This document is a detailed project description for the Fryingpan Creek Bridge replacement project in Mount Rainier National Park, Pierce County, Washington. The project involves constructing a new 218.5-foot long single-span steel plate girder bridge with a cast-in-place concrete deck, founded on deep drilled shafts, and includes roadway realignment, parking lot construction, minor pipe culvert replacement, and stone masonry work. The project is located 31 miles north of Packwood, Washington, with a tentative solicitation date in Winter 2026 and a fixed completion date in Summer 2029.

The project scope is extensive, covering multiple divisions of work including earthwork (21,500 cubic yards of roadway excavation), slope reinforcement, aggregate base courses, asphalt pavements, bridge construction (298,000 pounds of structural steel), and incidental construction. Key quantities include 234 cubic yards of structural concrete, 37,390 pounds of reinforcing steel, 950 linear feet of stone curb, and 5,350 square yards of erosion control products. The estimated price range is $10 million to $20 million, with comprehensive requirements for construction survey, quality control, soil erosion control, traffic management, and environmental mitigation measures.

View the file

Other files

File Type Posted
QA_2-20-2026.pdf PDF
mora11-1_Plans_Pre-Ad.pdf PDF
Fryingpan Prelim Letter.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA NP MORA 11(1), Fryingpan Creek Bridge

Mount Rainer National Park

Pierce County, WA

The work consists of bridge replacement, roadway realignment, parking lot, minor pipe culvert replacement, stone masonry

Bridge Information: The project includes construction of a single span, 218.5-foot long steel plate girder bridge with cast-in-place concrete deck. Abutments are founded on deep foundation

(drilled shafts). The work includes demolition of the existing steel arch girder bridge upon completion of the new structure.

Project length: 0.27 miles

Tentative Fixed Completion Date: Summer 2029

(Once solicitation is issued, see SF-1442 continuation, Block 11 for exact date.)

Tentative Solicitation Date: Winter 2026

Estimated Price Range: $10 million to $20 million

Location: 31 miles North of Packwood, Washington.

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

O n e S ch ed u le

S ch

N am e

B as e_

DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) Yes

153 Contractor Quality Control and Assurance (yes/no) Yes

154 Contractor Sampling & Testing (yes/no) Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes

157 Soil Erosion Control, Silt Fence 3000 LNFT

157 Soil Erosion Control, Fiber Roll 1200 LNFT

157 Soil Erosion Control, Check Dam 80 EACH

157 Soil Erosion Control, Temporary Stream Diversion LPSM e S ch ed

N as e_

DIVISION 200 – Earthwork

201 Clearing & Grubbing 1.8 ACRE

203 Removal of Masonry Guardwall 230 LNFT

203 Removal of Bridge LPSM

204 Roadway Excavation 21,500

CUYD

204 Conserve and Place Boulders 30 EACH

205 Blasting Consultant (Consultant/Engineering Services) (yes/no) No

207 Earthwork Geosynthetics 1000 SQYD

208 Structure Excavation 672 CUYD

211 Roadway Obliteration 1000 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Riprap 950 CUYD

255 Mechanically Stabilized Earth Walls (retaining walls) 1500 SQFT

257 Contactor-Designed Retaining Walls (contractor completed designs) LPSM

DIVISION 300 – Aggregate and Base Courses

302 Minor Crushed Aggregate 2100 TON

303 Ditch Reconditioning 600 LNFT

DIVISION 400 – Asphalt Pavements & Surface Treatments

403 Asphalt Concrete 900 TON

411 Asphalt Prime Coat (asphalt surface treatment) 20 TON

412 Asphalt Tack Coat (asphalt surface treatment) 2 TON

413 Asphalt Pavement Milling 800 SQYD

DIVISION 500 – Rigid Pavement

501 Minor Concrete Pavement 90 SQYD e S ch ed

N as e_

DIVISION 550 – Bridge Construction

551 Untreated Timber Pile, in place 13 EACH

552 Structural Concrete, Class A (AE) (concrete – major structures) 234 CUYD

552 Structural Concrete, Class D (AE) 292 CUYD

552 Structural Concrete, Class D (AE), for approach slab, Type 2 58 SQYD

554 Reinforcing Steel 37,390 LB

554 Reinforcing Steel, Epoxy Coated 73,200 LB

555 Structural Steel, Furnished, Fabricated, and Erected 298,000 LB

556 Bridge Railing, Steel 295 LNFT

564 Bearing Devices 8 EACH

565 Drilled Shafts, 42-in Diameter 420 LNFT

DIVISION 600 – Incidental Construction

602 Minor Pipe Culverts 350 LNFT

602 End Sections 7 EACH

604 Inlets 2 EACH

609 Curb, Stone 950 LNFT

613 Simulated Stone Masonry Surface (concrete – minor structures) 170 SQYD

613 Simulated Stone Masonry Test Wall 1 EACH

615 Sidewalks, Pads & Paved Medians (concrete – minor structures) 350 LNFT

620 Class B Masonry, Rock Face Finish 164 SQYD

620 Stone Masonry Guardwall 475 LNFT

620 Stone Masonry Headwall for 24-in Pipe Culvert 5 EACH

621 Monuments & Markers (construction survey & staking) (yes/no) Yes

622 Rental Equipment (yes/no) Yes

623 General Labor (yes/no) Yes

624 Topsoil (landscaping & related items) 3,200 SQYD

626 Cuttings, Willow Pole 50 EACH

629 Rolled Erosion Control Products & Cellular Confinement Systems (turf establishment) 5,350 SQYD

633 Permanent Traffic Control (sign system) 43 SQFT

633 Remove and Reset Sign 7 EACH e S ch ed

N as e_

634 Permanent Pavement Markings (traffic pavement markings)

15,300

LNFT

635 Temporary Traffic Control – Barricades 6 EACH

635 Temporary Traffic Control – Drum 40 EACH

635 Temporary Traffic Control – Flagger 270 HOUR

635 Temporary Traffic Control – TCS 400 DAYS

635 Temporary Traffic Control – Traffic Signal System 1 EACH

635 Temporary Traffic Control – Construction Sign 350 SQFT

635 Temporary Traffic Control – Portable Changeable Message Sign 2 EACH

636 Conduit, 4-INCH, HDPE 488 LNFT

637 Facilities & Services (field office) 39 MONTHS

646 Fixture, Bicycle Storage Rack 3 EACH

646 Fixture, Pedestrian Railing (Stone-Timber) 300 LNFT

647 Mitigation, Log Deflector 10 EACH

647 Mitigation, Root Wad 12 EACH