This document is a Questions & Answers (Q&A) file for the 2025 Benedict Park Stairs Project, issued by the Town of Snowmass Village under project number 055-73-58-573626. The Q&A addresses a specific inquiry from a potential contractor regarding the availability of staircase drawings for the project. The response clarifies that detailed stair information can be found on pages 10 and 11 of the project plans, with additional specifications in Section 05 5119. The document indicates that shop drawings will be a required submittal by the contractor after being awarded the contract, to ensure the stairs meet the project's design requirements prior to fabrication.
No pricing, funding details, or additional project specifics are provided in this Q&A document. The file appears to be part of the pre-construction communication process, focusing solely on providing clarification about the technical documentation related to the stair design for the Benedict Park project in Snowmass Village.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - 1
Project 055-73-58-573626: 2025 - Benedict Park Stairs Project
Buying Organization Town of Snowmass Village
No Question/Answer Question Date
Q1 Question: Drawings for staircase
Hi Mike didn't see any plans for staircase
Answer: The plans include information on the stairs on pages 10 & 11. More information is also supplied in Section 05 5119 of the specifications. Shops drawings will be a required submittal by the contractor once under contract to ensure the stairs meet the requirements/design prior to fabrication.
08/26/2025