PWS dated 21 July 2026_Redacted.pdf
PDF 70 KB Posted
- Attached to
- ELECTRICAL WORK
- Solicitation number
- FA2823-26-Q-A111
About this file
This is a Performance Work Statement (PWS) dated 21 July 2026 for an Electrical System Upgrade and Exterior Lighting Replacement project at Eglin Air Force Base, Florida.
The contractor shall perform four primary tasks: (1) Main Electrical Panel Replacement—demolish and remove the existing panel, install a new panel with new circuit breakers, and seal wall penetrations for watertight integrity; (2) Exterior Receptacle Replacement—replace twelve existing exterior wall receptacles with new 20-amp rated devices, connect them to a new GFCI breaker, remove extension boxes, and install new receptacles with in-use covers; (3) Sub-Panel Breaker Refresh—install fifteen new circuit breakers in the existing load center sub-panel; and (4) Exterior Lighting Replacement—remove six existing exterior safety wall lights with mounting plates and install six new LED wall pack lights with sealed, watertight mounting. All work must comply with applicable national, state, and local codes and regulations, use new materials meeting or exceeding industry standards, and include all necessary permits and inspections. The contractor is responsible for maintaining a clean work area throughout the project.
Deliverables include a project schedule coordinated with building test events, weekly progress reports submitted every Friday, a final inspection report upon project completion, and as-built drawings due within ten days of completion. The government will provide access to the work site and electrical rooms. The period of performance will be coordinated around scheduled building and site test events. No specific contract vehicle, set-aside, response date, or pricing information is provided in this document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS dated 13 Aug 2026_Redacted.pdf | ||
| Electrical Work Questions and Answers.pdf | ||
| Combo_Redacted.pdf | ||
| Clauses.pdf | ||
| SIite Visit and Due Dates.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Title:
1.0 Background
The existing electrical system has several components that are outdated, unsafe, or not up to current code standards. The exterior lighting is inefficient and requires frequent maintenance.
This project is to repair the electrical system and replace the exterior lighting to improve safety, reliability, and energy efficiency.
2.0 Scope of Work
The contractor shall provide all labor, materials, and equipment necessary to perform the following tasks:
2.1 Main Electrical Panel Replacement
Demolish and remove the existing main electrical panel.
Install a new main electrical panel with all new circuit breakers.
Seal all wall penetrations to ensure a watertight seal around conduits.
2.2 Exterior Receptacle Replacement
Replace twelve (12) existing exterior wall receptacles with new 20-amp rated devices.
Connect the new receptacles to a new Ground Fault Circuit Interrupter (GFCI) breaker in the main panel.
Remove any existing extension boxes on the exterior receptacles.
Install new receptacles and in-use (bubble) covers for all exterior receptacles.
2.3 Sub-Panel Breaker Refresh
Install fifteen (15) new circuit breakers in the existing load center sub-panel to refresh the panel's integrity.
2.4 Exterior Lighting Replacement
Remove and dispose of six (6) existing exterior safety wall lights and their associated wood mounting plates.
Install six (6) new LED wall pack lights.
Mount and seal the new light fixtures to the building to ensure a watertight installation.
3.0 Performance Requirements
All work shall be performed in a professional manner and in accordance with all applicable national, state, and local codes and regulations.
All materials and equipment shall be new and of a quality that meets or exceeds industry standards.
The contractor shall be responsible for all necessary permits and inspections.
The work area shall be kept clean and free of debris at all times.
4.0 Deliverables
Deliverable Due Date
Project Schedule To be worked out between test events scheduled for the building and site.
Weekly Progress Reports Every Friday
Final Inspection Report Upon project completion
As-Built Drawings Within 10 days of project completion
5.0 Government-Furnished Equipment and Information (GFE/GFI)
The government will provide access to the work site and electrical rooms.
6.0 Place of Performance
The work will be performed at Eglin AFB, FL
7.0 Period of Performance
The period of performance for this contract is to be worked out between test events that are scheduled for the building and site.