QKA Cattle Guard Replacement SOW Final.pdf
PDF 220 KB Posted
- Attached to
- QKA Cattle Guard Replacement
- Solicitation number
- 697DCK-24-R-00168
About this file
This solicitation and statement of work describe a federal contract opportunity for cattle guard replacement services at a Federal Aviation Administration radar site in Hawaii. The contractor will demolish five existing cattle guards and concrete basins, construct five new steel cattle guards rated to AASHTO standards with reinforced concrete catch basins, install composite fencing and HDPE drainpipes, and perform associated work. The opportunity is set aside for small businesses, with an estimated value between $250,000 and $500,000. Interested parties must submit technical and cost proposals by March 21, 2024 to be considered for the firm fixed price contract award. The optional site visit will be held on March 7, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
November 03, 2023
Mt. Ka’ala Road Cattle Guard Replacement
SCOPE OF WORK
The Contractor shall design, engineer and furnish all materials, labor, supervision, products, equipment, permits, insurance, etc. to complete replacement of five (5) existing cattle guards, associated catch basins, and miscellaneous site work at the Mt. Ka’ala Air Route Surveillance Radar (ARSR) radar site access road, located in the Mokule’ia Forest Reserve, Hawaii. The work includes the following principal items:
A. Scope
1. Construction and installation of five (5) heavy-duty metal cattle guards and new concrete water catch basins with drains.
2. The design portion of this project will require one initial site visit and both a 50% and 90% review with FAA representatives.
3. Installation of 3’ high silt fence on both sides of access road to encompass each area of work and any material storage.
4. Demolition and removal of five (5) existing cattle guards and concrete basins.
a. Asphalt road cutting as required.
b. All site preparation for new catch basins and drains.
c. Overburden removal and grading.
d. Rock and gravel for pad, reinforced concrete catch basins, drains and erosion control.
5. Construction will include but is not limited to:
a. Installation of new steel cattle guards with reinforced concrete catch basins functionally similar to the existing cattle guards and rated to American Association of State Highway and Transportation Officials (AASHTO) U80 standard.
b. Concrete approach aprons min 24” to each side of new cattle guard.
c. New asphalt patching as required.
d. Installation of new weather resistant composite fencing on each side of the road attached to the cattle guards.
e. Installation of 8” UV protected HDPE double wall drain pipe to extend 10’ to 24’ beyond the basin, and erosion control and end sections at the drain water outlet to protect the environment. The following items are a summary of the project and are provided solely for the purpose of describing the general nature and constraints of the work. The Contractor is responsible for accomplishing all items of work identified in the design/engineering, applicable drawings, specifications, and provisions of the contract:
B. General
1. Contractor will be responsible for a design build approach for new steel cattle guard with AASHTO U80 standard weight rating, reinforced concrete water catch basins, and associated components.
2. Mt. Ka’ala (QKA) Air Traffic facility and its access road comprise an active operational facility, manned 24 hours a day, 7 days a week.
3. Mt. Ka’ala Road is a paved one lane private and government road located approximately 3.5 miles west of Waialua, Hawaii in both agricultural lands and the Mokule’ia Forest Reserve. Access is controlled with multiple locked gates.
4. All work shall be coordinated with the FAA and be accomplished on a “Not to interfere with FAA and field operations” basis. FAA Contracting Officer Representative (COR), or designee, will be present during contractor work hours to provide gate access, road use coordination via radio, up/down traffic awareness, and other duties as required.
5. Construction Hours. Work shall take place during normal business hours, 0700 to 1600, Monday through Friday, weekends and national holidays excluded.
6. Road Access and Closures:
a. Mt. Ka’ala road uses controlled access via three locked gates. Road traffic is coordinated using handheld radios to avoid conflict between up and down traffic. In addition to milage markers, sequential culvert numbering (1-80) provides road position.
b. With prior coordination, the Ka’ala road can be closed to all traffic during periods between 10:00am and 4:00pm, Monday through Friday. Such as when existing cattle guards are removed and replaced. Closures are normally limited to 4 hrs.
in length but can be extended up to 6 hours on a case by case basis.
c. Outside of road closure periods, work can continue allowing for unfettered road use by operational vehicle traffic. Radio coordination of traffic headed up/down provides time to ready work site(s) to allow traffic through.
d. Outside of the road closure periods, and project work hours, unattended road access is required to maintain unfettered traffic flow 24/7 (e.g steel plating, temporary bridge, temporary rerouting around work site).
7. Construction material shall be stored only in FAA approved areas.
8. Construction staging shall be allowed only in the FAA approved areas.
9. The Contractor shall provide all temporary services required for construction.
10. There will be no utilities available to the Contractor during construction at the sites.
a. Temporary Electrical Power: 120V/240V electrical power is not available at this site for use the Contractor shall provide all temporary power as required for the duration of the project.
b. Sanitary Facilities: Sanitary Facilities are not available at this work site. The Contractor shall provide temporary toilet facilities as required for employees.
11. The Contractor shall clean up and restore the site grounds to its original condition after the work has been performed.
12. Contractor will be responsible for any road damage that occurs as a result of equipment or operator usage.
13. The Contractor shall have had experience with similar installations of comparable size and complexity as regards to coordinating, installation work, and job supervision. Evidence shall be submitted upon request of the Contracting Officer.
14. The Contractor shall comply with all Local, State, and Federal laws, rules and regulations governing the work including the National Electrical Code, Uniform Building Code, and Fire Life Safety codes. Associated Hawaii Department of Land and Natural Resources (HI DNLR)) code requirements and specifications. The Contractor is responsible to ensure that copies of specified codes and standards are readily available to their personnel.
15. The Contractor is responsible to ensure that their personnel are familiar with workmanship and installation requirements of specified codes, regulatory requirements, consensus standards, and DOT/FAA referenced directives.
C. Engineering & Design
1. The contractor shall identify (5) new nominal 8’ x 14’ steel cattle guards and reinforced concrete water catch basins with drains, Engineer and draw up all site prep, drainage, and fencing constructed of composite weather and UV resistant materials:
a. The steel cattle guards will sit flush within the concrete water catch basins and need to withstand a AASHTO U80 standard vehicle load. The cattle guard needs to be designed for convenient removal for maintenance using existing road maintenance equipment (e.g Caterpillar 236D3). The fencing on each side of the cattle guards needs to be designed for convenient removal and detachment from the cattle guard base for wide load traffic.
b. The concrete catch basin and cattle guard construction is a major component of this project, and prior to purchasing or completing involved design work, submittals must be reviewed and approved by the FAA representative for this project.
c. Concrete catch basin drains shall be a minimum of 8”in diameter. 4 of the 5 catch basin drains need the drain flange located in lower left corner of the basin
d. and 1 of the 5 catch basin drains need the drain flange located in the upper left corner. Drain locations will be confirmed on the contractor site walkthrough.
e. Drain piping: Extend 8” UV/weather resistant HDPE pipes out of basin 10’ to 24’ as required for each cattle guard using manufactured fittings. Install pit run rock and pipe ends at the end of the drain to prevent soil erosion and bury remaining piping with appropriate material.
2. The new cattle guard assemblies and its subparts must be reviewed/stamped by a licensed PE registered in the state of Hawaii.
3. Prior to final design approval, review is required at 50% completion and another at 90% completion to address any comments/questions or changes to the project with FAA representatives. Submittal will be reviewed for proper operation and compliance with requirements detailed in this section.
4. Submittals
a. Submit product/technical data for the Cattle guard.
b. Submit product/technical data for pre-cast concrete products.
c. Submit product/technical data for cast in place concrete (e.g. mix design, reinforcing steel, imbed steel).
d. Submit product/technical data for HDPE drainpipe and fittings.
e. Submit product/technical data for appurtenances to cattle guards (e.g. load limit signage, fencing, protective coatings, etc).
f. Submit product/technical data requested by the CO or COR.
g. Submit all submittals to the Contracting Officer via e-mail.
5. Inspections
a. Access for Inspection - The Contractor shall allow the COR complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the COR before being obscured by the next operation of the Contractor. Work obscured before inspection and acceptance by the COR, may, at the option of the COR be opened for inspection at no additional cost to Government.
b. The COR will inspect all work in progress up to completion and final Contractor's Acceptance Inspection (CAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The COR will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.
c. Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The COR will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present and it may be held concurrently with the CAI.
D. Demolition
1. Remove and properly dispose of all clean non-contaminated construction debris, overburden (vegetation, soil, rocks, etc.,) off site. Cut existing asphalt back if needed so damage does not occur to existing asphalt. Any contaminated overburden (asphalt, metal, concrete, etc.,) must be disposed of in accordance with state and local regulations and removed from site. The FAA will retain copies of disposal if required.
2. Privately owned fencing abutting existing cattle guards will be disassembled and removed for reuse and restoration of fence line to new cattle guards. At a minimum, the fence line work will extend to the first fence post away from each side of existing cattle guards.
3. Confirming and obtaining all required permits and inspections required by the State of Hawaii, Division of Forestry and Wildlife and/or the Island of Oahu Mokulē’ia Forest Reserve Management Offices and the National Environmental Policy Act
(NEPA).
4. See section A. General, for Road Closure requirements.
E. Installation
Site Prep
1. See section A. General, for Road Closure requirements.
2. Remove all trees and vegetation from the designated location.
3. Placement of geotextile fabric and a 4” aggregate base, including compaction.
4. Grade water drain and ensure pipe outlets are placed on rocked areas for erosion control. All construction practices must be in accordance with state and local codes and be properly designed for the associated climate zone.
5. Install concrete basins, cattle guard support, concrete approaches to cattle guards, cattle guards, fences, drains, and restore asphalt to the original condition.
6. All materials, e.g. gravel, shot rock, concrete, and cattle guard materials, will need to be transported to the site by the contractor.
Steel Cattle Guards
1. Provide and install (5) steel cattle guards with hot dipped galvanized finish, reinforced concrete water catch basins with 8” water drains, and composite UV/weather rated fencing per specifications stated above.
2. The contractor will supply all equipment, tools, materials, and parts required to complete this project.
3. Will be constructed per manufacturers specification, State and Federal building codes, and FAA specifications and standards.
Testing
1. Provide engineered specs and test results to FAA representative.
1.2 APPLICABLE DOCUMENTS
A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construction drawings refer to the latest editions (and any supplements) in effect on the date of the contract.
B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
1. Code of Federal Regulations (CFR):
a. OSHA General Industry Safety and Health Standards (29 CFR 1910), OSHA
Construction Industry Standards (29 CFR 1926). OSHA 2202 is a condensed version of 29 CFR 1926. Each is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.
1.3 DEFINITIONS
A. Federal Aviation Administration (FAA) - The terms "Federal Aviation Administration" (FAA) and "government" as used herein denotes the "owner".
B. Contracting Officer (CO) - The term "Contracting Officer" (CO) as used herein denotes the person designated to authorize or make changes to this contract on behalf of the government.
C. Contracting Officers Representative (COR) - The term "COR” as used herein denotes the representative of the Contracting Officer at the job site. The term is synonymous with the FAA terms "Resident Engineer" (RE).
D. Contractor and Subcontractor - The term "Contractor" as used herein denotes the firm who will perform and complete the work required by the Contract. The term "subcontractor" as used herein denotes the person or firm retained by the Contractor to perform a particular unit of work required by the Contractor. Subcontractors shall be required to meet all specifications required of the Contractor.
1.4 CONSTRUCTION CONDITIONS
A. Submittals – Engineering and design submittals will go through the 50% and 90% review process with the Contractor/Sub-Contractor(s), COR, and other FAA representatives, as required. Prior to submitting orders, the contractor shall submit specifications for each new component of the installation for approval. Of note: the cattle guard construction selection is a major component of this project and should be approved by the FAA representative early in the design process as to avoid any delay or redesign due to changes. During the project contractor shall provide submittals for Samples, certificates, reports, catalog cuts, letters, shop drawings, red-lines, maintenance and operations manuals, etc. as required. All documents shall be submitted to the COR and a hard copy binder to FAA site Tech.
B. Inspection
1. Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The RE will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present. It may be held concurrently with the CAI.
C. Project Coordination - The Contractor shall be required to coordinate his/her construction activities with the FAA through the COR. All work which affects the facility shall be coordinated and approved by FAA personnel through the COR at least 10 days in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA, through the COR, 5 days in advance. Each shutdown shall be limited and off-peak hours shall be required for testing or power shutdowns, with the facility placed back in service at the end of the workday, or as stipulated by the FAA.
D. Schedules
1. Project schedule showing salient tasks (E.g. from Notice to Proceed to completion of work and acceptance).
2. Hours of Work – Shall be approved by the COR. Most of the work is expected to be performed during normal working hours, 0700 to 1600, Monday through Friday, weekends and national holidays excluded.
3. Some work may be required afterhours. Work on weekends and Federal holidays shall be approved before time by the COR in writing.
E. Site Access - Access to the site will be via a pre-determined route identified and agreed upon at the pre-construction conference.
F. Waste Disposal - The Contractor shall provide on-site containers for the collection of construction waste materials, debris and rubbish and their daily removal from the site.
Any spillage on access and haul routes shall be cleaned up immediately. All spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents shall be disposed of off-site in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste.
The Contractor, at no additional cost to the government, shall pay disposal fees and miscellaneous charges. Copies of all documentation of the disposal of any fuel or hazardous wastes will be submitted to the COR.
G. Cleanup - The work site shall be kept clean and orderly during the progress of work.
After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.
H. O & M - Upon completion of the facility modifications, the Contractor shall provide operation and maintenance instructions for all new equipment. This information will then be retained by the COR (and the FAA) and used to reflect the as-constructed conditions.
1.5 SAFETY
OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:
A. Safety Plan - The Contractor shall have and submit a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site.
The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.
B. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. The COR may request documentation or other evidence of training at any time. Personnel without adequate training will be prohibited from using such equipment.
C. Lock Out / Tag Out – The Contractor shall employ and detail lock-out / tag-out procedures to employees working with and around electrical systems. When accessing an electrical panel, a FAA technician must be present prior to interrupting and energizing the breakers.
D. Material Safety Data Sheets - The Contractor shall have Material Safety Data Sheets
(MSDS) conforming to Federal Standard 313A, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. One (1) copy of each MSDS shall be submitted to the COR and one (1) copy of each MSDS shall be kept on file at the job site at all times. The Contractor and subcontractors will be prohibited from handling any material which does not have an applicable MSDS on file at the site until such MSDS arrives on site.
E. Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating.
F. HAZCOM Program - The Contractor shall have a hazard communications (HAZCOM) program. The Contractor and each subcontractor shall submit a copy of their HAZCOM program as well as a copy of their current OSHA 200 form, if requested.
G. Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the COR may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The COR may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.
H. Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.
2.0 CONTRACTOR-FURNISHED MATERIAL AND EQUIPMENT
2.1 MATERIAL DELIVERIES
All material deliveries made under this contract shall be arranged for delivery to the Contractor's material staging area. This area shall be located as determined at the pre-construction conference.
2.3 PERTINENT INFORMATION
Any pertinent information listed about the contractor-furnished material and equipment shall be submitted to the COR.
3.0 EXECUTION
3.1 WORK SEQUENCE
General: Mt. Ka’ala (QKA) is an active operational facility, which runs 24 hours a day, 7 days a week; therefore, all work shall be coordinated and accomplished on a “Not to interfere with FAA operations” basis.
3.2 CONTRACTOR USE OF PREMISES
A. Use of the Site - Do not disturb portions of the site beyond the areas in which work is required.
B. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government, the Government’s employees, and emergency vehicles at all time. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Use of the Existing Building - Maintain the existing building in a watertight condition throughout the construction period. Repair damage caused by construction operations.
Take all precautions necessary to protect the building during the construction period.
END OF SECTION
| C. Engineering & Design |
| 1.2 APPLICABLE DOCUMENTS |
| A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construc... |
| B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only. |
| 1.3 DEFINITIONS |
| 1.4 CONSTRUCTION CONDITIONS |