Cooling Tower Replacement Services Pricing/Cost Form

This is a Pricing/Cost Form for Request for Proposal #25-S-030 issued by Events DC (Washington Convention and Sports Authority) for Cooling Tower Replacement Services at the Walter E. Washington Convention Center in the District of Columbia. The solicitation requests firm fixed prices for the supply and installation of eight new cooling towers and the removal of eight existing cooling towers. Additionally, contractors must provide fully loaded, fixed hourly rates for contract/account managers and lead technicians for the base year and four optional one-year renewal periods. A mandatory pre-proposal conference and site visit is scheduled for March 16, 2026, at 11:00 AM EST, with written questions due by March 19, 2026, at 5:00 PM EST, and proposals due by April 6, 2026, at 5:00 PM EST. The contract base term extends from the award date through September 30, 2027, with four optional one-year renewal periods available at Events DC's discretion.

Pricing submissions must exclude all federal excise taxes, transportation taxes, and District of Columbia sales and use taxes, and must be as low as or lower than prices charged to the contractor's most favored customer for comparable quantities, terms, and conditions. Other direct costs may be submitted on a separate sheet and paid on a cost-reimbursement basis. The RFP is subject to a 35 percent set-aside for Certified Business Enterprises or Small Business Enterprises as required under District of Columbia law, and contractors must demonstrate compliance with First Source Employment Agreement requirements mandating that 51 percent of newly hired personnel be District of Columbia residents for contracts exceeding $300,000. All quotes are valid for 90 calendar days from the date of quote, and bidders must acknowledge receipt of Events DC's Standard Contract Provisions.

View the file

Other files

File Type Posted
Addenda_4_Cooling_Tower_RFP.pdf PDF
Addenda_4_Cooling_Tower_RFP.pdf PDF
RFP_Cooling_Tower_Replacement_FINAL.pdf PDF
RFP_Cooling_Tower_Replacement_FINAL.pdf PDF
RFP_Cooling_Tower_Replacement_FINAL.pdf PDF
Events_DC_SCTs_March_2025_FINAL_(no_construction_terms).pdf PDF
Final_Tax_Certification_Affidavit-NEW_(1).pdf PDF
W9_Form.pdf PDF
Events_DC_SCTs_March_2025_FINAL_(no_construction_terms).pdf PDF
SBE_Subcontracting_Plan.pdf PDF
Events_DC_SCTs_March_2025_FINAL_(no_construction_terms).pdf PDF
OCPS_Disclosure_Statement_2025_.pdf PDF
W9_Form.pdf PDF
FIRST_SOURCE_EMPLOYMENT_AGREEMENT_Non-Construction_Final.pdf PDF
REPRESENTATIONS_AND_CERTIFICATIONS.pdf PDF
Rules_of_the_Jobsite_for_Contractors_Updated_October_2014_(1).pdf PDF
SBE_Subcontracting_Plan.pdf PDF
Final_Tax_Certification_Affidavit-NEW_(1).pdf PDF
OCPS_Disclosure_Statement_2025_.pdf PDF
2020_ACH_FORM.pdf PDF
2020_ACH_FORM.pdf PDF
2020_ACH_FORM.pdf PDF
FIRST_SOURCE_EMPLOYMENT_AGREEMENT_Non-Construction_Final.pdf PDF
Rules_of_the_Jobsite_for_Contractors_Updated_October_2014_(1).pdf PDF
W9_Form.pdf PDF
FIRST_SOURCE_EMPLOYMENT_AGREEMENT_Non-Construction_Final.pdf PDF
OCPS_Disclosure_Statement_2025_.pdf PDF
Pricing_Cost_Form_Cooling_Towers.pdf PDF
REPRESENTATIONS_AND_CERTIFICATIONS.pdf PDF
Final_Tax_Certification_Affidavit-NEW_(1).pdf PDF
Pricing_Cost_Form_Cooling_Towers.pdf PDF
REPRESENTATIONS_AND_CERTIFICATIONS.pdf PDF
Rules_of_the_Jobsite_for_Contractors_Updated_October_2014_(1).pdf PDF
SBE_Subcontracting_Plan.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 1

PRICING/COST FORM RFP #25-S-030

COOLING TOWER REPLACEMENT SERVICES

Firm Fixed Prices

Please provide Firm Fixed Prices for the Work outlined in Section C.1.

FIRM FIXED PRICE QUANTITY PRICE (EACH)

NEW COOLING TOWERS 8 $

REMOVAL OF EXISTING COOLING TOWERS 8 $

Fully Loaded, Fixed Hourly Rate

Please provide Fully Loaded, Fixed Hourly Rates for all personnel required to provide the Work outlined in Section C.1 through C.8 for the Base Year and all Option Years.

FIRM FIXED PRICE BASE

YEAR

OPTION

YEAR 1

OPTION

YEAR 2

OPTION

YEAR 3

OPTION

YEAR 4

Contract/ Account Manager $ $ $ $ $

Lead Technician $ $ $ $ $

Other Direct Costs

On a separate sheet, if applicable, submit a list of, and total price for, anticipated ODC and proposed costs which may be paid on a cost-reimbursement basis.

(a) Events DC is exempt from Federal Excise Tax, Transportation Tax, and District of Columbia Sales and Use Taxes. All prices shall exclude all taxes.

(b) The prices offered shall be as low as or lower than those charged to the Contractor’s most favored customer for comparable quantities, terms and conditions.

By checking this box, I confirm that I have received Events DC’s Standard Contract Provisions (Attachment 9).

Signed by: Date: Title: __________Company: ________

Quotes are valid for a period of ninety (90) calendar days from date of quote.

1 | P a g e Pricing/Cost Form