Q and A from prebid meeting for Garage Doors.docx
DOCX document 14 KB Posted
- Attached to
- Garage Doors at Physical Plant
- Solicitation number
- 25-444DHS-ISDIS-B-47035
- Issued by
- Mercer County, Illinois
About this file
This document is a Questions and Answers (Q&A) summary from a prebid meeting for a garage door replacement project at the Illinois School for the Deaf, with the project reference number B-47035. The meeting was held on 03/28/2025 and covered specific details about garage door specifications, installation requirements, and project logistics. The scope includes replacing multiple garage doors with 2-inch thick polyurethane doors, all to be white in color, and adding garage door openers to doors that currently lack them. Work hours are established as Monday-Friday from 7:00 am-3:30 pm, with flexibility for early arrival and late departure, and an on-site engineer available 24/7.
The project involves installing standard garage door openers, with vendors responsible for both the opener installation and low voltage wiring. The school will provide a junction box, and vendors are instructed to match existing window configurations. Specific requirements include adding openers to the north door and a door on the west side of the building, with the west side door's wall station to be positioned inside. No specific pricing, funding sources, or contract terms were detailed in this prebid meeting Q&A document, which appears to focus primarily on technical and logistical project specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| standard-terms-and-conditions 9-5-2024~17.pdf | ||
| Physical Plant Garage Doors SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers for Garage Doors at Power Plant Prebid 03/28/2025 10: am Illinois School for the Deaf B-47035
1) How insulated do you want the garage doors?
We want a Polyurethane door with a door thickness of 2”.
2) What kind of Garage Door Opener do you need.
Standard Garage Door Opener is fine.
3) Will We the vendors be responsible to hook up the Garage Door Openers.
Yes
4) Who will do the low voltage wiring?
The vendor will.
5) Do you want loose or conduit?
Loose is fine.
6) Do you want us to match the amount and size of the windows you currently have?
Yes, match what is currently there.
7) What are the work hours?
Hours are Monday-Friday 7:00 am-3:30 pm, but you can come in early and stay later if you need. We have an engineer on duty 24/7.
8) North door does not have a garage opener currently installed; do you want one on?
Yes, please add an opener to that door.
9) Will the school electrician bring a Junction Box?
Yes.
10) Do you want all the garage doors we are replacing to be white?
Yes, make them all white.
11) 1 door on the west side of building does not have an opener currently do you want one added?
Yes, please add an opener.
12) Where do you want the wall station for the door on the west side of the building?
Put it on the inside of the door.