This document is a Questions and Answers (Q&A No. 6) memorandum issued by the Los Angeles County Metropolitan Transportation Authority (LACMTA) regarding RFP No. AE141998 for CEQA/NEPA Environmental Compliance Services. The RFP solicits proposals for environmental compliance services across LACMTA sites, encompassing CEQA and NEPA analysis, environmental assessments, permitting assistance, field monitoring, and technical support including preparation of Initial Studies, Environmental Impact Reports, Negative Declarations, and Categorical Exclusions, as well as biological, cultural, geological, noise, air quality, stormwater, hazardous materials, and sustainability compliance evaluations. The contractor must maintain qualified personnel across multiple environmental disciplines, including a Program Director with 15 years of experience or equivalent, Project Managers, Quality Assurance Managers, and specialized environmental specialists. Services are delivered through individual Task Orders issued at LACMTA's sole discretion with no minimum work volume guarantee. The base contract duration is five years with no renewal options. The pre-proposal conference was held on June 29, 2026, with a proposal due date of August 19, 2026, and this Q&A document was issued on August 28, 2026.
This federally funded contract includes mandatory Small Business Enterprise (SBE) and Disabled Veteran Business Enterprise (DVBE) participation goals totaling 33 percent (30 percent SBE and 3 percent DVBE), with full attainment required for award eligibility; good faith efforts alone do not satisfy unmet goals. The contract is cost reimbursable plus fixed fee and subject to prevailing wage requirements and federal compliance certifications. Key clarifications in Q&A No. 6 address indirect cost rate requirements for SBEs/DVBEs, confirming that contractors must submit overhead rates in accordance with FAR Part 31 and contract specifications, with Metro accepting CPA-audited indirect rates or cognizant audits performed in accordance with FAR Part 31, while noting Metro does not currently offer a safe harbor or similar program for indirect rates. Additionally, the RFP permits 23 or more years of experience to be considered equivalent to a Master's degree for the Program Director/Principal role. All Q&A responses are stated to be for informational purposes only and non-binding; only formal written amendments revise the solicitation documents.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. AE141998/T:ga Q&A No. 6
August 28, 2026
To: All Plan holders
Subject: Questions and Answers No. 06 RFP No. AE141998 CEQA/NEPA Environmental Compliance Services
Attached please find a list of questions from potential Proposers with Metro’s formal answers, all pertaining to the subject Request for RFP. Please note none of the questions or answers contained in the attachment should be viewed as a change, modification, or revision to the subject RFP requirements.
Any change to the subject RFP will be issued under a formal Amendment to the RFP by Metro.
ATTACHMENTS:
Questions and Answers Spreadsheet
Issued by:
LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY
Stephen Tsang Principal, Contract Administration
The information addressed in the attached Questions and Answers are for information purposes only and are not binding on LACMTA. Only formal written Amendments may revise solicitaion documents.
CEQA/NEPA Environmental Compliance Services RFP No. AE141998
QUESTIONS AND ANSWERS (Q&A 6)
RFP No. AE141998/T:ga 1 Q&A No. 6
No. Date of Question Question Answer Answer Issued RFP
Amendment
1 08/26/2026
For SBEs/DVBEs who do not yet have an internally-calculated or audited overhead rate, what overhead rate should these SBEs/DVBEs use? While the Safe Harbor Rate is an option, what in-lieu indirect cost rate program does Metro offer for these SBEs/DVBEs?
Contractor should submit an overhead rate in accordance with as required by FAR part 31 and as specified in SP-12 and GC-44. Presently, Metro does not have safe harbor or similar program for indirect rates.
08/28/2026
2 08/26/2026
Are all subconsultants (big and small) required to have a CPA-audited indirect cost rate? If that is not feasible, what are the options to keep the SBEs/DVBEs on our team?
Contractor should submit an indirect cost rate as required by FAR part 31 and as specified in SP-12 and GC-44.
Metro will accept CPA audited indirect rates that was performed in accordance with FAR part 31. Metro will also accept a cognizant audit that was performed in accordance
08/28/2026
3 08/262026
Will Metro consider 23+ years of experience as equivalent to a Master’s degree for the Program Director/Principal role?
Yes. 08/28/2026