QA_QLV27007039 V1.0.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
URI Engineering Consultant for Utility Modeling
Solicitation number
QLV27007039
Issued by
Providence County, Rhode Island

About this file

This is a Questions and Answers document related to a University of Rhode Island procurement for engineering consulting services to develop comprehensive computer utility models for the institution's water, sewer, stormwater, steam, natural gas, and electric systems across three campuses. The University will provide existing GIS data, CCTV inspection reports, meter data, and hydraulic models to support the consultant's work. The consultant will develop utility models, conduct field surveys of sewer and drainage structure rims and inverts, perform model calibrations and simulations, and deliver model files in formats the consultant justifies as optimal. The scope includes project management with bi-weekly virtual meetings and quarterly model updates. The geographic limits encompass all University-owned utility systems at the Kingston, Narragansett Bay, and W. Alton Jones campuses. The contract term begins approximately December 1, 2026, for an initial three-year period with two optional 12-month renewal periods contingent on performance and fund availability. Proposals were due October 30, 2026, at 1:30 PM EDT following a pre-bid meeting on October 13, 2026.

A minimum 10 percent Minority/Women Business Enterprise (MBE/WBE) participation is required, with certified firms identified through the Rhode Island Department of Administration MBE Compliance Office. The solicitation is qualifications-based, with technical proposals evaluated on a 100-point scale addressing staff qualifications, vendor capability with client references, work plan, methodology, and interview performance. Vendors must be Rhode Island-registered professional engineers with a minimum of 10 years' experience in computerized utility model development. The highest-scoring proposal must achieve a minimum of 80 points before cost negotiations commence. Required insurance includes $2 million professional liability per occurrence with $2 million annual aggregate, $1 million general liability, $100,000 workers' compensation, and $1 million automobile liability. A 0.33 percent contract administrative fee will be withheld from all invoices. The consultant will own and operate the modeling software under license, while the University will own the resulting model files for each utility system.

View the file

Other files

File Type Posted
QLV27007039_Nov_4_26_solicitation_doc.pdf PDF
QLV27007039_Oct_22_26_solicitation_doc.pdf PDF
QLV27007039 Addendum 1.doc DOC document
QLV27007039_Nov_5_26_solicitation_doc.pdf PDF
QLV27007039_Oct_13_26_solicitation_doc.pdf PDF
QLV27007039_Nov_2_26_solicitation_doc.pdf PDF
QLV27007039_Nov_11_26_solicitation_doc.pdf PDF
VendorChangeDetailsReport_QLV27007039_v1_Oct_2_26.pdf PDF
QLV27007039_Oct_5_26_solicitation_doc.pdf PDF
QLV27007039_Nov_17_26_solicitation_doc.pdf PDF
QLV27007039_Oct_30_26_solicitation_doc.pdf PDF
QLV27007039_Oct_28_26_solicitation_doc.pdf PDF
QLV27007039_Oct_26_26_solicitation_doc.pdf PDF
QLV27007039_Nov_18_26_solicitation_doc.pdf PDF
QLV27007039_Nov_12_26_solicitation_doc.pdf PDF
QLV27007039_Oct_29_26_solicitation_doc.pdf PDF
QLV27007039_Nov_19_26_solicitation_doc.pdf PDF
VendorChangeDetailsReport_QLV27007039_v3_Oct_22_26.pdf PDF
QLV27007039_Nov_6_26_solicitation_doc.pdf PDF
Prebid QLV27007039 URI Engineering Consultant for Utility Modeling.docx DOCX document
QLV27007039_Nov_3_26_solicitation_doc.pdf PDF
QLV27007039_Nov_10_26_solicitation_doc.pdf PDF
ISBE Form - RFP Appendix B - Modified Version.pdf PDF
QLV27007039_Nov_13_26_solicitation_doc.pdf PDF
QLV27007039_Oct_23_26_solicitation_doc.pdf PDF
QLV27007039 Scope of work.pdf PDF
QLV27007039_Oct_21_26_solicitation_doc.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Q&A QLV27007039 - URI Engineering Consultant for Utility Modeling
QuestionAnswer
For underground utility location, would you expect any SUE investigations through this project?No
Is surveying rims, inverts and other missing data included in the scope? Does URI have any existing survey, CCTV or flow data?Surveying rims and inverts in sewer and drainage structures shall be included in this scope. URI has CCTV inspection reports and video of major sewer and drain lines on the Kingston Campus.
For the W. Alton Jones septic systems and three water systems: a hydraulic model or an inventory only?Hydraulic models for water and sewer systems at W. Alton Jones campus shall be prepared to assess current and future loads/demands.
Can URI help get RIE supply pressures at the six gas master meters, and share RIE's earlier Kingston gas study?URI can request RIE supply pressures at URI's natural gas master meters.
Is SCADA or meter data available for calibration (wells, steam plant, gas master meters, electric submeters)?URI has a complete water model. Well meter and building meter data and hydrant fire flow test reports are available. Natural gas master meter data is available. Steam plant natural gas meter data is available. Monthly electric sub meter data is available from meters of varying ages.
Are there existing steam, gas, sewer or stormwater models URI can provide?See project solicitation for modeling information that is available.
Does URI want to run the models itself, or to own models it can give to any qualified firm? Who should hold the software licenses?URI will own the model file for each utility and the vendor is expected to provide these files to URI at the end of the contract. The vendor will have the software license and run the models.
Since this is a quals-based submission and no pricing is required at this time, do we need to submit the ISBE form with our submittal? Or will that only be required if selected and during contract negotiations?The modified ISBE is a commitment to the % participation and required to attach with your cost proposal. However only the tentative selected vendor will be required to submit an MBE plan to the MBECO office.
Is there a desire for the different utilities' GIS data to be delivered in an Esri utility network (UN) format)?The Vendor shall provide in their Technical Proposal justification of their chosen model format and why it is the best format to meet the needs of the University.
Are there any gauges or monitoring devices that can be used for calibration of the developed model?See answers to questions 6 and 7.
Are any video inspections or camera of drainage systems anticipated or expected?Video inspection of utility systems is not part of this scope.
Can you provide an estimate of the number of stormwater structures: Manholes, CB’s, Structures by campus?Kingston: 893 Catch Basins, 465 Drain Manholes, 122 BMPs, 174 Outfalls. NBC: 87 Catch Basins, 43 Drain Manholes, 1 BMPs, 10 Outfalls.
What is meant by the stormwater GIS layer is 70% accurate? What is accurate and what is lacking? Good information on 70% of the structures or only 70% of the structures are identified?The stormwater layer has areas of the Kingston Campus where construction has occurred and the drainage layer has not been updated. This accounts to approximately 30% of the Kingston drainage system.
10.Please clarify what the stated GIS accuracy percentages represent and correct the electrical GIS figure in Section A background.The accuracy percentages in the solicitation represents an estimate of the GIS mapping information to actual field conditions. A lower percentage indicates that less of the GIS mapping has not been field verified. The GIS information for the electrical distribution is 85% accurate.
How many simulations and reports should be assumed during the first year and subsequent years?Model simulations are largely dependent upon the amount of construction planned by the University. The 1st year simulations will be limited to models of utilities that are near completion (water, electric). These simulations will include identifying limiting areas of each utility network and also new construction designs.
Does the scope require new condition assessments, replacement cost estimates, and improvement priorities, or incorporation of existing condition information?Model simulations and assessments will involve cost estimating for budgeting purposes and setting priorities. The solicitation notes "It is preferred that the modeling software has a cost estimating feature for pipe replacement and can consider age and condition in setting pipe replacement priority".
What software, licensing, file formats, documentation, and training are required for URI’s ownership and use of the models?The vendor will own the modeling software and licensee. The vendor will operate the models to answer questions posed by URI. URI will own the modeling files.
Please clarify the electrical modeling responsibilities under this contract relative to CHA’s existing services.The vendor will be responsible for performing electric model development and simulations under this project. CHA's existing contract for high and medium voltage consulting will continue. CHA will need access the electric model.
What calibration and acceptance criteria apply to each model, and who is responsible for associated field testing and monitoring?URI requires a professional engineer with expertise in utility modeling for this project and to advise URI on the calibration and acceptance criteria needed for each model. The vendor will be responsible for associated field testing and monitoring.
What GIS data, editable models, records, and loading information will URI provide? Will the consultant have direct GIS access, and what known data gaps exist?URI will provide the each GIS utility layer, existing models, and meter data to the selected vendor. View access to URIs GIS portal can be provided. The known data gaps are summarized in the solicitation.
Please confirm the geographic limits and required model detail for each utility, including building services, catch basin connections, BMPs, and septic systems.The geographic limits are the limits of each URI owned utility systems on each campus. The required model detail for each utility includes the structures, conduits and components necessary to assess flow, pressure, amperage, pressure loss, resistance, voltage, etc. at each location along the utility distribution system.
Please confirm that the selected consultant and its subconsultants remain eligible to pursue future URI RFPs, including projects identified or evaluated under this contract.Since this is for Utility Modeling it would be determined based on what other future projects would be available by URI and if the modeling had any effect on the work requested from the future project. This would not effect a subcntractor in the bidding process again unless it directly conflicted witht the requested modeling as requested in this current RFP being bid.
Please confirm that additional survey is included in the initial phase and that the selected consultant will work with URI to identify gaps in existing survey information for all applicable utilities. What survey limits per campus should be assumed?Survey of rim and inverts of sewer and drainage structures is included in the initial phase. The limits of the survey will be the extent of the URI owned utility systems on each campus.