Price_Schedule.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
INDU Fire Suppression System Inspection & Testing Federal contract opportunity
Solicitation number
140P6425Q0034
Issued by
Department of the Interior National Park Service Midwest Region

About this file

The file is a Price Schedule for fire protection system inspection and testing services at Indiana Dunes National Park. The opportunity (Solicitation Number 140P6425Q0034) is a small business set-aside contract for comprehensive fire suppression system inspections across multiple buildings, including the Douglas Center, Cowles Lodge, and ten individual cabins. The base and optional scope involves 5-year inspections, sprinkler head testing, gauge replacements, system internals checks, and specific repairs like removing antifreeze, installing control valve signs, and replacing corroded components.

The solicitation is issued by the Department of the Interior National Park Service Midwest Region, with quotes due by 12:00 PM ET on July 31, 2025, via email. The contract is expected to be awarded in August 2025, with a 120-day performance period. An organized site visit is scheduled for July 23, 2025, at 9:00 AM CT at the Dunes Learning Center Parking Lot. Offerors must be actively registered in the System for Award Management, qualify as a small business under NAICS code 561621 (with a $25.0M size standard), and submit a price schedule, evidence of technical capability, prior experience, and SAM Unique Entity ID.

View the file

Other files for this federal contract opportunity

Other files attached to INDU Fire Suppression System Inspection & Testing, newest first.
File Type Posted
Sol_140P6425Q0034_Amd_0001.pdf PDF
Questions___Answers_0001.pdf PDF
UPDATED_Price_Schedule_0001.xlsx XLSX spreadsheet
Sol_140P6425Q0034.pdf PDF
Location_Maps.pdf PDF
HFP_Inspection_Report.pdf PDF
Statement_of_Work.pdf PDF
NPS_Structural_Fire_Management_Program.pdf PDF
SCA_WD_-_Porter_County___Lake_County__IN.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASE

UNITED STATES DEPARTMENT OF THE INTERIOR
National Park Services
Indiana Dunes National Park
Fire Protection System Inspection & Testing
Price Schedule (BASE)
DESCRIPTIONLABORMATERIALSEQUIPMENTTOTAL BASE*
BASELOCATIONBLDG NO.DESCRIPTIONQNTY*UNITS*AMOUNT*QNTY*UNITS*AMOUNT*QNTY*UNITS*AMOUNT*
1Douglas Center314Fire Sprinkler System Wet Pipe 4.0 Inches. Perform 5 year inspection, perform batch testing on all sprinkler heads, test or replace 1.5” fire hose cabinet, replace corroded sprinkler in janitor’s closet, install control valves on risers in basement.1LS$ - 011,062SF$ - 01LS$ - 0$ - 0
2Cowles Lodge215Fire Sprinkler System Dry Pipe 3.0 Inches. Perform 5 year inspection, perform batch testing on all sprinkler heads, replace gauges, perform internals on dry system, check valve, and FDC piping. Repair damaged sprinkler head that has been temporarily patched.1LS6,250SF1LS
3Cabin 1 - Jack Pine210Fire Sprinkler System, Residential Pipe 1.0 Inch. Perform 5 year inspection, replace all sprinkler heads, remove all antifreeze from system and replace with new code compliant antifreeze, install signs on control valves, perform internal inspection, replace gauges, install sprinkler box, spare sprinkler heads, and wrench. (Each Building)1LS576SF1LS
4Cabin 2 - Black Cherry2111LS576SF1LS
5Cabin 3 - Sassafras2121LS576SF1LS
6Cabin 4 - Cottonwood2131LS576SF1LS
7Cabin 5 - Sugar Maple2141LS576SF1LS
8Cabin 6 - White Pine2161LS576SF1LS
9Cabin 7 - Black Oak2171LS576SF1LS
10Cabin 8 - Service Berry2181LS576SF1LS
11Cabin 9 - Paper Birch2191LS576SF1LS
12Cabin 10 - Witch Hazel2201LS576SF1LS
Price Schedule (OPTIONS)
DESCRIPTIONLABORMATERIALSEQUIPMENTTOTALS OPTIONS*
OPTIONLOCATIONBLDG NO.DESCRIPTIONQNTY*UNITS*AMOUNT*QNTY*UNITS*AMOUNT*QNTY*UNITS*AMOUNT*
1Director Cabin203Fire Sprinkler Dry Pipe 3.0 Inch. Perform 5 year inspection, perform batch testing on all sprinkler heads, replace gauges.1LS$ - 0740SF$ - 01LS$ - 0$ - 0
2Staff Cabin204Fire Sprinkler Dry Pipe 3.0 Inch. Perform 5 year inspection, perform batch testing on all sprinkler heads, replace gauges.1LS$ - 0720SF$ - 01LS$ - 0$ - 0
3Caretakers House205Fire Sprinkler System Residential, Pipe 1.5 Inch. Perform 5 year inspection, perform batch testing on all sprinkler heads, replace gauges.1LS$ - 01,275SF$ - 01LS$ - 0$ - 0
4Sears House209 HS-499ZFire Sprinkler System Residential, Pipe 1.0 Inch. Perform 5 year inspection, perform batch testing on all sprinkler heads, replace gauges, repair or replace backflow preventer.1LS$ - 02,700SF$ - 01LS$ - 0$ - 0
5US 20 Dorm507Fire Sprinkler System. Perform 5 year inspection, perform batch testing on all sprinkler heads, replace gauges.1LS$ - 02,146SF$ - 01LS$ - 0$ - 0
TOTAL (ALL OPTIONS)$ - 0

GRAND TOTAL (BASE + ALL OPTIONS) $ - 0

*NOTE all quantities have been estimated. It is the responsibility of the offeror to verify all quantities and ensure that quote covers the completion of entire project.
*NOTE offerors are responsible for ensuring all amounts/formulas are accurate.
*NOTE LS = Lump Sum / SF = Square Feet