Product_Substitution_Request_Form.pdf

PDF 107 KB Posted

Attached to
Generator Replacement for Collin County Adult Detention Facility (CCADF) Lower B
Solicitation number
2026-063
Issued by
Collin County, Texas

About this file

This is a Product Substitution Request Form associated with Collin County, Texas's sealed bid solicitation 2026-063 for Generator Replacement at the Collin County Adult Detention Facility (CCADF) Lower B, with an estimated probable construction cost of $1,100,000.00. The form establishes the procedural mechanism for bidders to propose alternative products or materials in place of those specified in the project manual. Bidders must submit substitution requests by the deadline specified in the solicitation and provide comprehensive supporting documentation including product descriptions, specifications, drawings, photographs, and performance or test data. The form requires bidders to certify that proposed substitutions are equal or superior to specified products, maintain equivalent warranties and maintenance service, present no adverse effects on other trades or schedule delays, do not affect dimensions or functional clearances, and that the bidder will cover any costs associated with design changes resulting from the substitution.

The Product Substitution Request Form functions as a formal review mechanism within the project procurement process. Upon submission, the form undergoes evaluation and review by project officials who may approve the substitution, approve it with noted conditions, reject it in favor of specified materials, or reject it if submitted past the deadline specified in the solicitation documents. The form requires detailed information about the bidder, project identification, specific contract sections affected, and the proposed manufacturer and model information. Supporting documentation options include drawings, product data, physical samples, test results, and other relevant reports to substantiate the substitution request and enable comprehensive evaluation against the original specification requirements.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRODUCT SUBSTITUTION REQUEST FORM

(Must be submitted by the date specified within the solicitation)

Bidder: Project No:

Project:

Section: Article/ Paragraph:

Proposed Substitution:

Manufacturer: Address:

Telephone: Proposed Model No.:

Attached data includes product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.

Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its installation.

The undersigned certifies:

• Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

• Same warranty will be furnished for proposed substitution as for specified product.

• Same maintenance service and source of replacement parts, as applicable, is available.

• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

• Proposed substitution does not affect dimensions and functional clearances.

• Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by substitution.

Submitted By: Signed:

Firm: Address:

Phone:

REVIEW & ACTION (Initial)

Substitution approved - Make submittals in accordance with Project Manual requirements.

Substitution approved as noted - Make submittals in accordance with Project Manual requirements.

Substitution rejected - Use specified materials.

Substitution Request received too late - Use specified materials.

Signature: Date:

Supporting Data Attached: ____Drawings ____Product Data ____Samples ____Tests ____Reports ____Other

END OF REQUEST FORM