PWS_Domestic Water Systems Upgrade_W91QF525RA019.pdf
PDF 327 KB Posted
- Attached to
- ALTESS Domestic Water System Upgrade
- Solicitation number
- W91QF5-25-R-A019
About this file
This Performance Work Statement (PWS) details a domestic water system upgrade for the U.S. Army Acquisition, Logistics and Technology Enterprise Systems & Services (ALTESS) Project Office at the Radford Army Ammunition Plant in Virginia. The non-personal services contract requires the contractor to remove and replace aging infrastructure in two mechanical rooms (Rooms 119 and 241), including demolishing and replacing existing water lines, valves, regulators, check valves, and associated piping. Specific tasks include draining water systems, removing approximately 60-80 feet of four-inch waterline, replacing hot water heaters and utility sinks, installing new copper piping with appropriately sized valves, and ensuring complete system pressurization and leak testing.
The contract period of performance is from September 1, 2025, to March 1, 2026, with work to be conducted at the ALTESS Enduring Data Center. The upgrade is critically needed to prevent potential water system shutdowns that could impact cooling and heating for the facility's building and server rooms. Contractors must adhere to all state, federal, and environmental safety regulations, provide all necessary personnel and equipment, and maintain zero environmental mishaps or damage to associated equipment and facilities. Deliverables include pre/post service reports and warranty documentation, to be submitted to specific ALTESS personnel via hardcopy or email.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AUG 22
Performance Work Statement (Includes associated Performance Requirements Summary (PRS)
FOR
Domestic Water System Upgrades
AT THE
U.S. Army Acquisition, Logistics and Technology Enterprise Systems & Services
(ALTESS) Project Office Radford Army Ammunition Plant, Radford, VA
Part 1 General Information
1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.
1.1 Description of Services/Introduction: This non-personal services contract outlines the obligation to adhere to all state, federal, and environmental safety regulations while providing all personnel, equipment, supplies, facilities, transportation, specialized tools, materials, supervision, and other items for the Domestic Water System Upgrade. This service shall entail the removal of all aging and obsolete valves, ball valves, and associated piping, as well as all regulators, check valves, and relief valves associated with the upgrade. Provide and install all new valves (with ball valves) with piping to be copper, all regulators, check valves, and relief valves that all should be sized appropriately. These repairs and replacements are urgently required to prevent potential water shutdowns that could directly impact the cooling and heating of the building and server rooms situated inside the ALTESS data center located within the Radford Army Ammunition Plant, Radford, VA 24141.
The Government shall not exercise any supervision or control over the contract service providers performing the services herein. These contract service providers shall be accountable solely to the Contractor, who, in turn, is responsible to the Government.
1.2 Background: During the late 1940s, the Army completed construction of a covered and protected underground facility that would be stood up as an Army classified facility to support undisclosed work that would span numerous foreign conflicts and beyond.
As the Army’s mission and footprint evolved over time, the facility’s technological, environmental, and support requirements expanded to encompass advancements in data storage and processing, back up equipment and support equipment, and growing personnel. In 1959, the Army relocated ALTESS to the Radford Army Ammunition Plant due to its secure location and the presence of a fully functional, covered, and protected facility.
Since the construction of the building, the water lines, valves, and plumbing system have been maintenance and repaired, replaced as necessary throughout the years. However, over the past five to seven years, ALTESS has experienced an influx of personnel, mission workload increases, and usage that has placed a heavier burden on the water lines, valves, and plumbing system, resulting in increased decay.
To prevent a potentially hazardous shutdown of water systems that could directly impact on the Army mission, ALTESS is requesting upgrades to the current infrastructure of the domestic water system. These upgrades aim to bring the water system up to date, improve efficiency, and ensure its ability to handle the increased demand while also extending the lifespan of newer lines and valves.
1.3 Scope: The contractor shall furnish all labor, tools, materials, equipment, and supervision necessary to complete work associated with providing Domestic Water System Upgrade. This service shall include removal of all aging and obsolete valves, ball valves, and associated piping, all regulators, check valves, relief valves, and associated piping. Provide and install all new valves (with ball valves) with all piping to be copper, all regulators, check valves, and relief valves that shall be sized appropriately. Services will be located within the ALTESS data center on the Radford Army Ammunition Plant, Radford, VA 24141
1.4 Objectives: The objective of this service is to provide Domestic Water System Upgrade.
This service shall include removal of all aging and obsolete valves, ball valves, and associated piping, all regulators, check valves, and relief valves associated with the upgrade. Provide and install all new valves (with ball valves) with all piping to be copper, all regulators, check valves, and relief valves that shall be sized appropriately. rooms located with the ALTESS data center on the Radford Army Ammunition Plant, Radford, VA 24141
1.5 General Information:
1.5.1 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.2 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If the submittal of any documentation (e.g., deliverables, submittals, etc.) deadlines fall on a holiday, the closest workday prior to the holiday will apply as the deadline for submittal.
1.5.2.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.
When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents’ Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
1.5.3 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.3.1 Government Facility Office Hours: The Government facility office hours are 7:00am
– 4:00pm, Monday through Friday except U.S. Holidays identified in paragraph 1.5.2.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.3.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 7:00am – 4:00pm, Monday through Friday. The Government facility is open except for Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, weather, or similar Government directed facility closings
1.5.3.3 Contractor Support Hours: The Contractor shall provide support between the hours of 7:00 AM and 4:00 PM, Monday through Friday, excluding Federal holidays and when the Government facility is closed due to local or national emergencies, administrative closings, weather, or similar Government-directed facility closures. Work expected to be performed outside of these hours must be approved by the Government at least one week in advance.
For contracts other than firm fixed price contracts, the Contractor will not be reimbursed when the Government facility is closed for the aforementioned reasons. The Contractor shall maintain an adequate workforce at all times to ensure the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall prioritize the stability and continuity of the workforce.
1.5.4 Place of Performance: The work to be performed under this contract will be performed at the Radford Army Ammunition Plant (RFAAP), ALTESS building 450 and associated areas within the ALTESS data center located onsite in Radford, VA 24143.
1.5.5 Period of Performance: The Period of Performance (POP) for Domestic Water System Upgrade shall be from 9/1/2025 – 3/1/2026.
1.6 Security Requirements: The following information is provided on security related matters.
1.6.1 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized. Failure to submit required information/data and obtain required documentation or clearances will be grounds for denying access to U.S. installations, buildings, and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.
The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control System (IACS) processing requirements.
The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a Contractor employee no longer requires access.
1.6.2 Background Checks: Contractor(s) and service personnel visiting or accessing the Radford Army Ammunition Plant (RFAAP) must have US citizenship and provide one form of photo ID that includes a valid real ID for entrance onto RFAAP. All personnel shall be escorted at all times.
All contractors and service personnel providing a recurring service to the RFAAP installation are required to obtain a RFAAP badge. In order to obtain a RFAAP badge the contractor shall submit and obtain a favorable nationwide formal background investigation for the personnel.
This background investigation must be conducted by a state agency or licensed background firm and not a computer search. Contractor personnel cannot have any adjudication actions (parole, probation, or open case files) within the past 5 years, or they will not be able to obtain a RFAAP badge and access to the installation shall be denied. The investigation shall be submitted to RFAAP security personnel though the contracting official. The RFAAP Security Office shall then, upon validation of the favorable investigation, provide the RFAAP badge.
The personnel receiving a RFAAP badge shall be required to carry the badge with them at all times while on the installation and secure the badge out of sight when not on the installation.
Cell phones, cameras, PDA, and electronic devices are not allowed on the installation without prior approval.
Contractors not requiring a RFAAP badge must obtain a visitor’s badge at the Visitor Station located at the entrance to the RFAAP facility. This badge must be worn at all times and be plainly visible.
Contractor personnel performing work under this contract must possess and abide by the security requirements at the time of proposal submission, and must maintain the level of security required for the life of the contract
1.6.2.1 U.S. Citizen: Contractors that work with or teach youth under the age of 18 years are subject to U.S background checks. The Requiring Activity Manager will determine the extent of background checks required. The Contractor employee may begin performance of the contract after receiving a favorable local background check. The Contractor agrees to replace the employee should results of the background check, if required, be unfavorable as determined by the Requiring Activity Manager. The Contractor’s replacement of the employee with the unfavorable background check shall be within a timeframe provided by the Requiring Activity Manager. The Contractor shall also replace employees whose background check, during their tenure of employment, renders them with an unfavorable local or stateside background check, as determined by the Requiring Activity Manager. The Contractor shall forward a copy to the Contracting Officer via the COR and the Requiring Activity Manager of each favorable background check within 7 business days prior to service of receipt by the Contractor, identifying such with the appropriate contract number (#). The Contractor shall forward a copy to the Contracting Officer via the COR and the Requiring Activity Manager of each unfavorable background check within 7 business days of receipt by the Contractor, identifying such with the appropriate contract number (#}). When the Government awards a non-personal services contract directly to an individual, the failure of the individual to provide a favorable background check would be grounds for termination.
1.6.6 Physical Security: The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured IAW the Army Physical Security Program AR 190-13.
1.6.7 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.
1.7 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will advise the Contractor of how the Government views the Contractor's performance and the Contractor shall advise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.7.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter.
Meetings may start or end outside of regular duty hours.
1.8 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.9 Key Personnel: The following personnel are considered key personnel by the Government:
Key Personnel (Government):
James “Jay” Bowers Facility Operations Specialist US Army Acquisition Logistics Technology Enterprise Systems and Services (ALTESS) Office: 520-267-5509 Email: james.d.bower11.civ@army.mil
Tim Hancock Team Lead, Facility Management US Army Acquisition Logistics Technology Enterprise Systems and Services (ALTESS) Office: 520-706-0273 Email: timothy.w.hancock@army.mil
Contracting Office Representative (COR) Alison J. McCraw Acquisitions Management Specialist US Army Acquisition Logistics Technology Enterprise Systems and Services (ALTESS) Office: 520-706-0045 Email: alison.j.mccraw@army.mil
1.10 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.10.1 Contractor Identification Badges: Contractor personnel shall be easily identifiable through the display of badges IAW Contractor Identification (AE Reg. 27-715). The Contractor (to include subcontractors) shall provide each of their employees with an easily readable identification badge. The badge must include the employee’s name, the contractor’s company name, the functional area of assignment, and a recent color photograph of the employee.
Companies with U.S. Government contracts will require their employees to wear these badges visibly when performing work at Government workplaces unless this would be impractical because of mission or safety considerations. The Contractor shall collect all ID Badges upon completion of the contract or termination of employee. A listing of issued ID cards shall be furnished to the Contracting Officer prior to the contract performance date and updated as needed to reflect Contractor personnel changes.
mailto:james.d.bower11.civ@army.mil mailto:timothy.w.hancock@army.mil mailto:alison.j.mccraw@army.mil
1.11 Contractor Travel: There is no specific Government-directed travel as part of this PWS.
1.12 Data Rights: The Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.13 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/ , the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.
1.14 Organizational Conflict of Interest (OCI): Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCI as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s OCI Mitigation Plan will be determined to be acceptable solely at the discretion of the Contracting Officer. In the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.15 Environmental Compliance: The following provides information on Environmental Compliance.
1.15.1 Environmental Compliance Plan and Program: The Contractor shall ensure that all of its operations and activities conform to the ALTESS and Radford Army Arsenal environmental policy requirements. The Contractor shall ensure that all contract personnel have received appropriate levels of training in the handling, use, storage, and disposal of hazardous material. In addition, the Contractor shall ensure that all Contractor controlled activities on the Radford Arsenal installation are conducted in accordance with the Radford Army Arsenal and ALTESS Spill Prevention and Response Plan, Solid Waste Policy.
“If contract requires the use of hazardous materials/substances, the Contractor shall, prior to mobilization, inform the ALTESS facility management team of the amounts and types of hazardous materials needed to be brought onto the Garrison in order to fulfill their contractual http://www.dimoc.mil/resources/limitations/ requirements. Contractors shall also provide Material Safety Data Sheets, storage requirements and proposed storage locations for the hazardous material.
“The Contractor shall clean up at its own expense any contamination, including soil and ground water contamination caused by hazardous materials/substances brought onto the garrison, or by his activities. The Contractor must immediately report any hazardous substance spills to the ALTESS facility management team.
1.16 Government Property and Services: The Government will make available the restroom facilities in Building 220 and/or Building 450 for the contractor’s use in performance of tasks outlined in the PWS. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.
Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line-item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”
Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.
Day – means, unless otherwise specified, a calendar day.
Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.
Deliverable – means anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is deliverable under a cost contract when accepted by the Government for continued use under the contract
Government Property - means all property owned or leased by the Government. Government property includes both Government-furnished and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.
Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.
High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.
Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.
Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. With very few if any exceptions, the QASP is an internal to Government document.
Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however, they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.
Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
Work Day - The number of hours per day the Contractor provides services in accordance with the contract.
Work Week - Monday through Friday, unless otherwise specified.
2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis ALTESS Acquisitions Logistics & Technology Enterprise Systems & Services ANSI American National Standards Institute AOR Area of Responsibility AR Army Regulation ASTM American Society For Testing and Materials AT Anti-terrorism ATCTS Army Training Certification Tracking System CAC Common Access Card CCA Cold Crank Amps CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii)
COR Contracting Officer’s Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DEAC Diesel Engine Antifreeze Coolant DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DoD Department of Defense EDC Enduring Data Center ELC Extended Life Coolant ESC Extended Service Coverage FAR Federal Acquisition Regulation GFP Government Furnished Property HLO High Level Objective HIPAA Health Insurance Portability and Accountability Act of 1996 IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification IT Information Technology JVS Joint Verification System KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs OPSEC Operations Security PA Property Administrator PII Personally Identifiable Information POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program RA Requiring Activity RFAAP Radford Army Ammunition Plant RCO Regional Contracting Office SIGE Safety and Health Protection Plan TE Technical Exhibit USAG United States Army Garrison UOM Unit of Measure
PART 3
GOVERNMENT PROPERTY (GP) AND SERVICES
3. Government Property and Services
3.1 Facilities: The Government will make available the restroom facilities in Building 220 and/or Building 450 for the contractor’s use in performance of tasks outlined in the PWS. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.
3.2 Utilities: The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves, light switches, etc. after using the required amount to accomplish tasks requiring the use of the utilities.
PART 4
SPECIFIC TASKS
4.1 Basic Services: The Contractor shall provide transportation or equipment, and services required to perform work under this contract in accordance with this PWS, Domestic Water System Upgrade. This service shall include removal of all aging and obsolete valves, ball valves, and associated piping, all regulators, check valves, and relief valves associated with the upgrade. Provide and install all new valves (with ball valves) with all piping to be copper, all regulators, check valves, and relief valves that shall be sized appropriately. rooms located within the directly supporting the ALTESS Enduring Data Center (EDC) located on site in Radford, VA 24141-1061:
4.1.1 Domestic Water System Upgrade: The Domestic Water System Upgrade. This service shall include removal of all aging and obsolete valves, ball valves, and associated piping, all regulators, check valves, and relief valves associated with the upgrade. Provide and install all new valves (with ball valves) with all piping to be copper, all regulators, check valves, and relief valves that shall be sized appropriately. The Domestic Water System Upgrade will be performed in two separate mechanical rooms. The upgrade shall include:
Room 119 Upgrade:
• Draining all water piping, remove and replace all steel portions of incoming domestic water line(s), including two main shut off gate valves, check valve(s), regulator, and pressure gauge. Steel section is approximately six (6’) foot in length and should have unions and valves at both ends to ensure components can be isolated and repaired.
• Removal and replacement of Gate Valve “A” and the associated steel union and nipple at the same location.
o Advise if above replacement could be relocated to a better point of access (contact government POC for direction)
• Add ball valve to one and a half (1-1/2”) inch piping branch that accesses hot water system.
• Remove and replace all gate valves and check valves in hot water system configuration.
o There is approximately twelve (12) gate valves and two (2) check valves May require reconfiguration for some of the system piping and/or complete removal of valves and branches that are considered no longer in use.
o Replacement of vacuum breaker of pressure relief located on to of system.
• Removal of eye wash station and all associated piping and valves prior to valve replacement/reconfiguration.
• Remove and replace two (2) eighty (80) gallon hot water heaters.
o Remove and replace steel connectors
• Remove and replace utility sink and faucet.
o Install new hot water supply to new utility sink from hot water heaters. Supply shall have valves at both ends.
o Installation of valves at both ends of cold-water supply to include adding hose bib on wall beside of sink.
• Remove water line to hose bib behind chillers to include:
o At the takeoff from the main line, install a new valve, close valve, and plug.
• Install valve to make up water line.
• Pressurize entire water system and check for leaks at all connection points.
o Repair areas as necessary
• Reinsulate all piping and valves.
Room 241 Upgrade:
• Draining of all water from piping and demo approximately sixty (60’) to eighty (80’) feet of existing four (4”) inch waterline. Additional items to be removed shall include all:
o Associated valves, regulators, back flow circuits, to include branch supply take offs of all sizes (including unused components like eye was stations, hose bibs and well tank), and any other associated components.
• Demo and remove two (2”) inch main supply branch to restrooms and cooling.
o Remove line back to a point to which the new supply can be tied back in.
• Install three-fourth (3/4”) inch branch off of new two (2”) inch line to new location for hot water makeup.
o Include valve at two (2”) inch line then regulator and check valve at connection point with union for ease of servicing.
• Install new flange on four (4”) inch water line entering facility.
o Install new two (2”) valve on flange to include installation of new strainer/check valve, new regulator, new drain point, new gauge, and valve take off for monitoring transducer.
This section of components shall have unions and valves at both ends to ensure components can be isolated and repaired.
• Install new two (2”) inch main water supply through new path to avoid crossing over primary electrical distribution. This installation shall also include:
o New supply shall extend from the supply valve at the four (4”) inch line all the way to the point where it can be tied back into the existing two (2”) inch supply for restrooms and cooling tower.
o Installing of valve at piping join points o Installation of multiple take offs and valves installed on the two
(2”) inch main that include one for the hot water make up, a new supply to the humidifier, and a stub out for future usage.
All points to have valves at both ends.
• Pressurize entire water system and check for leaks at all connections points o Repair as necessary
• Reinsulate all piping and valves
• Removal and disposal of all demolished parts and supplies to include cleaning up of areas impacted by upgrade service.
o Include removal and disposal (off site) of epoxies, glues, sealants or any considerable hazardous materials used for plumbing.
8. Service Contract Reporting
8.1 System for Award Management (SAM) Service Contract Report (SCR): The Contractor shall report ALL Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the {Insert Component’s Name} via a secure data collection site. The Contractor is required to completely fill in all required data fields through the following web address: www.sam.gov. Reporting inputs will be for the labor executed during the period of performance during each Government FY, which runs from October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk by clicking “View Assistance for SAM.gov” which is located at the top of the SAM.gov website. From there, you can the select “Contact Our Service Desk” which will allow you to contact SAM.gov directly. If contract period of performance ends prior to September 30, the Contractor has 30 calendar days from end date of the contract to complete the SAM SCR requirement.
http://www.sam.gov/
Steps for Submitting a Service Contract Report (SCR)
1. Go to www.sam.gov and log in.
2. Select Entity Registrations and then select Service Contract Reporting.
3. SAM displays your entities which have service contracts and meet the reporting criteria.
Select View by entity to see the service contracts for each entity.
4. Next, select Add for the service contract against which you want to create a Service
Contract Report. Each service contract which meets the FAR Subpart 4.1703 reporting thresholds is displayed.
5. You will be taken to the Complete Service Contract Report page. SAM displays the contract details and allows you to report. You are required to enter the following information:
• Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous Government fiscal year under the contract (this amount should include the prime and any subcontract amount).
• Prime Contractor Hours Expended: Prime contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 hours to calculate a Full Time Employee (FTE) equivalent, displayed under the Prime Contractor Hours Expended as Prime Contractor FTEs.
6. Report any required Tier 1 subcontractor information by selecting the Add Tier 1 Subcontract Information button.
7. When you are ready to submit the report, select Submit. This saves your report and returns you to the Select Service Contract page where you can create other SCRs or edit an existing SCR.
Steps for Editing a Submitted Report
1. Follow steps 1-4 above. Any previously submitted SCR will have a View/Edit button instead of an Add button.
2. Select View/Edit. You will be able to view the current SCR, edit available fields, and resubmit the record. You can also delete previously entered information altogether.
STD: All information provided by the Contractor shall be accurate, complete, and not exceed suspense dates noted in corresponding paragraph above.
AQL: 100% Compliant
PART 9
APPLICABLE PUBLICATIONS
9. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.
9.1.1 National Industrial Security Program Operating Manual (NISPOM), 85 C.F.R. 83312 (2021)
9.1.2 Installation Access Control, Army Regulation (AR190-16) (1991)
9.1.3 The Army Physical Security Program, Army Regulation (AR 190-13) (2019) http://www.sam.gov/
9.1.4 Physical Security Program: Access to Department of Defense Installations, DoD Manual 5200.08, volume 3. (2020)
9.1.5 U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1) (2014)
9.1.6 Property Accountability Policies, Army Regulation (AR 735-5), (2013)
9.1.7 Inspection, Monitoring, Testing, and Corrective Action, 42 United States Code § 6991d
(c) (2005)
9.1.8 Federal Facilities, 42 United States Code § 6991f (2005)
9.1.9 Information Technology Contingency Plan, Department of Army Pamphlet DA PAM 25- 1-2 (p.10) (2020)
9.1.10 Telecommunication Infrastructure Standard for Data Centers, American National Standards Institute, Telecommunication Industry Association, ANSI/TIA 942 (2020)
9.1.11 Protection of Environment, Standards for Universal Waste Management, Applicably Batteries. 40 C.F.R. §273.2(b)(1999)
9.1.12 Department of Defense Configuration Management, EGSA 107G, (1984).
9.1.13 Institute of Electrical and Electronic Engineers (IEEE) Standard 446, Orange Book - Recommended Practice for Emergency and Standby Power for Industrial and Commercial Applications (1995)
9.1.14 Life Safety Code, National Fire Protection Agency (NFPA 101) (2024).
TECHNICAL EXHIBIT A
Performance Requirements Summary (PRS)
Service Required Standard of Performance
Acceptable Quality Level
(AQL)
Surveillance Method
Incentive / Disincentive
PRS#1
The contractor shall provide Domestic Water System Upgrades to mechanical rooms as outlined within PWS.
PWS.
Para 1 Para 1.1 Para 1.3 Para 1.4 Para 1.5.3.3 Para 4.1.1
Contractors shall provide removal of all old valves (with ball valves) to include associated piping.
regulators, check valves, and relief valves. Provide and install all new valves (with ball valves) with all piping to be copper with inclusion of all regulators, check valves, and relief valves shall be sized appropriately for the system
Zero environmental mishaps, damage to associated equipment and facilities, or security incidents in performance of this service.
ALTESS, Facility manager and/or
COR
representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance 100% inspection upon completion of PMs and ERS services, random sample inspection and periodic inspections.
None
PRS#2
The contractor shall repressurize, check for leaks, repair areas as necessary as outlined within PWS.
PWS.
Para 1 Para 1.1 Para 1.3 Para 1.4 Para 1.5.3.3 Para 4.1.1
Perform repressurizing of water supply lines to include but not limited to monitoring for leaks and repair areas as needed.
Zero environmental mishaps, damage to associated equipment and facilities, or security incidents in performance of this service.
ALTESS, Facility manager and/or
COR
representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance 100% inspection upon completion of PMs and ERS services, random sample
PRS#3
The contractor shall remove demolished parts and associated supplies to include cleaning up of work areas prior to exiting work areas as outlined within PWS.
PWS.
Para 1 Para 1.1 Para 1.3 Para 1.4 Para 1.5.3.3 Para 4.1.1
Removal and disposal of all demolished parts and supplies to include cleaning up of areas impacted by upgrade service or as directed by the SOW and government representative.
Zero environmental mishaps, damage to associated equipment and facilities, or security incidents in performance of this service.
ALTESS, Facility manager and/or
COR
representatives through Governmental Surveillance Documentation, customer complaint systems or visual performance 100% inspection upon completion of PMs and ERS services, random sample
8. DELIVERABLES
8. The items listed Table 8, Deliverables Summary, are deliverable to the Government in accordance with this PWS.
Table 8: Deliverables Summary
Deliverable Frequency Number of Items/Copies
Format
Submit To
Pre/Post Service Reports
Once/ Per Services/As requested
One (1) copy/ Per Services/As requested
Hardcopy or via email
James “Jay” Bowers james.d.bower11.civ@army.mil Facility Operations Specialist, ALTESS
Tim Hancock, timothy.w.hancock@army.mil Team Lead, Facility Management, ALTESS
Alison McCraw Alison.j.mccraw.civ@army.mil Acquisitions Management Specialist, ALTESS
Warranty Documents/Reports for Parts (if available)
Once/ Per Services/As requested
One (1) copy/ Per Services/As requested
Hardcopy or via email
James “Jay” Bowers james.d.bower11.civ@army.mil Facility Operations Specialist, ALTESS
Tim Hancock, timothy.w.hancock@army.mil Team Lead, Facility Management, ALTESS
Alison McCraw Alison.j.mccraw.civ@army.mil Acquisitions Management Specialist, ALTESS mailto:james.d.bower11.civ@army.mil mailto:timothy.w.hancock@army.mil mailto:Alison.j.mccraw.civ@army.mil mailto:james.d.bower11.civ@army.mil mailto:timothy.w.hancock@army.mil mailto:Alison.j.mccraw.civ@army.mil
| U.S. Army Acquisition, Logistics and Technology Enterprise Systems & Services (ALTESS) Project Office |
| Radford Army Ammunition Plant, Radford, VA |