This is a Propane Standby System Inspection Report dated October 9, 2018, for the Baraga Maximum Correctional Facility in Baraga, MI, conducted by IPS Industrial Propane Service. The inspection covered a comprehensive evaluation of the facility's propane system, including storage tank inspection, internal valves, emergency shutdown systems, transport bulkhead, liquid pumps, bypass valves, and vaporizer/mixer unit. The inspection was performed by Ken Oswald with facility representative Tyler present.
The report indicates the storage tank is at 65% capacity and manufactured by Trinity (serial #118362) with a 30-gallon capacity. The vaporizer/mixer unit is an Ely Energy model from 1990 operating at specific parameters including pump PSI of 120, optimum temperature of 160°F, and gas mix settings of 1.32 across all three units. Most components were found to be in good working condition, with only minor issues noted including small weeds in the fenced area and a small flex on the bypass line. The system features multiple safety components including emergency shutdown systems, hydrostatic relief valves, and monitoring gauges, all of which were verified to be functioning properly.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Design Build Advertisement R10-17).pdf | ||
| Gas Distribution-Shts.I--6.pdf | ||
| 472_19087.RAA Addendum 2.pdf | ||
| Ely Energy Vaporizer.pdf | ||
| Design Build Spec Final.pdf | ||
| LEIN Request REV 04-2018.pdf | ||
| 472_19087.RAA Addendum 1.pdf | ||
| Site Photos.pdf | ||
| Ely Energy Mixer.pdf | ||
| LPG Equipment Layout.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOB INFORMATION
Job # 10990
Customer # M5-053
Customer Name & Billing Address BARAGA MAXIMUM CORRECTIONAL FACILITY [301
WADAGA ROAD BARAGA, MI 49908]
Location Name & Address BARAGA MAXIMUM CORRECTIONAL FACILITY [301
WADAGA ROAD BARAGA, MI 49908]
IPS Job Coordinator Dutch (Olin) Russell
STORAGE TANK INSPECTION
Any leaks at tank fittings? No
Multi-port in proper working condition? Yes
Relief valve stacks in good condition? Yes
Remarks
8d09
Relief valve stacks have their protective caps in place? Yes
Magnetel gauge in good working condition? Yes
Temperature and pressure gauges in good condition? Yes
Piers and tank pads in good condition? Yes
Product in tank at time of inspection? Yes
Remarks
65%
Any combustible materials inside of fenced areas? Yes
Remarks
Small weeds
INTERNAL VALVES & EMERGENCY SHUTDOWN SYSTEM
Internal valves in good working condition? Yes
ESV valves in good working condition? Yes
Emergency shutdown system working correctly? Yes
Emergency shutdown signs or decals in place and in good condition? Yes
TRANSPORT BULKHEAD
Any leaks in piping from bulkhead to tank (liquid and vapor)? No
Liquid and vapor acme adapters in good condition? Yes
Does the system have the required safety features and are they in good working condition?
Yes
Liquid and vapor decals in place? Yes
Emergency shutdown system in place and in good working condition? Yes
Emergency signs or decals in place and in good condition? Yes
LIQUID PUMPS & BYPASS VALVES
Are the pumps in working condition? Yes
Have the pumps been greased? Yes
Did IPS employee need to grease pumps? No
Any leaks in piping from tank valves to pump inlet? Yes
Remarks
Small flex on bypass line
Any leaks in pump assembly or pump flanges? No
Pump pressure checked. Yes
PSI Pump is running at 120
Pump pressure gauge in good condition? Yes
Pump bypass valve was checked for proper working condition? Yes
Checked pump motor wiring
(conduit, flexes, seal-offs)
Yes
Hydrostatic relief valves in required locations? Yes
Checked hydrostatic reliefs for debris, weep hole location & that protective caps are in place.
Yes
LIQUID LINE FROM PUMPS TO VAPORIZER INLET
303 W. Maple St. PO Box 145
Byron, MI 48418
P) 810-266-4687
Date: 10/09/2018Propane Standby System Inspection Report
Submitted by MI Construction Service 2 at 10/09/2018 14:43 EDT Page: 1
Captured at 10/09/2018 14:42 EDT gocanvas.com
Submission ID: C5B5FB8F-4848-44F9-8106-FE307BE6713F https://www.gocanvas.com/?utm_source=canvas_pdf&utm_medium=pdf_link&utm_campaign=canvas_pdf_link
Any leaks in piping from pumps to vaporizer? No
Hydrostatic relief valves in required locations? Yes
Checked hydrostatic reliefs for debris, weep hole location & that protective caps are in place.
Yes
VAPORIZER / MIXER UNIT INFORMATION
Manufacturer Ely energy
Model # Na
Serial # Na
Year Built 1990
Has Pilot Relighter? Yes
Has thermocouple? No
Gas valve Make/Model # Yes
Has power pile? Yes
High Mix (PSI) 6
Low Mix (PSI) 5
Pump PSI 120
Optimum Temp (Degrees F) 160
Low Temp (Degrees F) 150
High Temp (Degrees F) 165
High Propane 1
Low Propane 1
Vaporizer/Mixer Info Surge Tank
Vaporizer/Mixer Info Venturi Regulator (PSI)
#1 45
#2 35
#3 35
Vaporizer/Mixer Info Gas Mix Setting
#1 1.32
#2 1.32
#3 1.32
STORAGE TANK SPECIFICATIONS
Manufacturer Trinity
Serial # 118362
Capacity 30
Diameter (inches) 131
Length (feet) 561
Manway?
Magnetel?
Rotor Gauge?
PSI Gauge 100
Materials Used
Sa615
Inspector Ken Oswald
Facility Representative(s)
Tyler
Date of Inspection 10/09/2018
303 W. Maple St. PO Box 145
Byron, MI 48418
P) 810-266-4687
Date: 10/09/2018Propane Standby System Inspection Report
Submitted by MI Construction Service 2 at 10/09/2018 14:43 EDT Page: 2
Captured at 10/09/2018 14:42 EDT gocanvas.com
Submission ID: C5B5FB8F-4848-44F9-8106-FE307BE6713F
File details come from the government source that posted it. Updated .