Q&A Document 1.pdf
PDF 2 KB Posted
- Attached to
- Pump Station J Overflow Wet Well Rehabilitation
- Solicitation number
- 24-2540
- Issued by
- Muskegon County, Michigan
About this file
This document is a Questions and Answers (Q&A) file for the Pump Station J Overflow Wet Well Rehabilitation project issued by Muskegon County, Michigan. The document contains a single question (Q1) dated 03/27/2024 regarding the liner system for the project, specifically inquiring about the potential approval of the OBIC Liner system as an equal or better option, the necessity of destructive testing, and the required epoxy thickness for single layer applications. The response directs the inquirer to consult Addendum #1 for detailed answers to these technical questions about the wet well rehabilitation project.
The Q&A document does not provide specific pricing details, funding sources, or contract terms. The focus appears to be on technical specifications related to the liner system and coating application for the pump station wet well. The document suggests that more detailed information about the proposed alternatives and technical requirements will be found in the referenced Addendum #1, which is not included in this file. The project seems to involve a specialized rehabilitation of a pump station's wet well, with specific requirements for coating and testing methodologies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24-2540 Pump Station J Overflow Wet Well Rehabilitation.pdf | ||
| 24-2540 Pump Station J Overflow Wet Well Rehab Bid Sheet.xlsx | XLSX spreadsheet | |
| 24-2540 Pump Station J Overflow Wet Well Rehap Addendum #1.pdf | ||
| W9 BLANK.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - 1
Project 24-2540 - Pump Station J Overflow Wet Well Rehabilitation
Buying Organization Muskegon County
No Question/Answer Question Date
Q1 Question: Liner System
Would the OBIC Liner system be approved as an equal or better option?
Is the destructive testing necessary? There is an added cost to repair, what if lab testing can be provided in place of destructive test?
What thickness is being required by epoxy and other single layer applicaitons?
Answer: Please see attached Addendum #1 documentation for the answers to these questions.
03/27/2024