PUBMID008352 VDPS - Lincoln High School BidPermit Set.pdf

PDF 2 MB Posted

Attached to
Interior Door Upgrades High School and Middle School
Solicitation number
RFP-VDPS-250000002363-2
Issued by
Macomb County, Westland City, Michigan

About this file

The document is a bid set for interior door improvements at Lincoln High School for Van Dyke Public Schools, located in Warren, Michigan. The project involves renovating existing educational building spaces, specifically targeting door replacements in the Music Suite and Auditorium. The scope excludes broader building envelope and structural updates, focusing instead on selective door replacements. The project is designed for 100% Construction Documents (CD) as of 04/09/2025, with previous revisions at 75% and 95% CD stages.

The project documents detail precise specifications for door replacements, including door types D1, D2, and D3, with specific hardware requirements and fire rating considerations. The renovation covers multiple rooms in the Music Suite and Auditorium, including practice rooms, storage areas, and offices. Notable technical specifications include using 2021 Michigan Rehabilitation Code, Alteration Level 2, and adherence to various state and national building codes. The total building area is substantial, with 225,994 square feet of total area, and the specific work area for this project is 7,012 square feet. An important preparatory requirement is asbestos abatement, which must be performed and inspected by certified entities prior to construction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site

Building Code:

Mechanical Code:

Electrical Code:

Plumbing Code:

Energy Code:

Life Safety Code:

Use Group:

Construction Type:

Area, Building:

Existing Basement:

Existing 1st Floor:

Existing 2nd Floor:

Total Area:

Work Area:

Music Suite (1st Floor):

Auditorium (1st Floor):

2021 Michigan Rehabilitation Code Alteration Level 2

2021 Michigan Mechanical Code 2023 National Electrical Code (NEC) 2021 Michigan Plumbing Code 2015 Michigan Uniform Energy Code

2012 NFPA 101

E, Education

IIB

7,035 SF

135,785 SF

49,786 SF

225,994 SF

7,012 SF

9,298 SF

A. Asbestos abatement performed and inspected by certified entities will be required.

Project Number

ISSUE FOR BID:

NOT TO SCALE

OWNER

ARCHITECT

CITY, STATE, ZIP:

STREET:

COMPANY:

PHONE:

AOR:

CONTACT:

EMAIL:

COMPANY:

SITE MAP

SHEET INDEXPROJECT SCOPE NARRATIVEPROJECT TEAM

NAME:

Date:

Exp. Date:

Lic. No.

Ann Arbor, MI, 48103

2373 Oak Valley Drive

O|X Studio, Inc.

(734) 929-9000

Robb Burroughs

Matt Biglin mattb@oxstudioinc.com

Van Dyke Public Schools

ROBERT BURROUGHS

04-09-2025 04-22-2025

1301043972

SHEET

1 2 3 4 5 6

A

B

C

D

E a rc h it ec tu re co n st ru ct io o b je ct s

P

) 9

-9

F:

(7

) 9

-9 w w w

.o xs tu d io in c.

m

STREET:

CONTACT:

PHONE:

EMAIL:

11387 East Nine Mile Road

Jeffrey VanConant, Director of Facilities and Operations

Office: (586) 759-9439 Cell: (586) 634-3589 vanconant.jeff@vdps.net

Warren, MI 48089CITY, STATE, ZIP:

PROJECT MANAGER

CITY, STATE, ZIP:

STREET:

COMPANY:

PHONE:

PM:

CONTACT:

EMAIL:

Minneapolis, MN, 55402

80 South 8th Street, Suite 1850

Site LogiQ Design, LLC

(612) 770-4704

Tim Stevenson

Tim Stevenson tim.stevenson@sitelogiq.com

APPLICABLE CODES & LIFE SAFETY SUMMARY SPECIAL INSPECTIONS & TESTS

/9

/2

:4

:3

P M

VDP25

04/09/25

G-100

L in c o ln

H ig h S c h o o l

I n te ri o r D o o r Im p ro v e m e n ts

Title Sheet

22900 Federal Ave, Warren, MI 48089

Lincoln High School - 2025 Interior Door Improvements

F e d e ra l A v e

W a rr e n

M I

Sheet Number Sheet Name Current Revision Description

Current Revision Date

General

G-100 Title Sheet 100% CD 04/09/2025

G-101 General Information & Accessible Clearances 100% CD 04/09/2025

Demolition

AD-101 Demolition Plans 100% CD 04/09/2025

Architectural

A-101 Floor Plan 100% CD 04/09/2025

A-401 Enlarged Floor Plans 100% CD 04/09/2025

A-701 Door & Frame Legend & Details 100% CD 04/09/2025

22900 Federal Ave, Warren, MI

Renovation of existing Educational building. Select doors to be replaced in Music Suite and Auditorium. Other building envelope improvements and structural updates are not included as part of this scope.

# REVISION DATE

1 75% CD 03/21/2025

2 95% CD 04/03/2025

3 100% CD 04/09/2025

PT-1

A-101

SIM

101.1

XX

XX

1i

1t

A-101

SIM

Reference Text

Top #: Detail Number (Location on sheet)

Bottom #: Sheet on which detail is located

Typical Detail Bubble (applies to all detail types):

Detail plan view:

Dashed outline indicates area being detailed

Detail section view:

Tail indicates direction of section cut

Door number. See door and hardware schedule.

Window Type number.

See window schedule.

Accent paint location and paint identification. Accent paint color to be continuous for entire length of wall.

Electrical fixture tag

Lighting fixture tag

Plumbing fixture tag

Equipment tag

Extent of finish material replacement if not continuous for entire length of wall.

Indicates face of new construction to be aligned with face of existing construction to remain.

A

A-202

A-242

1 Ref

R ef

1 Ref

R ef

1000T

150 SF

Room name

Building section:

Arrow indicates direction of building section

Exterior elevation:

Arrow indicates face of structure being represented

Top #: Detail Number (Location on sheet)

Bottom #: Sheet on which detail is located

Reference Text

Detail Number (Location on sheet)

Sheet on which detail is located

Interior elevation:

Level Mark

New column grid

Keynotes:

See sheet notes, same sheet as symbol

Indicates room number Indicates room area

Room Tag:

Wall section:

Tail indicates direction of section cut

Target Elevation

A Existing column grid

+ 5'-0"

New construction / New door and frame shown open 90º.

Indicates change in flooring material.

A-101

SIM

A-202

SIM

A-202

SIM

A-101

Name

Elevation

Wall partition type tag0 S A.

1t

## ## ##.A Reference Keynotes

Sheet Keynotes

Existing construction to remain. Existing doors shown open 45º.

Wall Floor Base

North Wall Accent finish location and finish identification. Accent finish to be continuous for entire length of wall.

Wall finish

Floor finish

Wall base type

N

1 View Name A101 1/8" = 1'-0"

View title with Graphic Scale & North Arrow:

Detail number

Graphic scale of drawing

Sheet number

North Arrow (Direction varies per project)

Determine where 1' lies on the graphic scale

Reading the Graphic Scale:

4' 8' Measure to 1' on the sheet to determine the scale

4' - 8" (min) w cl os er

(m in

) o r

(m in

(m in closer & latch 12" (min) w/ w cl os er

(m in

) o r d o r

= Direction of Travel Approach

ADA Door and Maneuvering Clearances m in m in w cl o se r

(m in

) o r

(min)

2' - 0"

42" @ d=54"

36" @ d=60"

2' - 0"

(min)

1' - 6"

Door maneuvering clearances Clearances for doors in series

22" min.

m in m in . 24" min.

m in m in . 24" min.

32" min.

Opaque Assemblies:

Roofs Insulation Entirely above Deck R-30.0 c.i. (U-0.032) Metal Building R-19 + R-11 Ls (U-0.037) or R-25 + R-8 Ls Attic and Other: R-49.0 (U-0.021)

Walls, Above-Grade Mass Walls (Concrete, CMU) R-11.4 c.i. (U-0.090) Metal Building R-0 + R-19 c.i. (U-0.050) Steel-Framed R-13.0 + R-10 c.i. (U-0.055) Wood-Framed and Other R-13.0 + R-7.5 c.i. (U-0.051) or R-19 + R-5 c.i.

Walls, Below-Grade Below-Grade Walls (all) R-7.5 c.i. (C-0.119)

Floors (Exposed Beneath) Mass R-14.6 c.i. (U-0.057) Steel-Joist R-30.0 (U-0.038) Wood-Framed and Other R-30.0 (U-0.033)

Slab-On-Grade Floors Unheated R-15 for 24 in. (F-0.520) Heated R-20 for 48 in. (F-0.688)

Opaque Doors Swinging (U-0.500) Nonswinging (U-0.500)

Fenestration (Including glazed doors):

Vertical Glazing, 0% - 40% of wall Nonmetal framing (all) U-0.32 SHGC-0.40 VT/SHGC = 1.10 Metal framing

Fixed U-0.42 SHGC-0.40 VT/SHGC = 1.10 Operable U-0.50 SHGC-0.40 VT/SHGC = 1.10 Entrance Door U-0.77 SHGC-0.40 VT/SHGC = 1.10

Skylight, All Types 0% - 3% of Roof Uall-0.50 SHGCall-0.40 (No VT/SHGC req't.)

Values based on ASHRAE 90.1 - 2013, Climate Zone 5A, Non-Residential.

Project Number

ISSUE FOR BID:

NAME:

Date:

Exp. Date:

Lic. No.

ROBERT BURROUGHS

04-09-2025 04-22-2025

1301043972

SHEET

1 2 3 4 5 6

A

B

C

D

E a rc h it ec st ru ct je ct

) 9

-9

) 9

-9 w w w

.o xs tu d io in c.

/9

/2

:4

:3

P M

VDP25

04/09/25

G-101

L in c o ln

H ig h S c h o o l

I n te ri o r D o o r Im p ro v e m e n ts

General Information & Accessible Clearances

F e d e ra l A v e

W a rr e n

M I

General Symbol Legend Graphic Scale LegendMinimum Insulation Values

# REVISION DATE

1 75% CD 03/21/2025

D1

D1D1 D1

D1

D1

D1

D1

D1

D1

D1 D1

D2

D2

D2

D2 D2 D2

D2

D2

D2

D2

D2

D2

D1D1 D1 D1

D1

D1

D2 D2 D2 D2

D2

D2

Existing construction to remain.

Demolition Floor Plan Legend

Existing construction to be demolished.

Project Number

ISSUE FOR BID:

NAME:

Date:

Exp. Date:

Lic. No.

ROBERT BURROUGHS

04-09-2025 04-22-2025

1301043972

SHEET

1 2 3 4 5 6

A

B

C

D

E a rc h it ec st ru ct je ct

) 9

-9

) 9

-9 w w w

.o xs tu d io in c.

/9

/2

:4

:3

P M

VDP25

04/09/25

AD-101

L in c o ln

H ig h S c h o o l

I n te ri o r D o o r Im p ro v e m e n ts

Demolition Plans

F e d e ra l A v e

W a rr e n

M I

General Sheet Notes:

A. Demolish existing interior construction as indicated.

B. All dimensions to be verified in field prior to construction. Notify

Architect of all discrepancies in layout prior to starting framing.

C. All existing materials to remain, U.N.O. Those damaged or otherwise disturbed by the contractor's operations shall be patched and repaired to match existing adjacent materials so that repair is imperceptible.

D. Contractor shall maintain all required exits unobstructed, illuminated, and protected from construction activities.

E. Contractor to clean areas adjacent to demolition area of dust, dirt and debris caused by demolition operations.

F. Promptly dispose of demolished materials. Do not allow demolished materials to accumulate onsite. Transport demolished materials and legally dispose of them.

G. Contractor shall notify Architect of any conflicts between existing conditions and construction documents.

H. Area of demolition will require assessment for asbestos and potential abatement, by VDPS. Abatement must be conducted by a certified professional. Construction to coordinate with abatement as it occurs.

I. Salvage removed (mortise lock) hardware to Director of Building and Grounds. Coordinate with SIQ PM and District Representative.

Sheet Keynotes D1 Demolish existing door, frame, casing and hardware.

Coordinate removal with district asbestos consultant.

D2 Prep opening to receive new door and door frame.

N

AD-101 1/8" = 1'-0"

8'4' 16'

2 Demo - Music Suite

N

AD-101 1/8" = 1'-0"

8'4' 16'

1 Demo - Auditorium

# REVISION DATE

1 75% CD 03/21/2025

E X

IS

T

G A

S

M E

T E

R

S N

A P

C O

L E

R

E X

IS

T

IN

G

R E

F R

IG

EXISTING ICE

CREAM COLER

C O

K E

C O

L E

R

Architectural Floor Plan Legend

New Construction

Area Not in Scope

Align Symbol

Existing Construction to Remain

A. All dimensions to be verified in field prior to construction. Notify architect of all discrepancies prior to starting work.

B. All dimensions on plans are to face of finish face or column centerlines, Unless Noted Otherwise (U.N.O.)

C. All interior door frames shall be located a distance of six inches from the throat return to the closest adjacent perpendicular partition, U.N.O.

D. Refer to sheet A-701 for Door Schedule.

E. Refer to sheet A-401 for room occupancy loads.

Music Suite

Auditorium

A-401

Sim

A-401

Sim

Project Number

ISSUE FOR BID:

NAME:

Date:

Exp. Date:

Lic. No.

ROBERT BURROUGHS

04-09-2025 04-22-2025

1301043972

SHEET

1 2 3 4 5 6

A

B

C

D

E a rc h it ec st ru ct je ct

) 9

-9

) 9

-9 w w w

.o xs tu d io in c.

/9

/2

:4

:3

P M

VDP25

04/09/25

A-101

L in c o ln

H ig h S c h o o l

I n te ri o r D o o r Im p ro v e m e n ts

Floor Plan

F e d e ra l A v e

W a rr e n

M I

General Sheet Notes:

N A-101 1/32" = 1'-0"

32'16' 64'

1 Overall Floor Plan

# REVISION DATE

1 75% CD 03/21/2025

UP

UP

UP

UP

Architectural Floor Plan Legend

New Construction

Area Not in Scope

Align Symbol

Existing Construction to Remain

6759 SF

G105

Auditorium

1519 SF

G100

Lobby

G105B

G105A

G105J G105C

G105D G105E G105HG105F

G101

900 Occ.

A1 A1

A1

2619 SF

F113 Band

1751 SF

F119

Vocal

145 SF

F115

Practice

153 SF

F117

Storage

79 SF

F118

Practice

125 SF

F121

Office

126 SF

F122

Storage

321 SF

F120

Instrument Storage

142 SF

F116

Storage

135 SF

F114

Storage

144 SF

F100

Office

142 SF

F101

Storage

67 SF

F102

Practice Room

70 SF

F103

Practice Room

70 SF

F104

Practice Room

106 SF

F105

Practice Room

74 SF

F106

Practice Room

70 SF

F107

Practice Room

66 SF

F108

Practice Room F120A

F122A

F120B

F106A

F114A

F116B

F115A

F118A

F121A

F116A F117A

F107A

F108A

F105A

F100A F101A

F102A

F103A

F104A

52 Occ.

1 Occ.

1 Occ.

1 Occ. 7 Occ.

1 Occ. 1 Occ.

3 Occ.

1 Occ. 3 Occ.

1 Occ.

35 Occ.

5 Occ.

3 Occ.

3 Occ.

3 Occ.

3 Occ.

3 Occ.

3 Occ.

A. All dimensions to be verified in field prior to construction. Notify architect of all discrepancies prior to starting work.

B. All dimensions on plans are to face of finish face or column centerlines, Unless Noted Otherwise (U.N.O.)

C. Refer to sheet A-701 for Door Schedule.

Project Number

ISSUE FOR BID:

NAME:

Date:

Exp. Date:

Lic. No.

ROBERT BURROUGHS

04-09-2025 04-22-2025

1301043972

SHEET

1 2 3 4 5 6

A

B

C

D

E a rc h it ec st ru ct je ct

) 9

-9

) 9

-9 w w w

.o xs tu d io in c.

/9

/2

:4

:3

P M

VDP25

04/09/25

A-401

L in c o ln

H ig h S c h o o l

I n te ri o r D o o r Im p ro v e m e n ts

Enlarged Floor Plans

F e d e ra l A v e

W a rr e n

M I

General Sheet Notes:

Sheet Keynotes A1 Crash bars required on new exit doors for spaces with an occupancy over 50.

N A-401 1/8" = 1'-0"

8'4' 16'

1 New - Auditorium

N A-401 1/8" = 1'-0"

4'2' 8'

2 New - Music Suite

# REVISION DATE

1 75% CD 03/21/2025

Door Type D1 Door Type D2

1/4" Fully tempered safety glazing

Per schedule

P er s ch ed u le

"P er s ch ed u le

Per schedule

6"

Door Type D3

P er s ch ed u le

Per schedule

Frame Type F1

2" Per schedule 2"

P er s ch ed u le

Door Hardware (Measured floor to center of hardware)

(K n ob an d

P an ic E xi t

P u ll H an dl e

P u sh P la te

Project Number

ISSUE FOR BID:

NAME:

Date:

Exp. Date:

Lic. No.

ROBERT BURROUGHS

04-09-2025 04-22-2025

1301043972

SHEET

1 2 3 4 5 6

A

B

C

D

E a rc h it ec st ru ct je ct

) 9

-9

) 9

-9 w w w

.o xs tu d io in c.

/9

/2

:4

:3

P M

VDP25

04/09/25

A-701

L in c o ln

H ig h S c h o o l

I n te ri o r D o o r Im p ro v e m e n ts

Door & Frame Legend & Details

F e d e ra l A v e

W a rr e n

M I

Door Type Legend

Door Schedule

Mark Room Name

Door Frame Door Hardware

Set Fire

Rating**Width* Height* Thickness* Type Material Finish Type Material Finish

F100A Office 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.01 ---

F101A Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.02 ---

F102A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F103A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F104A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F105A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F106A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F107A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F108A Practice Room 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F114A Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.02 ---

F115A Practice 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F116A Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.04 ---

F116B Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.05 ---

F117A Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.04 ---

F118A Practice 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.03 ---

F120A Instrument Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.06 20 min.

F120B Instrument Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.07 ---

F121A Office 3' - 0" 7' - 0" 0' - 1 3/4" D2 HM/GL By Manuf. F1 HM PT H.01 ---

F122A Storage 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.04 ---

G101 Lobby 6' - 0" 7' - 0" 0' - 1 3/4" D3 HM By Manuf. F1 HM PT H.08

G105A Auditorium 3' - 6" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105B Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105C Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105D Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105E Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105F Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105H Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

G105J Auditorium 3' - 0" 7' - 0" 0' - 1 3/4" D1 HM By Manuf. F1 HM PT H.09 20 min.

Door Frame Legend

Door Hardware Heights Diagram

General Sheet Notes:

A. Refer to specifications for additional door hardware requirements, including submittal requirements.

Note:

* Verify all door sizes in field. Dimensions of new doors and frames to match existing.

** Verify existing fire rating for the doors being replaced, and replace in-kind for any doors with existing ratings greater than newly noted ratings.

# REVISION DATE

1 75% CD 03/21/2025

Sheets
A-101 - Floor Plan
A-401 - Enlarged Floor Plans
A-701 - Door & Frame Legend & Details
AD-101 - Demolition Plans
G-100 - Title Sheet
G-101 - General Information & Accessible Clearances

File details come from the government source that posted it. Updated .