This is a pricing sheet for a federal construction solicitation requiring roof repairs at two buildings at MCB Camp Lejeune, North Carolina. The solicitation number is N40085-26-R-9033 and the project number is 26-0422.

Offerors must provide separate pricing for two Exhibit Line Items (ELINs): ELIN 0001 covers all roof repair work at Building HP145 in accordance with provided drawings and specifications, while ELIN 0002 covers roof repairs at Building HP175. Each line item price must include all applicable costs, overhead, labor burden, and profit. Submission on all line items is mandatory; failure to propose on all items will result in rejection of the offer as non-responsive. The Government will evaluate offers for award by adding the prices for ELINs 0001 and 0002, though evaluation of options does not obligate the Government to exercise them in accordance with FAR 52.217-5.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roof Repairs BEQ HP145 & HP175 Solicitation No. N40085-26-R-9033 MCB Camp Lejeune, North Carolina Project No. 26-0422

PRICING SHEET

Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter:

ELIN 0001

Price includes completing all work associated with roof repairs at Building HP145 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0002. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0002

Price includes completing all work associated with roof repairs at Building HP175 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001. The price for this line item should include all applicable costs, overhead and profit for this work.

TOTAL ELIN 0001 - 0002: $______________________________________

Notes A. Offers must be submitted on all line items. Failure to propose on all line items may result in the offer being rejected as non-responsive.

B. ELINs shall include all markups (overhead, labor burden, and profit).

C. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for ELINs 0001 and 0002. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).