This performance work statement outlines demolition services required at the Youngstown Local Training Area in New York. The contractor shall demolish all structures including one building, concrete pad and stairs, clean a 75 foot radius, and demolish two additional concrete structures. The contractor shall also provide a quote to demolish approximately three miles of chain link fencing and salvage any fence sections in good condition. The period of performance is 12 months. The contractor must attend a site visit on August 1, 2023 and submit all required licenses within 10 days of award. The contractor will be evaluated on quality control and meeting demolition standards at least 90% of the time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS YLTA DP FINAL MS Amended MAS.docx | DOCX document | |
| Site Visit notes and Q and As.docx | DOCX document | |
| W912PQ23Q0026-0001 (amendment).pdf | ||
| Youngstown Site Visit Attendance 2023-08-01_Redacted.pdf | ||
| YLTA Demo SOW(FED 2023) 08.02.2023 revised.pptx | PPTX presentation | |
| YLTA Demo PPT(FED 2023) 06.08.2023 FINAL.pptx | PPTX presentation | |
| W912PQ-23-Q-0026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR
Demolition Services
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Demolition Services, as defined in this PWS.
1.1.1 Objectives: (RESERVED)
1.2 Background: The 860-acre Youngstown Local Training Area (YLTA) located at 1525 Balmer Rd., Youngstown, NY 14131, is federally owned property is licensed to the New York Army National Guard. The Service Contract Act (SCA) prevailing wage applies work conducted at this location. Wage Decision is attached.
1.3 Period of Performance (PoP): The Period of Performance shall be 12 months.
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of (0600-1500) on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Youngstown Local Training Area, 1525 Balmer Rd., Youngstown, NY 14131. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Teleworking is not authorized.
1.4.1.1 Telework: The Government does not permit the contractor to telework in support of this requirement. In furtherance of Continuity of Operations Planning (COOP), a telework program may be enacted to ensure that the Government's mission-critical operations stay operational during times of national emergency or incidents of national significance. Telework shall be at no additional cost to the Government.
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation, including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days:
1.4.2.1 New Year’s Day: January 1st
1.4.2.2 Martin Luther King, Jr.’s Birthday
1.4.2.3 President’s Day
1.4.2.4 Memorial Day
1.4.2.5 Juneteenth National Independence Day: June 19th
1.4.2.6 Independence Day: July 4th
1.4.2.7 Labor Day
1.4.2.8 Columbus Day
1.4.2.9 Veteran’s Day: November 11th
1.4.2.10 Thanksgiving Day
1.4.2.11 Christmas Day: December 25th
1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS). A final QCP shall be submitted to the Contracting Officer Representative (COR) NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP.
1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.5 Installation Access and Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by Department of Defense (DoD), Headquarters Department of Army (HQDA) and/or local policy (see PWS 6.0). Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.4.5.1.1 Homeland Security Presidential Directive (HSPD)-12 Background Investigation Requirements: (RESERVED)
1.4.5.1.2 Trusted Associate Sponsorship System (TASS): (RESERVED)
1.4.5.2 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a Government representative).
1.4.5.3 Awareness Training (AT) Level 1: (RESERVED)
1.4.5.4 iWATCH Training: (RESERVED)
1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.6 (RESERVED)
1.4.5.7 (RESERVED)
1.4.5.8 (RESERVED)
1.4.5.9 (RESERVED)
1.4.5.10 (RESERVED)
1.4.5.11 OPSEC Training: (RESERVED)
1.4.5.12 OPSEC SOP/Plan. (RESERVED)
1.4.5.13 (RESERVED)
1.4.5.14 (RESERVED)
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1 Key Control. NOTE: All references to keys include key cards. The contractor shall establish and implement methods of ensuring that no keys/key cards issued by the Government are lost or misplaced or are used by unauthorized persons. No keys issued by the Government shall be duplicated. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The contractor shall include procedures covering key control in the QCP.
1.4.6.1.1 The contractor shall immediately report any occurrences of lost or duplicated keys/key cards to the COR.
1.4.6.1.2 In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon direction by the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the Government replaces or re-keys the locks, the Government will deduct the total cost of lock replacement or re-keying from the monthly payment due the contractor. In the event a master key is lost or duplicated, the Government will replace all locks and keys for that system and will deduct the total cost from the monthly payment due the contractor.
1.4.6.1.3 The contactor shall prohibit the use of the Government issued keys/key cards by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contactor employees engaged in the performance of services in those areas, or personnel authorized entrance by the KO.
1.4.6.2 Lock Combinations: (RESERVED)
1.4.7 Special Qualifications: The contractor shall ensure all employees possess all required licenses for operating heavy equipment used in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.)
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.
1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero-tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.4.12 Contractor Travel: (RESERVED)
1.4.13 Data Rights: (RESERVED)
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications, or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Phase In / Phase Out Periods: (RESERVED)
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
| AEI | Army Enterprise Infostructure | |
| AR | Army Regulation | |
| AT/OPSEC | Antiterrorism/Operational Security | |
| BI | Background Investigation | |
| CM | Contract Manager | |
| COR | Contracting Officer Representative | |
| DA | Department of the Army | |
| DD254 | Department of Defense Contract Security Classification Specification | |
| DFARS | Defense Federal Acquisition Regulation Supplement | |
| DoD | Department of Defense | |
| DSCA | Defense Counterintelligence and Security Agency | |
| FAR | Federal Acquisition Regulation | |
| GFP/M/E/S | Government Furnished Property/Material/Equipment/Services | |
| HQDA | Headquarters, Department of the Army | |
| HSPD | Homeland Security Presidential Directive | |
| IA | Information Assurance | |
| IS | Information System(s) | |
| KO | Contracting Officer | |
| NGB | National Guard Bureau | |
| OCI | Organizational Conflict of Interest | |
| PII | Personally Identifiable Information | |
| PIPO | Phase In/Phase Out | |
| POC | Point of Contact | |
| PRS | Performance Requirements Summary | |
| PWS | Performance Work Statement | |
| QA | Quality Assurance | |
| QASP | Quality Assurance Surveillance Plan | |
| QC | Quality Control | |
| QCP | Quality Control Program | |
| SCR | Service Contract Reporting | |
| SSN | Social Security Number | |
| TE | Technical Exhibit | |
| USD(I) | Under Secretary of Defense for Intelligence | |
| YLTA | Youngstown Local Training Area |
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract: NONE
3.1 Property: NONE
3.2 Materials: NONE
3.3 Equipment: NONE
3.4 Services: NONE
3.5 Utilities: NONE
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
4.2 Secret Facility Clearance: N/A
4.3 Contractor Security Clearance: N/A
5.0 Contractor Performance Requirements: The contractor shall:
5.1 CLIN 0001 Demolish all structures defined in the “Demolish Building and Fence” ppt. attachment
5.1.1 Demolish building, reinforced concrete pad and stairs at 1 location listed in the PWS attachment.
5.1.2 The 75 foot radius shall be cleaned up of the surrounding area from the center-point of the item called out to be demolished. All visible items shall be identified, demolished and removed from site. Examples include lose and embedded metal, elevated concrete, abandoned equipment, poles and electrical/mechanical systems in and around the specified demo sites.
5.1.3 Demolish 2 additional elevated concrete structures as part of the base RFQ.
5.2 CLIN 0002 Demolish fencing option, quote for demolishing approximately 3 miles of chain-link fence/ 15,840 linear feet. Provide unit price/s in linear feet for demolish chain-link fence (internal to site, not perimeter) and turnover chain-link fence rolls that are in “good condition” to the facility. See ppt slides attached to solicitation, labeled, YLTA Demo PPT (FED 2023) 06.08.2023 FINAL, pgs 5 and 6.
5.3 Service Contract Reporting: NA
5.4 A site visit is scheduled for 1AUG2023 10:00 a.m. You must email Meghan.a.sheridan.civ@army.mil and Melissa.santoro2.civ@army.mil with any attendee’s -their name, company name, date of birth, issuing state of your license and license number by 10:00 a.m. on 31JUL2023 for admittance.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
| Date of Publication |
| Mandatory or Advisory |
| Website |
| Federal Acquisition Regulation |
| 12/30/2022 |
| Mandatory |
| https://www.acquisition.gov/?q=browsefar |
| Defense Federal Acquisition Regulation Supplement |
| 12/30/2022 |
| Mandatory |
| http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html or https://www.acquisition.gov/dfars |
| DoDM 5200.2 Procedures for the DoD Personnel Security Program (PSP) |
| 04/03/2017 |
| Advisory |
| https://www.esd.whs.mil/Directives/issuances/dodm/ |
DoDI 5400.11 Department of Defense Privacy and Civil Liberties Programs 01/29/2019
| Advisory |
| https://www.esd.whs.mil/Directives/issuances/dodi/ |
DoD 5400.11-R Department of Defense Privacy Program
| 05/14/2007 |
| Advisory |
| https://www.esd.whs.mil/Directives/issuances/dodm/ |
AR 25-2
Information Assurance 04/04/2019
| Advisory |
| http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx |
AR 530-1
Operations Security
| 09/26/2014 |
| Advisory |
| http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx |
AR 525-13
Antiterrorism
| 12/09/2019 |
| Advisory |
| http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx |
AR 381-12
Threat Awareness and Reporting Program (TARP) (Section II, ¶ 2-4.b)
| 06/01/2016 |
| Advisory |
| http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx |
6.1 Applicable Forms: Forms applicable to the PWS are listed below:
| Form |
| Date |
| Website |
I-9 Employment Eligibility Verification 10/21/2019 https://www.uscis.gov/sites/default/files/files/form/i-9.pdf
DD 250
Material Inspection and Receiving Report
| Aug 2000 |
| https://www.esd.whs.mil/Directives/forms/dd0001_0499/ |
TECHNICAL EXHIBIT 1
Performance Requirements Summary (PRS)
This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
| Performance Objective |
| Performance Standard |
| Acceptable Quality Levels (AQL) |
| Surveillance Method / By Whom |
5.1.1 Demolish building, pad and stairs
| All visible items shall be identified, demolished and removed from site. Examples include lose and embedded metal, elevated concrete, abandoned equipment, poles and electrical/mechanical systems in and around the specified demo sites. |
| Meets the standard 90% of the time. Alternate AQL: Demolition and cleaning does not meet performance standards |
| Random monitoring and inspection / COR |
5.1.2 Cleanup of the surrounding area
| . All visible items within 75 ft of center-point shall be identified, demolished and removed from site |
| Meets the standard 90% of the time. Alternate AQL: Demolition does not meet performance standards |
| Random monitoring and inspection / COR |
5.1.3 Demolish two elevated concrete structures
| Demolish elevated concrete and foundation walls (including rebar) to 8” below finished grade. Infill with dirt. |
| Meets the standard 90% of the time. Alternate AQL: Demolition does not meet performance standards |
| Random monitoring and inspection / COR |
5.2 Demolish fence (OPTION)
| The contractor shall demolish approximately 3 miles of chain-link fence. Chain-link fence rolls in good condition to be turned over to the facility. |
| Meets the standard 90% of the time. Alternate AQL: Demolition does not meet performance standards |
| Random inspection / COR |
TECHNICAL EXHIBIT 2
Deliverables Schedule
| PWS Reference / Deliverable Title |
| Frequency |
| Number of Copies |
| Medium/Format |
| Submit To |
1.4.3 Quality Control Plan
| A final QCP shall be submitted NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP. |
| 1 |
| Electronic Submission |
| COR |
1.4.7 Special Qualifications
| The contractor shall submit a copy of all required licenses for operating heavy equipment used in the performance of this contract NLT 10 day after award. |
| 1 |
| Electronic Submission |
| COR |
| 1.4.9 Contract Manager (CM) |
| The contactor shall designate a CM and alternate who shall ensure performance under this contract. The name of this person and alternate shall act for the contractor and shall be designated in writing to the KO NLT 10 days after award. |
| 1 |
| Electronic Submission |
| COR/KO |
1.4.10.1 Contractor Identification
| The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the COR/KO within 14 days of an employee’s departure |
| 1 |
| Electronic Submission |
| COR/KO |
| 5.2 CLIN 0002 Demolish fencing option |
| The contractor shall submit, upon submittal of quote for base CLIN 0001, a quote for CLIN 0002 demolishing approximately 3 miles of chain-link fence/ 15,840 linear feet Provide unit price/s in linear feet for demolish chain-link fence (internal to site, not perimeter) and turnover chain-link fence rolls that are in “good condition” to the facility |
| 1 |
| Electronic Submission |
| KO |
TECHNICAL EXHIBIT 3
Estimated Workload Data
(RESERVED)
Ver. October 2022