About this file
This document appears to be a question and answer (Q&A) file related to a state or local government contract opportunity for the removal and installation of new carpet. The contract includes the removal and replacement of 4" vinyl cove base in specified areas on the 4th and 5th floors of a building. The contractor is responsible for providing a dumpster for the disposal of the old carpet, which can be placed near the loading dock. The document confirms the specific areas on the 4th and 5th floors that will receive new carpet, excluding private offices. A mandatory site visit is required, despite any previous walkthroughs of the areas.
The pricing and other contractual terms are not detailed in this Q&A document. However, it appears this is an active procurement with a defined scope of work, and the contracting agency is responsive to bidder questions to ensure a clear understanding of the requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ-Carpet~1.docx | DOCX document | |
| standard-terms-and-conditions.pdf | ||
| forms-b.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions/Answers
Q1) Should the Removal and Replacement of the 4'' Vinyl Cove Wall Base be included in the bid? Currently the RFQ Document does not call for it. Removal of vinyl cove base is necessary in order to remove and reinstall carpet.
A1) The RFQ calls for installation material – so all remove of all carpet to include vinyl cove base should be included in your bid.
Q2) Should Haul-away and Disposal of the old carpet be included in the bid or will customer be providing an on-site dumpster? If Customer is not providing on-site dumpster will customer allow vendor to stage a 40 Yard dumpster on-site near dock?
A2) Dumpster should be provided by vendor. A dumpster can be placed to the south of the loading dock, approximately 75 feet away from the dock itself.
Q3) Please confirm the following 4th Floor areas to receive new carpet: Corporate Regulation Areas- Common Areas Including Vestibule and Closets with a Stopping Point Southwest Central Files Doorway. Private Offices not Included.
A3) Please confirm with site visit.
Q4) Please confirm the following 5th Floor areas to receive new carpet: Corporate Regulation Areas - Common Areas North Side, East, West Sides Including Vestibules and Closets with a Stopping Point Midway between producer regulation. Private Offices and Licensing Areas not Included.
A4) Please confirm with site visit.
Q5) If areas have been walked previously is the mandatory site visit required?
A5) You will need attend mandatory site visit as instructed in the RFQ.