Pricing Schedule-Attachment C.pdf

PDF 121 KB Posted

Attached to
B6030 A/C Roof Sealant
Solicitation number
FA466126R0006
Issued by

About this file

This is a Pricing Schedule for federal construction contract FNWZ 26-0180, specifically for roof coating sustainment work on buildings B6030 A & C and B6015 A & C. The contractor must provide a lump sum (LS) price that encompasses all survey, layout, plant, labor, supplies, equipment, materials, supervision, and incidentals required to complete the sustainment work in full compliance with the Statement of Work and contract terms and conditions.

The contract performance timeline establishes a 120-calendar-day period to complete the project and achieve Beneficial Occupancy Date (BOD), followed by a 60-day closeout documentation period. The pricing schedule includes 10 weather days per contract line item (CLIN) for the construction portion, with additional weather-related delays subject to site verification and approval by the Contracting Officer. Contractors must submit their pricing for the single line item on the blank pricing line provided.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment C Coat Roof B6015 A & C

PRICING SCHEDULE FNWZ 26-0180

Attachment C – Pricing Schedule

0001 Base Pricing - Item 1 – Coat Roof B6030 A & C, FNWZ 26-0180 (SUSTAINMENT) This item includes all survey, layout, plant, labor, supplies, equipment, materials, supervision and incidentals required to complete all SUSTAINMENT work in compliance with the Statement of Work and terms & conditions of the contract for Coat Roof B6030 A & C, FNWZ 26-0180.

1 LS $________________________

CONTRACT PERFORMANCE TIME:

1. The Contractor will have a limited number of calendar days to complete the project and reach the Beneficial Occupancy Date (BOD). The Period of Performance is 120 days. Once the BOD is complete, the Contractor will have 60 days to complete all the Closeout Documentation.

2. 10 weather days have been included in each CLIN for the Construction portion of the project.

Additional time for weather-related delays will be site verified & granted by the Contracting Officer.