Q&A 3.pdf

PDF 288 KB Posted

Attached to
Central Florida Rail Corridor (CFRC) Track Improvements - Multiple Locations
Solicitation number
RFP-10060
Issued by
Volusia County, Florida

About this file

This document is a set of Questions and Answers (#3) related to a Florida Department of Transportation (FDOT) solicitation for track improvements to the Central Florida Rail Corridor (CFRC) at multiple locations. The solicitation includes four distinct projects: Project 1 (Universal Crossovers), Project 2 (Rail Renewal), Project 3 (Curve Reconstruction), and Project 4 (MOW Siding). The solicitation was advertised under No. DOT-RFP-25-5002-TIML, and the responses are due by October 2, 2024, at 10:00 am. A mandatory pre-proposal meeting was held on September 4, 2024. The document clarifies details related to the types of special trackwork materials, scope of work at grade crossings, and the scope of work for the MOW Siding project.

The solicitation is subject to a 1% MFMP Transaction Fee, and all bidders must be registered in the State of Florida's MyFloridaMarketplace system. Additionally, out-of-state companies must be authorized to do business in Florida, and any individuals providing services must be properly licensed by the Florida Department of Business and Professional Regulation. The solicitation also includes compliance with nondiscrimination statutes and authorities, such as Title VI of the Civil Rights Act of 1964.

View the file

Other files

File Type Posted
Addendum 1.pdf PDF
Agreement between Dept and Contractor.pdf PDF
Exhibit B - Method of Compensation.pdf PDF
Exhibit D.pdf PDF
Exhibit G - G101.00 Disp SunRail Material.pdf PDF
Exhibit M - CFRC Track Chart APRIL 2023.pdf PDF
Exhibit N - SunRail CMP-SMCP R3.pdf PDF
Exhibit E - Insurance Provisions.pdf PDF
Exhibit G - G101.00 Disp SunRail Material.pdf PDF
Exhibit H - CFRC GENERAL ORDER NO. 6 TTSI 2.pdf PDF
Exhibit L - CFRC TRACK AND SIGNAL CHART.pdf PDF
Agreement between Dept and Contractor.pdf PDF
Exhibit C - FTA Provisions.pdf PDF
Exhibit D.pdf PDF
Exhibit G - G101.00 Disp SunRail Material.pdf PDF
Exhibit I - CWR.pdf PDF
Exhibit N - SunRail CMP-SMCP R3.pdf PDF
Exhibit B - Method of Compensation.pdf PDF
Exhibit D.pdf PDF
Exhibit E - Insurance Provisions.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Exhibit L - CFRC TRACK AND SIGNAL CHART.pdf PDF
Addendum 4 Complete.pdf PDF
Agreement between Dept and Contractor.pdf PDF
Exhibit A - Scope of Services.pdf PDF
Exhibit B - Method of Compensation.pdf PDF
Exhibit F - Fence Policy.pdf PDF
Exhibit H - CFRC GENERAL ORDER NO. 6 TTSI 2.pdf PDF
Exhibit L - CFRC TRACK AND SIGNAL CHART.pdf PDF
Exhibit M - CFRC Track Chart APRIL 2023.pdf PDF
Exhibit N - SunRail CMP-SMCP R3.pdf PDF
Q&A 2 Complete.pdf PDF
Addendum 1.pdf PDF
Addendum 5 Complete - Part 2.pdf PDF
Agreement between Dept and Contractor.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
DOT-RFP-25-5002-TIML RFP.pdf PDF
Exhibit E - Insurance Provisions.pdf PDF
Exhibit I - CWR.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Exhibit L - CFRC TRACK AND SIGNAL CHART.pdf PDF
Exhibit O - CFRC MWIs.pdf PDF
Addendum 1.pdf PDF
Exhibit A - Scope of Services.pdf PDF
Exhibit C - FTA Provisions.pdf PDF
Exhibit D.pdf PDF
Exhibit F - Fence Policy.pdf PDF
Exhibit K - MOW MOS Operating Rules.pdf PDF
Q&A 1.pdf PDF
Addendum 2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Transportation

RON DESANTIS

GOVERNOR

605 Suwannee Street

Tallahassee, FL 32399-0450

JARED W. PERDUE, P.E.

SECRETARY

Improve Safety, Enhance Mobility, Inspire Innovation www.fdot.gov

Questions and Answers # 3

ADVERTISEMENT NUMBER: DOT-RFP-25-5002-TIML SunRail DESCRIPTION: Central Florida Rail Corridor (CFRC) Track Improvements - Multiple Locations

DATE: 9/11/2024

1. Project 1 (Universal Crossovers) – Please clarify if the special trackwork material stored at 523 N.

Garland Avenue is panelized or loose.

Answer: Crossovers panelized except the crossover “common ties”, 15 - 23 ft long ties.

2. Project 1 (Universal Crossover) – Section 3.1.1 of the Scope of Services document notes that

Contractor shall supply “OTM”. It is assumed that this is limited to track spikes and rail anchors only. Please confirm.

Answer: correct

3. Project 2 (Rail Renewal) includes the replacement of rail through several grade crossings.

Please clarify the scope of work at these locations.

Answer: At grade crossing cut existing rail at the grade crossing welded joints and match new rail to existing grade crossing rail. Assume no transition rails are required. All rail cuts shall be staggered in accordance with the CFRC MWI 801-06 CFRC Welding Manual.

4. Project 4 (MOW Siding) shows a 700’ underdrain on the plan & profile drawing which is not mentioned in the Scope of Services document. Please clarify.

Answer: The civil work including the underdrain is complete. The Project 4 scope of work is only for the construction of the MOW Storage track – ties, rail, fasteners, ballast, etc. See

Addendum 4 for revised MP806.3 Storage Track Plan.