QA_2-20-2026.pdf

PDF 87 KB Posted

Attached to
WA NP MORA 11(1), Fryingpan Creek Bridge
Solicitation number
69056726B000001
Issued by

About this file

This is a Questions and Answers document for Project No. WA NP MORA 11(1), Fryingpan Creek Bridge. The document contains one general question regarding the project advertisement timeline. According to the response dated February 20, 2026, the Fryingpan Creek Bridge Project was originally scheduled to be advertised for bid in December 2025 but has been rescheduled to Spring 2026, specifically April or May 2026. No additional contract details, requirements, or specifications are provided in this document.

View the file

Other files

File Type Posted
PROJECT DESCRIPTION_WA NP MORA 11(1).pdf PDF
mora11-1_Plans_Pre-Ad.pdf PDF
Fryingpan Prelim Letter.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. WA NP MORA 11(1), Project Fryingpan Creek Bridge

# General Technical Question Answer Date

1 X

Could you tell me when the Frying Pan Bridge

Project is scheduled to be advertised for bid?

The original plan was December 2025.

We are now anticipating a Spring 2026

(April/May) advertisement.

2/20/26

Check General or Technical

File details come from the government source that posted it. Updated .