This is a presolicitation document for a federal construction contract involving pavement preservation and minor guardrail installation work across multiple National Park Service projects in Washington State.

The work encompasses four projects: WA NP OLYM PMS(1) Pavement Preservation Olympic Phase 1; WA NP OLYM PMS(2) Pavement Preservation Olympic Phase 2; WA NP NOCA PMS(2) Pavement Preservation Stehekin; and WA FLAP JEFFER 91420(6) Upper Hoh Road Resurfacing. The work is located in Olympic National Park and North Cascades National Park across Chelan, Clallam, Grays Harbor, Jefferson, and Mason Counties. The base schedule covers 60.59 miles and parking areas with three optional phases: Option X adds 1.92 miles, Option Y adds 12.07 miles, and Option Z adds 6.92 miles. The estimated price range is $10,000,000 to $20,000,000 with a tentative solicitation date of Fall/Winter 2026 and a tentative fixed completion date of Fall 2028.

The scope of work includes contractor quality control and assurance, sampling and testing, and construction scheduling requirements. Work encompasses earthwork (guardrail removal), aggregate and base courses, asphalt pavements and surface treatments including micro surfacing and chip seal operations, asphalt concrete pavement patching, guardrail system installation, permanent and temporary pavement markings, rumble strips, and extensive temporary traffic control requirements including flaggers, pilot cars, traffic control supervisors, cones, portable message signs, and construction signage. The base schedule requires rental equipment and general labor, while options X, Y, and Z do not. Quantities vary significantly across the base schedule and optional phases.

View the file

Other files

File Type Posted
WA OLYM NOCA Hoh Prelim Plans.pdf PDF
Prelim Letter_WA NP OLYM PMS(1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA NP OLYM PMS(1), Pavement Preservation Olympic Phase 1;

WA NP OLYM PMS(2), Pavement Preservation Olympic Phase 2;

WA NP NOCA PMS(2), Pavement Preservation Stehekin; &

WA FLAP JEFFER 91420(6), Upper Hoh Road Resurfacing

North Cascades National Park and Olympic National Park

Chelan, Clallam, Grays Harbor, Jefferson, and Mason Counties

Washington

The work consists of pavement preservation and minor guardrail installation.

Project length: BASE SCHEDULE: 60.59 miles and parking areas

OPTION X: 1.92 miles and parking areas

OPTION Y: 12.07 miles and parking areas

OPTION Z: 6.92 miles and parking areas

Tentative Fixed Completion Date: Fall 2028

(Once solicitation is issued, see SF1442 Continuation, Block 11 for exact date.)

Tentative Solicitation Date: Fall/Winter 2026

Estimated Price Range: $10,000,000 to $20,000,000

Location: This project is in Washington State in/adjacent to Olympic National Park and Stehekin in North Cascades National Park.

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-24

B as e

O p ti o n X

O p ti o

Y ti o

Z

DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) No No No No

153 Contractor Quality Control and Assurance (yes/no) Yes Yes Yes Yes

154 Contractor Sampling & Testing (yes/no) Yes Yes Yes Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes Yes

DIVISION 200 – Earthwork

203 Removal of Guardrail 250 LNFT e

O p ti o ti o ti o

DIVISION 300 – Aggregate and Base Courses

302 Roadway Aggregate, Method 2 12 TON

308 Emulsified Asphalt-Treated Aggregate Base, Grading D 375 SQYD

DIVISION 400 – Asphalt Pavements & Surface Treatments

403 Asphalt Concrete Pavement 340 TON

406 Fog Seal 100 TON 45 TON

Chip Seal, Type 1C Emulsified Asphalt Blotter

80 TON

4,400 SQYD

7.8 TON

150,000

SQYD

280 TON

75,000 SQYD

240 TON

409 Micro Surfacing, Type 2 235,000 SQYD 30,000 SQYD

412 Micro Surfacing, Type 3 780,000 SQYD

414 Cracks, Cleaning, and Sealing 7 MILE 1.9 MILE 2.3 MILE

Asphalt Concrete Pavement Patching, Type 1 Asphalt Concrete Pavement Patching, Type 2

680 SQYD

4,500 SQYD 1,650 SQYD

1,400 SQYD

1,600 SQYD 125 SQYD

DIVISION 600 – Incidental Construction

617 Guardrail System MGS, Type 2, Class A, Steel Posts 650 LNFT

622 Rental Equipment (yes/no) Yes No No No

623 General Labor (yes/no) Yes No No No

633 Rumble Strip, Transverse 30 SQYD

Permanent Pavement Markings (Type B) Permanent Pavement Markings, Symbols (Type B)

1,900,000

LNFT

200 EACH

30,000 LNFT

55 EACH

390,000 LNFT

33,400 LNFT

40 EACH

635 Temporary Traffic Control – Flagger 5,500 HOUR 1,600 HOUR 1,500 HOUR 1,100 HOUR

635 Temporary Traffic Control – Pilot Car 350 HOUR 120 HOUR

635 Temporary Traffic Control – Traffic Control Supervisor 75 DAY 25 DAY 25 DAY 45 DAY e

O p ti o ti o ti o

Temporary Traffic Control, Cone Temporary Traffic Control, Portable Changeable Message Sign Temporary Traffic Control, Pavement Markings Temporary Traffic Control, Construction Sign

750 EACH

6 EACH

300,000 LNFT

480 SQFT

4,100 LNFT

65,000 LNFT