on to the relevant
11 experience in Volume 2. We have our relevant
12 experience, as you noticed, broken up into two
13 different types of relevant experience. The
14 primary one is the PSC experience, the product
15 service code, product and service code experience.
16 The other one is the leading edge technologies
17 experience.
18 Our primary one is the PSC though. As
19 far as your PSC experience, you can only use a
20 project one time in PSC. You can't use it for
21 multiple PSCs. Okay. And that PSC work has to be
22 ongoing or completed within five years, and it has
1 to have at least one year of performance on it.
2 There are some exceptions to the
3 one-year performance. If there's an interim or a
4 final CPARS, it can be accepted. If there's a
5 completed award fee determination, it can be
6 accepted if it's less than a year.
7 And the last one, if the period of
8 performance is less than a year, and the project
9 is completed. Now, the value of projects under
10 the PSC has to be at least $1 million. You'll
11 see, there is a pretty good explanation of how you
12 determine the value of the project in the RFP that
13 I'm really not going to elaborate on. I haven't
14 had that many questions about it.
15 As far as the PSCs are concerned, we
16 expect the contractors to use their reasonable
17 discretion when they're determining whether or not
18 a project would meet a particular PSC in the RFP.
19 You know, our primary verification is FPDS- NG, 20 which actually uses the PSC code, but just because
21 it's not listed on the FPDS with that PSC code
22 doesn't mean that the, that PSC, that type of work
7/12/16 PRE-PROPOSAL CONFERENCE Page: 8 (29 - 32)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 wasn't integral to the project.
2 That's the key, is that it has to be
3 integral to the project, and we had two separate
4 verifications for the PSC. If -- I'm trying to
5 make sure that I don't miss some of these
6 questions that's have been asked.
7 Our primary way of verifying the
8 information for the PSC, especially for, even for
9 the extra points on the PSC, because each of those
10 points can be found on an FPDS-NG report, that is
11 our primary way. If FPDS-NG report exists, and
12 it's complete, and verifies all of it, that is our
13 primary verification, and we're going to take that
14 at face value. The only things that you submit in
15 those instances is the FPDS report itself. We
16 still require a copy of the statement of work
17 under that, and we, anytime we require a statement
18 of work, and this is going to apply to both PSC
19 and LETs, if we require a statement of work, we're
20 asking you to highlight those areas where that, 21 with emphasis on that PSS, and, actually, when I
22 get into the LETs too, are where that LET is being
1 performed. And we also want even if FPTS-NG
2 verifies everything, we want you to fill out the
3 J.P-2 Form, the PSC template.
4 Okay. If the FPDS-NG is not available, 5 that doesn't mean that you can't use that, that
6 project for that PSC. It just has to go through
7 some other verification requirements. Not only do
8 you have to send in the Form J.P- 2, but you have
9 to also, we also are requiring that a contracting
10 officer, a warranted contracting officer, signs
11 off on it, and says, yes, that was a part of this
12 project.
13 We do allow for a COR. The default is
14 the ordering contracting officer. Not the
15 ordering contracting officer, but the contracting
16 officer, the warranted cognizant contracting
17 officer for that project. That's the default. If
18 they are not available, we will accept a signature
19 from a contracting officer's representative.
20 And I've had a number of questions about
21 what about COTRs. Well, OMB first when they come
22 out with the training and the certification
1 requirements for CORs, it originally was a
2 contracting officer's technical representative.
3 But they kind of made the COTR obsolete when they
4 were revised that memorandum. So it is a
5 contracting officer's representative now. So if
6 it's a COTR, or if it's COR, we would look at that
7 as synonymous. It's as long as they meet the
8 requirements that are in the RFP that the
9 information that we're asking for.
10 Now, of course, you're always going to
11 have to, you're required to submit the statement
12 of work, especially if the FPDS is not complete or
13 it's incomplete and the form.
14 The other thing that I would like to
15 mention is the -- oh, man, just flittered away.
16 Anyways, it'll pop back in my head.
17 Okay. There are some other things.
18 There's additional points that can be for the PSC
19 projects that, as you've seen in Section M, 20 there's additional points to be had.
21 Oh, here's what I was going to say. I
22 knew it'd pop back in my head. The PSC codes, we
1 are not asking you to ask the contracting officer
2 to make any kind of changes in FPDS-NG. That
3 contracting officer has put that PSC code in. We
4 don't expect them to change it. That's why we
5 have other verification routes that you can take
6 if that's not the primary PSC.
7 Now, as far as the others that you can
8 gain points, the first one was the project size
9 and complexity. You get varying points if it's
10 from 2 million up to 5 million, 5 million up to 15
11 million, and greater than 15 million. You can get
12 additional points for projects that meet those
13 criteria.
14 There is another change that was from
15 our draft RFPs. As far as the demonstrating
16 experience with multiple federal government
17 customers, we had switched from a listing that we
18 had in the draft RFPs of the agencies that you
19 could get credit for, and we've just gone to
20 funding agency ID, which is found in FPDS-NG.
21 So it does open up more opportunities to
22 gather those points because there's a lot more
7/12/16 PRE-PROPOSAL CONFERENCE Page: 9 (33 - 36)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 funding agencies than there are in our list. So
2 that was one of the changes that we made from the
3 draft RFPs.
4 The next one is the, a project with cost
5 reimbursement. The cost reimbursement, the one
6 thing that I want to tell you is time and
7 material, and labor hour type contracts
8 ,<inaudible>. This is FAR Part 16 cost
9 reimbursement
10 type contract, and everything that that
11 means. So if you do demonstrate experience in
12 cost reimbursement contracts, and some of the PSCs
13 fall into that category, you will get extra points
14 for that.
15 Fair opportunity task order award
16 against a MA IDIQ contract, this is a 16.505 type
17 of a task order where fair opportunity was
18 provided, and it was competed. If that's the
19 case, then you get the points. It's not a FAR
20 Part 8, and we will not, schedule, competed
21 schedule awards and such we will not accept. It
22 has to be a multiple award, IDIQ contract for you
1 to get those points.
2 The reason for that is, is that's
3 because that's what this contract is. We're
4 looking for experience with contractors that have
5 actually had multiple award IDIQ contracts such as
6 Alliant SB or the other GWACs that are out there.
7 The other thing I'd like to say, for the
8 last three that I mentioned, the fair opportunity
9 task order award against a MA IDIQ, contract
10 project with cost reimbursement, and demonstrating
11 experience with multiple federal government
12 customers, there's only one way to verify that, 13 and that is FPDS-NG. If it cannot be verified by
14 FPDS-NG, you will not get the points for that.
15 The other one is the project in a
16 foreign location. The one thing that I would like
17 to say about -- actually, a couple of things I
18 would like to say about that.
19 The first one is that as the RFP says, a
20 foreign location as defined in our RFP, is that as
21 far as the United States is concerned, it's the 48
22 contiguous states. It's Alaska, it's Hawaii, and
1 it's territories and possessions.
2 For you to get credit for foreign work, 3 it has to be outside of that. So it's outside of
4 USA and all of it's possessions. So that's the
5 one thing.
6 The second thing about the foreign
7 location is that it can be verified by FPDS-NG, 8 but we're not requiring that it be verified by
9 FPDS-NG. If there was a significant piece of that
10 work that was overseas, even though it's coded as
11 primarily in the United States, you can get credit
12 for that. It's just that we have the verification
13 requirements that are in the contract. And part
14 of that has to do with, you know, highlighting
15 statements of work, or whatever, showing that that
16 work being performed overseas.
17 And this work cannot be TDY. It can't
18 be just traveling overseas for a particular
19 project. It has to be boots on the ground, 20 working in those foreign locations on an ongoing
21 basis.
22 In the PSC Code Table, I've gotten a lot
1 of questions about wanting us to elaborate on
2 PSCs, and definitions, and such. We are not going
3 to do that. The RFP states that the Federal
4 Procurement Data System Product and Service Codes
5 Manual is what governs in this. And there's not
6 going to be anymore information than what's in
7 that. That's why I was talking about earlier
8 about using your reasonable discretion about
9 determining whether a PSC would fit in a
10 particular, in a particular relevant experience
11 slot.
12 Leading edge technology relevant
13 experience. That verification really kind of
14 goes, it's pretty much in line with the
15 verification on the PSC if you don't, if the FPDS
16 is incomplete.
17 As far as the LETs are concerned, once
18 again, it's just like the PSC. It had to have
19 been integral to the performance of the project.
20 Once again just like in PSCs, it can only be used
21 one time in the LETs, but there's, you do have one
22 big advantage. There's only one exception to
7/12/16 PRE-PROPOSAL CONFERENCE Page: 10 (37 - 40)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 being able to use a project twice is that you can
2 use -- in the PSC you can have up to seven
3 projects. It's four in the PSC, the first
4 section, it's two in second section, it's one in
5 the third section. A total of seven projects.
6 You can use each one of those PSCs one time in the
7 LETs, so you could get up to seven instances if it
8 happens to hit one of those LETs. You can get up
9 to seven instances that you can reuse that PSC in
10 the LET, but you can only use it once.
11 Once, again, it's that same verification
12 process that we talked with the PSC - statements
13 of work, highlighted area in the statements of
14 work, award forms. Each one of these requires
15 award form, statements of work, sign-off on the
16 contracting officer, if the contracting officer is
17 not available a COR will work.
18 Okay. And the one area in LETs where
19 you get extra points is the breadth of LETs that
20 you hit. It has to be individual LETs. It can't
21 be multiple, you know, you can have up to three
22 experience citations in each leading edge
1 technology. Multiple within a leading edge
2 technology doesn't count as breadth, but across
3 leading edge technologies does count as breadth.
4 The other thing is that I would say, 5 don't, I wouldn't spend my time when you actually
6 put questions on index cards about typos, or
7 problems like that because I've been made well
8 aware of it.
9 As my colleague on A2 said, they are
10 just what he considered artifacts from all the
11 draft RFPs that we've had, so I tried to catch all
12 of those. Apparently, I didn't catch them all, 13 but I've already got them highlighted. There will
14 be an amendment to actually make those changes.
15 I say that now because I know on the
16 J.P-1 that it's not scoring correctly. It's not
17 adding one of them up. So all of that will be
18 fixed, and it will be coming on an amendment
19 later. And you'll find the descriptions of the
20 LETs as one of our proposal attachments, at J.P-4.
21 Okay. On our past performance, what we
22 require is we require a past performance from each
1 one of the PSC relevant experience that you're
2 actually citing in your proposal.
3 As far as the past performance is
4 concerned, we're going to rely on PPIRS. If a
5 PPIRS's past performance exists, what we require
6 is that the most current one is sent in, and
7 that's really actually it's for the verification
8 for the past performance on that PSC. We do allow
9 -- if a PPIRS report does not exist, then we do
10 allow for you to use a form. It's J.P-5, the past
11 performance template, that you can give to your
12 customer that they can actually fill out and rate.
13 It follows strictly in line with the
14 same rating evaluation factors that is found in
15 PPIRS, and will be used the same way as PPIRS is.
16 Those have to be as part of your, they
17 can't be sent in separately from customers. It
18 has to be part of your package. So you're going
19 to have to send that out to your customer. That
20 customer is going to have to send it back to you, 21 and you're going to have to send it in. We won't
22 accept them, we won't accept anything outside of
1 the proposal that the contractor is supposed to
2 send in.
3 Yeah. And the other, if there is
4 negative past performance, we do allow for you to
5 do a one-page summary on that negative past
6 performance to give your side of it.
7 There was, I know, in the proposal
8 tables in the beginning of it, it was, had
9 mentioned the double-side and stuff, kind of
10 ambiguous about whether it was one page or not.
11 It is one page, and that will be another that will
12 be fixed.
13 I'm actually kind of running out of
14 time, so we'll move on. Okay. On the system
15 certifications and clearances, the one thing that
16 I want to say here is that this is, especially
17 affects those that are offering as a CTA, or
18 whether joint venture with members, or whether a
19 prime and subcontractor. Under these
20 certifications and clearances, they all have to be
21 in the name of the prime contractor. We won't
22 accept certifications from any subcontractors, or
7/12/16 PRE-PROPOSAL CONFERENCE Page: 11 (41 - 44)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 just individual members of a JV.
2 There is one exception. If it's a joint
3 venture, either the JV itself can have the
4 certification, or if each individual member of
5 that joint venture has that certification, it can
6 be used. So that is important.
7 Okay. As far as the cost accounting
8 system and audit information, this is actually a
9 big change from the original Alliant Small
10 Business solicitation. I don't know if any of you
11 guys remember, but that was actually a go-no go.
12 What we have now is just a scoring. It's just
13 additional points if you do have it.
14 But what's required is that the
15 contractor has to have had an accounting system
16 that had been audited and determined adequate for
17 cost reimbursement contracting by DCAA, DCMA, or
18 any other agency or cognizant auditing agency.
19 Typically, as you guys know, it's
20 usually a, it's associated with a cost
21 reimbursement type work, whether it's a task order
22 or a contract. GSA is not going to be sponsoring
1 any of these audits. These audits just have to
2 exist. If they exist and you provide the
3 documentation that we ask for, whether it's a
4 Standard Form 1408, whether it's the audit report
5 itself, anything that shows us unequivocally that
6 your accounting systems have been audited and
7 determined adequate for cost reimbursement
8 contracting, then you will be able to get those
9 points. But it is just points. It doesn't keep
10 anybody from competing. You know, there may be
11 other ways that offerors can gather up points in
12 different areas.
13 But that's a big deal. Used to you
14 couldn't even, in the old Alliant Small Business, 15 you couldn't even compete, but at least you now
16 can compete if you don't have those, don't have
17 that.
18 The other things, the forward pricing
19 rate agreements, the earned value management
20 systems, acceptable estimating systems, all of
21 those certifications, I mean, for lack of a better
22 term, they just are what they are. I mean, you
1 have the documents that show that you have that
2 certification, and depending on what levels you
3 have, you will get the additional points for
4 having those certifications.
5 You can go to the next one. Okay. This
6 was another area that was kind of born out of the
7 NDAA 2016. As you know, now we're allowing
8 newly-formed joint ventures, newly-formed prime
9 contractors, and a team of subcontractors.
10 But what we've added is an
11 organizational risk assessment within the
12 contract, within the RFP. There's going to be, 13 there will be an amendment to this. It's not a, 14 it possibly could be a significant amendment to
15 some of you, but it's just, it's really going to
16 be a, it's a clarification on our part.
17 What we meant when we wrote it, but it
18 may not be clear, for the purposes of this
19 evaluation factor, a business arrangement is
20 defined as an individual company. If an
21 individual company is proposing as itself, not
22 using subcontractors, not part of a joint venture, 1 then you get the points. There's nothing else you
2 have to do.
3 The other one is a joint venture, or it
4 could be a partnership or a joint venture, or a
5 prime contractor and it's proposed first tier
6 subcontractor team. That is the business
7 arrangement.
8 Okay. Here's what needs to be
9 clarified. Previously performed. There's
10 actually two words in there that have a lot of
11 meaning that just may not on the face of it seem
12 that way. What we mean by previously is previous
13 to the issue of the RFP. That's what previously
14 means, and that amendment will actually clarify
15 that.
16 What we mean by perform is we mean work
17 that is being performed. If a subcontract has
18 simply been signed, but there's been no work
19 performed under that subcontract, then that won't
20 count. So when you see the term, "previously
21 performed," that means previous to the RFP being
22 issued, and, "performed," means performance under
7/12/16 PRE-PROPOSAL CONFERENCE Page: 12 (45 - 48)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 that subcontract.
2 The other thing, many questions about
3 whether the prime contractor that's proposing can, 4 could they have been a subcontract to their
5 subcontractor? And the answer to that is no. It
6 has to be the prime, if it's a prime contractor
7 and a subcontractors, that any work that was done
8 had to have been performed in a prime sub
9 relationship with a prime contractor proposing on
10 the RFP was the prime contractor and that prime
11 sub -- I'm even confusing myself.
12 The prime contractor had to have been
13 the prime contractor in the prime sub relationship
14 if there was a previous relationship there.
15 Okay. A business arrangement is
16 considered to have previously performed if one of
17 the following conditions is met. Of course, an
18 individual company, nothing else needs to be said, 19 they get the points.
20 A joint venture has previously performed
21 work on a contract or an order. That is an
22 existing joint venture that existed prior to
1 issuing the RFP, and that has done work under
2 other contracts successfully.
3 The other one is that as far as the
4 prime and a subcontractor arrangement, a prime
5 subcontractor arrangement would be considered to
6 have previously performed, each proposed
7 subcontractor has previously performed on a
8 contract or order as a subcontractor to the
9 offering prime contractor. If that is the case, 10 then they can actually get the points as far as
11 the organizational risk assessment.
12 Okay. As far as the cost price is
13 concerned, I think it's pretty straight forward.
14 Just remember, I've had a lot of questions about
15 the rates, and not understanding especially that
16 range of rates that we're talking about proposing
17 under, those are direct labor rates. That's what
18 the employee is getting paid. It has no fringe
19 benefits on it. It has no overhead. No G&A.
20 It's just the direct rate that the contractor, I
21 mean, that the employee is being paid. That's
22 what those rates represent.
1 Those rates were, we went through a lot
2 of research in developing those rates. The only
3 thing, just the major things that I'd want to say
4 about that is that you want to be very careful, 5 we're not telling you can't propose outside of
6 those rates, either lower or higher, but we just
7 want to caution you that you do that at your own
8 peril.
9 If you do do that, just make sure that
10 you submit all of the justifications and stuff
11 that we ask you to. If you go beyond, either
12 above or below our rates, we ask that you
13 supplement that with some kind of explanation as
14 to why you did that.
15 The other thing, there's a couple of
16 other things that you would have to explain to us
17 if you do something outside of what we've asked
18 for. We've, actually, set a, it's not a ceiling
19 profit because you can propose whatever profit you
20 want to understanding that these rates only apply
21 to time and material, and labor hour type task
22 orders.
1 We've set a target rate of 7.5 percent.
2 If you propose something higher than that, that
3 would require a justification as to why you did
4 that.
5 The other justification would be is if
6 on the indirect rates, what we're asking you on
7 your indirect rates because part of this cost
8 submittal, this pricing submittal, is a basis of
9 estimates where you give us, you know, how you
10 estimate things, and how you do it with your, you
11 know, your audited rates, and forward pricing
12 rates, and such as that, we ask you to do that
13 same thing when you, actually, put in your
14 overhead rates in the spreadsheet. We would ask
15 that you would explain something that goes outside
16 of your normal business practices as far as using
17 those audited rates.
18 The other thing that I'd like to let you
19 know is that on that spreadsheet, you only put, 20 you're only putting one year's worth of, in there, 21 and you're putting, you're putting your rates for
22 one year, your overhead for that one year, and
7/12/16 PRE-PROPOSAL CONFERENCE Page: 13 (49 - 52)
Anderson Court Reporting -- 703-519-7180 -- www.andersonreporting.net
1 it's being extrapolated out.