The document provided appears to be a preliminary bid results spreadsheet for a state and local contract opportunity issued by the Oregon Department of Transportation (ODOT) for the supply and installation of a pre-manufactured Wash Rack Platform at the ODOT Shady Maintenance Station site in Douglas County, Oregon. The project requires the provision and installation of a Work Platform adjacent to a Wash Rack, with an estimated quantity of 1 lump sum. The bid response deadline is October 10, 2024, at 2:00 PM.

The preliminary bid results show pricing from three contractors - L&M Custom Builders, Hayes Construction, and Freedom Builders. The total project cost estimates range from $42,710.00 to $75,000.00. No other details are provided regarding the award criteria, funding sources, or contract term.

View the file

Other files

File Type Posted
RFCQ_ESB Shady Wash Rack~1.docx DOCX document
2024-91 Notice of Intent to Award- signed.pdf PDF
RFCQ_ESB Shady Wash Rack.docx DOCX document
Reference Drawings Shady_wash_plans.pdf PDF
Exhibit 1 WASH RACK PLATFORM SCOPE OF WORK.pdf PDF
Exhibit 2 Plans~15.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00011611October 10, 2024 2:00 PM
Preliminary Results*L&M Custom BuildersHayes ConstructionFreedom Builders
ItemDescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Total Project CostProvision and installation of a Work Platform adjacent to a Wash Rack1LS$42,710.00$42,710.00$65,189.20$65,189.20$75,000.00$75,000.00
*Preliminary Results are not an indicator of Award