PW1663-25 Nusome Rd Pudding River Approach - Preliminary Results.xls
XLS spreadsheet 37 KB Posted
- Solicitation number
- S-62900-00013094
- Issued by
- Jackson County, Oregon
About this file
This is a bid abstract document for the Oregon Department of Transportation (ODOT) project PW1663-25 Nusome Road Pudding River Bridge Approach, detailing preliminary bidding results for construction work on a bridge approach improvement project. The project encompasses bridge removal, structure excavation, backfill operations, concrete repair, reinforced concrete bridge end panel installation, asphalt concrete pavement placement, guardrail installation, and native plant seeding. Specific quantities include 87 square yards of reinforced concrete bridge end panels, 225 tons of commercial asphalt concrete pavement, 360 tons of aggregate base, 50 feet of guard rail Type 2A, and 0.1 acres of native plant seeding, along with various temporary protection, erosion control, and survey work items. Five contractors submitted bids: HP Civil Inc., Farline Bridge, Roy Houck Construction LLC, Legacy Contracting Inc., and Oregon State Bridge Construction Inc.
The bid totals range from approximately $264,085.55 (HP Civil Inc., lowest bid) to $425,195.00 (Oregon State Bridge Construction Inc., highest bid), with intermediate bids of $277,039.97 (Farline Bridge), $295,100.00 (Roy Houck Construction LLC), and $348,530.50 (Legacy Contracting Inc.). Pricing is structured as unit prices and lump-sum items across all line items, with significant variation among bidders on major cost components such as bridge removal work, temporary protection and traffic direction, and concrete repairs. No information regarding set-asides, incumbent contractors, funding sources, or contract term renewal options is provided in this preliminary results document.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Abstract_2025_04_25 (1)
| Bid Abstract - PW1663-25 ITB - Nusom Rd: Pudding River Bridge Approach | ||||||||||||||
| HP CIVIL INC | FARLINE BRIDGE | ROY HOUCK CONSTRUCTION LLC | LEGACY CONTRACTING INC | OREGON STATE BRIDGE CONSTRUCTION INC | ||||||||||
| Line | Number | Description | Unit | Quantity | Price | Total | Price | Total | Price | Total | Price | Total | Price | Total |
| 1 | 0210-0100 | MOBILIZATION | LS (Lump Sum) | 1 | $26,408.55 | $26,408.55 | $27,000.00 | $27,000.00 | $40,000.00 | $40,000.00 | $42,150.00 | $42,150.00 | $42,500.00 | $42,500.00 |
| 2 | 0225-0050 | TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC | LS (Lump Sum) | 1 | $27,500.00 | $27,500.00 | $8,500.00 | $8,500.00 | $16,000.00 | $16,000.00 | $13,980.00 | $13,980.00 | $10,000.00 | $10,000.00 |
| 3 | 0225-0075 | TEMPORARY SIGNS | LS (Lump Sum) | 300 | $10.00 | $3,000.00 | $36.00 | $10,800.00 | $42.00 | $12,600.00 | $38.50 | $11,550.00 | $36.00 | $10,800.00 |
| 4 | 0225-0114 | TEMPORARY BARRICADES, TYPE III | EA (Each) | 8 | $150.00 | $1,200.00 | $200.00 | $1,600.00 | $230.00 | $1,840.00 | $325.00 | $2,600.00 | $200.00 | $1,600.00 |
| 5 | 0225-0210 | TEMPORARY PLASTIC DRUMS | EA (Each) | 40 | $30.00 | $1,200.00 | $45.00 | $1,800.00 | $55.00 | $2,200.00 | $55.00 | $2,200.00 | $45.00 | $1,800.00 |
| 6 | 0225-0450 | PORTABLE CHANGEABLE MESSAGE SIGNS | EA (Each) | 2 | $1,500.00 | $3,000.00 | $5,000.00 | $10,000.00 | $3,250.00 | $6,500.00 | $2,850.00 | $5,700.00 | $15,000.00 | $30,000.00 |
| 7 | 0225-0490 | FLAGGERS | HR (Hour) | 80 | $55.00 | $4,400.00 | $65.00 | $5,200.00 | $75.00 | $6,000.00 | $72.00 | $5,760.00 | $1.00 | $80.00 |
| 8 | 0280-0100 | EROSION CONTROL | LS (Lump Sum) | 1 | $1,500.00 | $1,500.00 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | $2,800.00 | $2,800.00 | $10,000.00 | $10,000.00 |
| 9 | 0280-0192 | INLET FILTER INSERTS, TYPE 3 | EA (Each) | 2 | $200.00 | $400.00 | $150.00 | $300.00 | $175.00 | $350.00 | $89.00 | $178.00 | $250.00 | $500.00 |
| 10 | 0280-0255 | CONCRETE WASHOUT FACILITY | EA (Each) | 1 | $1,500.00 | $1,500.00 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $2,800.00 | $2,800.00 | $2,000.00 | $2,000.00 |
| 11 | 0280-0322 | SEDIMENT BARRIER, TYPE 3 | FT (Foot) | 440 | $6.00 | $2,640.00 | $5.00 | $2,200.00 | $6.00 | $2,640.00 | $5.25 | $2,310.00 | $6.00 | $2,640.00 |
| 12 | 0290-0100 | POLLUTION CONTROL PLAN | LS (Lump Sum) | 1 | $100.00 | $100.00 | $500.00 | $500.00 | $1,500.00 | $1,500.00 | $1,950.00 | $1,950.00 | $1,000.00 | $1,000.00 |
| 13 | 0305-0100 | CONSTRUCTION SURVEY WORK | LS (Lump Sum) | 1 | $5,000.00 | $5,000.00 | $6,200.00 | $6,200.00 | $7,000.00 | $7,000.00 | $9,500.00 | $9,500.00 | $5,000.00 | $5,000.00 |
| 14 | 0310-0100 | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | LS (Lump Sum) | 1 | $67,500.00 | $67,500.00 | $5,700.00 | $5,700.00 | $5,000.00 | $5,000.00 | $9,300.00 | $9,300.00 | $11,500.00 | $11,500.00 |
| 15 | 0320-0100 | CLEARING AND GRUBBING | LS (Lump Sum) | 1 | $1,000.00 | $1,000.00 | $10,000.00 | $10,000.00 | $7,500.00 | $7,500.00 | $8,750.00 | $8,750.00 | $16,500.00 | $16,500.00 |
| 16 | 0501-0100 | BRIDGE REMOVAL WORK | LS (Lump Sum) | 1 | $10,000.00 | $10,000.00 | $34,500.00 | $34,500.00 | $6,500.00 | $6,500.00 | $26,335.00 | $26,335.00 | $60,000.00 | $60,000.00 |
| 17 | 0510-0250 | STRUCTURE EXCAVATION | LS (Lump Sum) | 1 | $1,500.00 | $1,500.00 | $1,840.00 | $1,840.00 | $6,500.00 | $6,500.00 | $8,900.00 | $8,900.00 | $15,000.00 | $15,000.00 |
| 18 | 0510-0750 | GRANULAR STRUCTURE BACKFILL | LS (Lump Sum) | 1 | $500.00 | $500.00 | $1,350.00 | $1,350.00 | $5,500.00 | $5,500.00 | $9,800.00 | $9,800.00 | $10,000.00 | $10,000.00 |
| 19 | 0530-0100 | REINFORCEMENT | LS (Lump Sum) | 1 | $21,400.00 | $21,400.00 | $15,000.00 | $15,000.00 | $19,000.00 | $19,000.00 | $18,235.00 | $18,235.00 | $35,000.00 | $35,000.00 |
| 20 | 0542-0110 | CONCRETE REPAIR | SY (Square Yard) | 8 | $500.00 | $4,000.00 | $250.00 | $2,000.00 | $750.00 | $6,000.00 | $875.00 | $7,000.00 | $500.00 | $4,000.00 |
| 21 | 0545-0100 | REINFORCED CONCRETE BRIDGE END PANELS | SY (Square Yard) | 87 | $1.00 | $87.00 | $550.00 | $47,850.00 | $435.00 | $37,845.00 | $485.00 | $42,195.00 | $575.00 | $50,025.00 |
| 22 | 0585-0100 | ASPHALTIC PLUG JOINT SEALS | LS (Lump Sum) | 1 | $8,000.00 | $8,000.00 | $10,500.00 | $10,500.00 | $12,275.00 | $12,275.00 | $19,365.00 | $19,365.00 | $15,000.00 | $15,000.00 |
| 23 | 0585-0220 | POURED JOINT SEAL | LS (Lump Sum) | 1 | $1,750.00 | $1,750.00 | $2,150.00 | $2,150.00 | $2,500.00 | $2,500.00 | $7,600.00 | $7,600.00 | $5,000.00 | $5,000.00 |
| 24 | 0640-0100 | AGGREGATE BASE | TN (Ton) | 360 | $20.00 | $7,200.00 | $34.00 | $12,240.00 | $60.00 | $21,600.00 | $58.50 | $21,060.00 | $54.50 | $19,620.00 |
| 25 | 0740-0120 | COMMERCIAL ASPHALT CONCRETE PAVEMENT, 1/2" DENSE | TN (Ton) | 225 | $150.00 | $33,750.00 | $124.05 | $27,911.25 | $136.00 | $30,600.00 | $125.50 | $28,237.50 | $160.00 | $36,000.00 |
| 26 | 0810-0100 | GUARD RAIL, TYPE 2A | FT (Foot) | 50 | $35.00 | $1,750.00 | $39.44 | $1,972.00 | $41.00 | $2,050.00 | $39.50 | $1,975.00 | $35.00 | $1,750.00 |
| 27 | 0810-0250 | GUARDRAIL TRANSITION | EA (Each) | 4 | $3,200.00 | $12,800.00 | $3,006.53 | $12,026.12 | $3,650.00 | $14,600.00 | $4,300.00 | $17,200.00 | $3,130.00 | $12,520.00 |
| 28 | 0810-0370 | GUARDRAIL TERMINALS, NON-FLARED, TEST LEVEL 3 | EA (Each) | 4 | $3,500.00 | $14,000.00 | $3,300.15 | $13,200.60 | $4,000.00 | $16,000.00 | $3,750.00 | $15,000.00 | $3,415.00 | $13,660.00 |
| 29 | 1030-0227 | NATIVE PLANT SEEDING | AC (Acre) | 0.1 | $10,000.00 | $1,000.00 | $17,000.00 | $1,700.00 | $20,000.00 | $2,000.00 | $41,000.00 | $4,100.00 | $17,000.00 | $1,700.00 |
| $264,085.55 | $277,039.97 | $295,100.00 | $348,530.50 | $425,195.00 |