QA B-47475.docx

DOCX document 15 KB Posted

Attached to
Roadway Weather Information System
Solicitation number
25-494DOT-FINAD-B-47475
Issued by
Cook County, Illinois

About this file

This is a Questions & Answers document for procurement B-47475 involving the Illinois Department of Transportation (ILDOT) related to Road Weather Information System (RWIS) sites. The document addresses two key inquiries regarding the scope and requirements of the contract, with ILDOT anticipating the addition of 3-5 additional RWIS sites over the course of the agreement term.

The document clarifies that subcontractors will not be allowed for this procurement, referencing Section 1.6 which required clarification on this matter. Vendors who have already submitted bids are permitted to update their proposals based on the information provided in this Q&A document, ensuring compliance with the no-subcontractor requirement.

View the file

Other files

File Type Posted
IFB Offer to the State B47475.pdf PDF
IPG Vendor Disclosures Fomerly Forms B - B47475.docx DOCX document
QA3 B-47475.docx DOCX document
RWIS Summary QA Ref1.xlsx XLSX spreadsheet
Vendor DIsclosures Formerly Forms A - B47475~1.docx DOCX document
QA2 B-47475.docx DOCX document
IFB Vendor Instructions B47475~1.docx DOCX document
Contract RWIS B47475 Revised.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers B-47475

1. Q: How many RWIS sites does ILDOT anticipate adding during the term of the contact?

A: The Agency anticipates adding 3-5 additional sites over the course of the agreement.

1. Q: Are subcontractors allowed?

A: Section 1.6 needs clarification. Subcontractors will not be allowed. If Vendors have already submitted a bid Vendors are allowed to update their bid accordingly based off this Q&A document.