This is a Price Schedule attachment for an indefinite delivery indefinite quantity (IDIQ) grounds maintenance contract for Crown Hill National Cemetery under solicitation number 36C78626Q50152, issued by the Department of Veterans Affairs National Cemetery Administration.
The contract encompasses comprehensive cemetery grounds maintenance services across a base year plus four option years. Services are organized into 37 contract line items (CLINs) covering interment operations, turf and landscape maintenance, pest and vegetation control, facility cleaning, snow removal, and headstone maintenance. Key service requirements include interment shelter operations (270 estimated events annually), transportation of urns and floral arrangements (350 events), niche cover installation (350 events), mowing of 2.2 acres (39 times), string trimming around 2,095 headstones (39 times), and fertilizer, herbicide, and insecticide applications across 12-14.2 acres at specified seasonal intervals. Additional services include core aeration, overseeding, leaf removal, tree pruning and removal, irrigation system maintenance, road cleaning, snow removal with ice melt application (24 events), pressure washing, pest control, and headstone cleaning for all 2,095 headstones. The price schedule requires contractors to provide unit prices for each CLIN, with extended prices calculated for estimated quantities. Monthly services include blade edging (8 months), mole and rodent control (8 months), irrigation operations (8 months), road cleaning (12 months), and trash removal (12 months). The contractor must furnish all management, manpower, supervision, equipment, materials, and supplies necessary to perform the work.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BASE
| Price Schedule | |||||
| Services | |||||
| CLIN | Description | Est. Qty | Unit | Unit Price | Extended Price |
| 0001 | Interment shelter: cleaning and flag raising/lowering | 270 | EA | ||
| 0002 | Transport urn and floral arrangements | 350 | EA | ||
| 0003 | Receive & Install new and replaced niche covers | 350 | EA | ||
| 0004 | Support for weekend or Holiday interments | 10 | EA | ||
| 0005 | Support for Holidays and Special Events | 2 | EA | ||
| 0006 | Mow turfgrass (2.2 acres) | 39 | EA | ||
| 0007 | String trim around 2,095 headstones | 39 | EV | ||
| 0008 | Blade edge along sidewalks, curbs, and other flat surfaces | 8 | MO | ||
| 0009 | Fertilizer: supply and apply over historic, Confederate, and 12 Annex acres; early May, early Sep, and early Nov | 3 | EV | ||
| 0010 | Pre-emergent herbicide: supply and apply on 14.2 acres twice: Mar/April and late June | 2 | EV | ||
| 0011 | Post-emergent broadleaf herbicide; supply and apply to 14.2 acres twice -- mid-May and late June | 2 | EV | ||
| 0012 | Post-emergent yellow-nutsedge and crabgrass herbicide; supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 0013 | Grub insecticide: supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 0014 | Core aeration of turfgrass: 2.2 acres in Historic cemetery only in base year -- September | 1 | EV | ||
| 0015 | Overseed turfgrass: 2.2 acres in Historic cemetery and Confederate plot -- September | 1 | EV | ||
| 0016 | Fall leaf removal | 10 | EV | ||
| 0017 | Planting beds & tree rings: mulch and edge maintenance -- April/early May | 1 | EV | ||
| 0018 | Planting beds & tree rings: pre-emergence herbicide -- April and September | 2 | EV | ||
| 0019 | Planting beds & tree rings:emerged weed removal/control -- April through October | 7 | MO | ||
| 0020 | Shrub maintenance/pruning: Spring and Fall | 2 | EV | ||
| 0021 | Japanese Beetle control on trees and shrubs | 2 | EV | ||
| 0022 | Mole and rodent control: extermination and pest svcs | 8 | MO | ||
| 0023 | Soil sampling/testing | 1 | EA | ||
| 0024 | Sunken Grave Repair | 15 | EA | ||
| 0025 | Turfgrass renovation | 600 | SF | ||
| 0026 | Irrigation system: fall shutdown, spring startup, backflow testing | 2 | EA | ||
| 0027 | Irrigation system: operation and maintenance | 8 | MO | ||
| 0028 | Road cleaning/sweeping/blowing | 12 | MO | ||
| 0029 | Trash and debris removal | 12 | MO | ||
| 0030 | Pressure wash commital shelter, columbaria, other hardscapes | 2 | EV | ||
| 0031 | Insect and pest control at committal shelter and Admin Building (optional) | 8 | MO | ||
| 0032 | Snow removal and Ice Melt application: streets, parking lots; walkways and sidewalks | 24 | EV | ||
| 0033 | Headstone cleaning - all 2,095 | 2095 | EA | ||
| 0034 | Tree pruning | 10 | EA | ||
| 0035 | Tree removal | 2 | EA | ||
| 0036 | Tree stump removal | 2 | EA | ||
| 0037 | Ice Melt Application | 12 | EV | ||
| Subtotal (Services) | $ - 0 | ||||
| Aggregated Total (Supplies & Services) |
| Base Year | |
| Option Year 1 | |
| Option Year 2 | |
| Option Year 3 | |
| Option Year 4 | |
| Aggreated Base thru Option Year 4 Total | $ - 0 |
INTERNAL FOR OFFICIAL GOVERNMENT USE ONLY
OY1
| Services | |||||
| CLIN | Description | Est. Qty | Unit | Unit Price | Extended Price |
| 1001 | Interment shelter: cleaning and flag raising/lowering | 270 | EA | ||
| 1002 | Transport urn and floral arrangements | 350 | EA | ||
| 1003 | Receive & Install new and replaced niche covers | 350 | EA | ||
| 1004 | Support for weekend or Holiday interments | 10 | EA | ||
| 1005 | Support for Holidays and Special Events | 2 | EA | ||
| 1006 | Mow turfgrass (2.2 acres) | 39 | EA | ||
| 1007 | String trim around 2,095 headstones | 39 | EV | ||
| 1008 | Blade edge along sidewalks, curbs, and other flat surfaces | 8 | MO | ||
| 1009 | Fertilizer: supply and apply over historic, Confederate, and 12 Annex acres; early May, early Sep, and early Nov | 3 | EV | ||
| 1010 | Pre-emergent herbicide: supply and apply on 14.2 acres twice: Mar/April and late June | 2 | EV | ||
| 1011 | Post-emergent broadleaf herbicide; supply and apply to 14.2 acres twice -- mid-May and late June | 2 | EV | ||
| 1012 | Post-emergent yellow-nutsedge and crabgrass herbicide; supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 1013 | Grub insecticide: supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 1014 | NA | 0 | EV | ||
| 1015 | Overseed turfgrass: 2.2 acres in Historic cemetery and Confederate plot -- September | 1 | EV | ||
| 1016 | Fall leaf removal | 10 | EV | ||
| 1017 | Planting beds & tree rings -- mulch and edge maintenance -- April/early May | 1 | EV | ||
| 1018 | Planting beds & tree rings -- pre-emergence herbicide -- April and September | 2 | EV | ||
| 1019 | Planting beds & tree rings:emerged weed removal/control -- April through October | 7 | MO | ||
| 1020 | Shrub maintenance/pruning: Spring and Fall | 2 | EV | ||
| 1021 | Japanese Beetle control on trees and shrubs (optional) | 2 | EV | ||
| 1022 | Mole and rodent control: extermination and pest svcs | 8 | MO | ||
| 1023 | Soil sampling/testing (optional) | 1 | EA | ||
| 1024 | Sunken Grave Repair | 15 | EA | ||
| 1025 | Turfgrass renovation | 600 | SF | ||
| 1026 | Irrigation system: fall shutdown, spring startup, backflow testing | 2 | EA | ||
| 1027 | Irrigation system: operation and maintenance | 8 | MO | ||
| 1028 | Road cleaning/sweeping/blowing | 12 | MO | ||
| 1029 | Trash and debris removal | 12 | MO | ||
| 1030 | Pressure wash commital shelter, columbaria, other hardscapes | 2 | EV | ||
| 1031 | Insect and pest control at committal shelter and Admin Building (optional) | 8 | MO | ||
| 1032 | Snow removal and Ice Melt application: streets, parking lots; walkways and sidewalks | 24 | EV | ||
| 1033 | Headstone cleaning - all 2,095 | 2095 | EA | ||
| 1034 | Tree pruning | 10 | EA | ||
| 1035 | Tree removal | 2 | EA | ||
| 1036 | Tree stump removal | 2 | EA | ||
| 1037 | Ice Melt Application | 12 | EV | ||
| Subtotal (Services) | $ - 0 | ||||
| Aggregated Total (Supplies & Services) | ERROR:#REF! |
INTERNAL FOR OFFICIAL GOVERNMENT USE ONLY
OY2
| Services | |||||
| CLIN | Description | Est. Qty | Unit | Unit Price | Extended Price |
| 2001 | Interment shelter: cleaning and flag raising/lowering | 270 | EA | ||
| 2002 | Transport urn and floral arrangements | 350 | EA | ||
| 2003 | Receive & Install new and replaced niche covers | 350 | EA | ||
| 2004 | Support for weekend or Holiday interments | 10 | EA | ||
| 2005 | Support for Holidays and Special Events | 2 | EA | ||
| 2006 | Mow turfgrass (2.2 acres) | 39 | EA | ||
| 2007 | String trim around 2,095 headstones | 39 | EV | ||
| 2008 | Blade edge along sidewalks, curbs, and other flat surfaces | 8 | MO | ||
| 2009 | Fertilizer: supply and apply over historic, Confederate, and 12 Annex acres; early May, early Sep, and early Nov | 3 | EV | ||
| 2010 | Pre-emergent herbicide: supply and apply on 14.2 acres twice: Mar/April and late June | 2 | EV | ||
| 2011 | Post-emergent broadleaf herbicide; supply and apply to 14.2 acres twice -- mid-May and late June | 2 | EV | ||
| 2012 | Post-emergent yellow-nutsedge and crabgrass herbicide; supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 2013 | Grub insecticide: supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 2014 | NA | 0 | EV | ||
| 2015 | Overseed turfgrass: 2.2 acres in Historic cemetery and Confederate plot -- September | 1 | EV | ||
| 2016 | Fall leaf removal | 10 | EV | ||
| 2017 | Planting beds & tree rings -- mulch and edge maintenance -- April/early May | 1 | EV | ||
| 2018 | Planting beds & tree rings -- pre-emergence herbicide -- April and September | 2 | EV | ||
| 2019 | Planting beds & tree rings:emerged weed removal/control -- April through October | 7 | MO | ||
| 2020 | Shrub maintenance/pruning: Spring and Fall | 2 | EV | ||
| 2021 | Japanese Beetle control on trees and shrubs (optional) | 2 | EV | ||
| 2022 | Mole and rodent control: extermination and pest svcs | 8 | MO | ||
| 2023 | Soil sampling/testing (optional) | 1 | EA | ||
| 2024 | Sunken Grave Repair | 15 | EA | ||
| 2025 | Turfgrass renovation | 600 | SF | ||
| 2026 | Irrigation system: fall shutdown, spring startup, backflow testing | 2 | EA | ||
| 2027 | Irrigation system: operation and maintenance | 8 | MO | ||
| 2028 | Road cleaning/sweeping/blowing | 12 | MO | ||
| 2029 | Trash and debris removal | 12 | MO | ||
| 2030 | Pressure wash commital shelter, columbaria, other hardscapes | 2 | EV | ||
| 2031 | Insect and pest control at committal shelter and Admin Building (optional) | 8 | MO | ||
| 2032 | Snow removal and Ice Melt application: streets, parking lots; walkways and sidewalks | 24 | EV | ||
| 2033 | Headstone cleaning - all 2,095 | 2095 | EA | ||
| 2034 | Tree pruning | 10 | EA | ||
| 2035 | Tree removal | 2 | EA | ||
| 2036 | Tree stump removal | 2 | EA | ||
| 2037 | Ice Melt Application | 12 | EV | ||
| Subtotal (Services) | $ - 0 | ||||
| Aggregated Total (Supplies & Services) | ERROR:#REF! |
INTERNAL FOR OFFICIAL GOVERNMENT USE ONLY
OY3
| Services | |||||
| CLIN | Description | Est. Qty | Unit | Unit Price | Extended Price |
| 3001 | Interment shelter: cleaning and flag raising/lowering | 270 | EA | ||
| 3002 | Transport urn and floral arrangements | 350 | EA | ||
| 3003 | Receive & Install new and replaced niche covers | 350 | EA | ||
| 3004 | Support for weekend or Holiday interments | 10 | EA | ||
| 3005 | Support for Holidays and Special Events | 2 | EA | ||
| 3006 | Mow turfgrass (2.2 acres) | 39 | EA | ||
| 3007 | String trim around 2,095 headstones | 39 | EV | ||
| 3008 | Blade edge along sidewalks, curbs, and other flat surfaces | 8 | MO | ||
| 3009 | Fertilizer: supply and apply over historic, Confederate, and 12 Annex acres; early May, early Sep, and early Nov | 3 | EV | ||
| 3010 | Pre-emergent herbicide: supply and apply on 14.2 acres twice: Mar/April and late June | 2 | EV | ||
| 3011 | Post-emergent broadleaf herbicide; supply and apply to 14.2 acres twice -- mid-May and late June | 2 | EV | ||
| 3012 | Post-emergent yellow-nutsedge and crabgrass herbicide; supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 3013 | Grub insecticide: supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 3014 | NA | 0 | EV | ||
| 3015 | Overseed turfgrass: 2.2 acres in Historic cemetery and Confederate plot -- September | 1 | EV | ||
| 3016 | Fall leaf removal | 10 | EV | ||
| 3017 | Planting beds & tree rings -- mulch and edge maintenance -- April/early May | 1 | EV | ||
| 3018 | Planting beds & tree rings -- pre-emergence herbicide -- April and September | 2 | EV | ||
| 3019 | Planting beds & tree rings:emerged weed removal/control -- April through October | 7 | MO | ||
| 3020 | Shrub maintenance/pruning: Spring and Fall | 2 | EV | ||
| 3021 | Japanese Beetle control on trees and shrubs (optional) | 2 | EV | ||
| 3022 | Mole and rodent control: extermination and pest svcs | 8 | MO | ||
| 3023 | Soil sampling/testing (optional) | 1 | EA | ||
| 3024 | Sunken Grave Repair | 15 | EA | ||
| 3025 | Turfgrass renovation | 600 | SF | ||
| 3026 | Irrigation system: fall shutdown, spring startup, backflow testing | 2 | EA | ||
| 3027 | Irrigation system: operation and maintenance | 8 | MO | ||
| 3028 | Road cleaning/sweeping/blowing | 12 | MO | ||
| 3029 | Trash and debris removal | 12 | MO | ||
| 3030 | Pressure wash commital shelter, columbaria, other hardscapes | 2 | EV | ||
| 3031 | Insect and pest control at committal shelter and Admin Building (optional) | 8 | MO | ||
| 3032 | Snow removal and Ice Melt application: streets, parking lots; walkways and sidewalks | 24 | EV | ||
| 3033 | Headstone cleaning - all 2,095 | 2095 | EA | ||
| 3034 | Tree pruning | 10 | EA | ||
| 3035 | Tree removal | 2 | EA | ||
| 3036 | Tree stump removal | 2 | EA | ||
| 3037 | Ice Melt Application | 12 | EV | ||
| Subtotal (Services) | $ - 0 | ||||
| Aggregated Total (Supplies & Services) | ERROR:#REF! | ||||
| ** Each period of performance requires an IGCE – (base award, and all option periods require an IGCE) |
INTERNAL FOR OFFICIAL GOVERNMENT USE ONLY
OY4
| Services | |||||
| CLIN | Description | Est. Qty | Unit | Unit Price | Extended Price |
| 4001 | Interment shelter: cleaning and flag raising/lowering | 270 | EA | ||
| 4002 | Transport urn and floral arrangements | 350 | EA | ||
| 4003 | Receive & Install new and replaced niche covers | 350 | EA | ||
| 4004 | Support for weekend or Holiday interments | 10 | EA | ||
| 4005 | Support for Holidays and Special Events | 2 | EA | ||
| 4006 | Mow turfgrass (2.2 acres) | 39 | EA | ||
| 4007 | String trim around 2,095 headstones | 39 | EV | ||
| 4008 | Blade edge along sidewalks, curbs, and other flat surfaces | 8 | MO | ||
| 4009 | Fertilizer: supply and apply over historic, Confederate, and 12 Annex acres; early May, early Sep, and early Nov | 3 | EV | ||
| 4010 | Pre-emergent herbicide: supply and apply on 14.2 acres twice: Mar/April and late June | 2 | EV | ||
| 4011 | Post-emergent broadleaf herbicide; supply and apply to 14.2 acres twice -- mid-May and late June | 2 | EV | ||
| 4012 | Post-emergent yellow-nutsedge and crabgrass herbicide; supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 4013 | Grub insecticide: supply and apply to 14.2 acres once -- June | 1 | EV | ||
| 4014 | NA | 0 | EV | ||
| 4015 | Overseed turfgrass: 2.2 acres in Historic cemetery and Confederate plot -- September | 1 | EV | ||
| 4016 | Fall leaf removal | 10 | EV | ||
| 4017 | Planting beds & tree rings -- mulch and edge maintenance -- April/early May | 1 | EV | ||
| 4018 | Planting beds & tree rings -- pre-emergence herbicide -- April and September | 2 | EV | ||
| 4019 | Planting beds & tree rings:emerged weed removal/control -- April through October | 7 | MO | ||
| 4020 | Shrub maintenance/pruning: Spring and Fall | 2 | EV | ||
| 4021 | Japanese Beetle control on trees and shrubs (optional) | 2 | EV | ||
| 4022 | Mole and rodent control: extermination and pest svcs | 8 | MO | ||
| 4023 | Soil sampling/testing (optional) | 1 | EA | ||
| 4024 | Sunken Grave Repair | 15 | EA | ||
| 4025 | Turfgrass renovation | 600 | SF | ||
| 4026 | Irrigation system: fall shutdown, spring startup, backflow testing | 2 | EA | ||
| 4027 | Irrigation system: operation and maintenance | 8 | MO | ||
| 4028 | Road cleaning/sweeping/blowing | 12 | MO | ||
| 4029 | Trash and debris removal | 12 | MO | ||
| 4030 | Pressure wash commital shelter, columbaria, other hardscapes | 2 | EV | ||
| 4031 | Insect and pest control at committal shelter and Admin Building (optional) | 8 | MO | ||
| 4032 | Snow removal and Ice Melt application: streets, parking lots; walkways and sidewalks | 24 | EV | ||
| 4033 | Headstone cleaning - all 2,095 | 2095 | EA | ||
| 4034 | Tree pruning | 10 | EA | ||
| 4035 | Tree removal | 2 | EA | ||
| 4036 | Tree stump removal | 2 | EA | ||
| 4037 | Ice Melt Application | 12 | EV | ||
| Subtotal (Services) | $ - 0 | ||||
| Aggregated Total (Supplies & Services) | ERROR:#REF! |