Preliminary Bid Results~70.xlsx
XLSX spreadsheet 15 KB Posted
- Solicitation number
- S-KN0010-00015264
- Issued by
- Klamath County, Oregon
About this file
This is a Preliminary Bid Results tabulation for ITB No. S-73000-00015265, issued on January 15, 2026, for a Steel Bridge Ramp—Girder Strengthening project. The bid closing occurred on January 15, 2026, at 2:00 p.m. Seven contractors submitted bids: Lee Contractors, LLC; Farline Bridge, Inc.; Wildish Standard Paving Co.; Hamilton Construction Co.; HP Civil Inc.; Oregon State Bridge Construction, Inc.; and DallumBuildCo LLC. The project scope includes mobilization, temporary work zone traffic control, pollution control planning, internal shear anchors installation (224 each), and crack injection and sealing work (150 linear feet). The bid tabulation presents unit prices and total prices for each line item across all seven bidders, with total bid amounts ranging from $173,300.00 to $461,300.00. This tabulation is explicitly noted as not being an indicator of award but rather a compilation of submitted bids for consideration.
The project involves five primary bid line items with varying complexity and cost implications. Mobilization costs ranged from $15,000.00 to $36,300.00 across bidders, while temporary traffic control ranged from $18,000.00 to $122,500.00, representing significant variation in contractor approaches to project logistics. The internal shear anchors bid item, representing the largest quantity (224 units), demonstrated unit pricing between $450.00 and $1,200.00 per anchor, substantially affecting total project costs. Lee Contractors, LLC submitted the lowest total bid at $173,300.00, while DallumBuildCo LLC submitted the highest at $461,300.00. The substantial pricing variance across bidders—particularly in traffic control and mobilization components—reflects differing risk assessments and operational strategies among the competing contractors.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 1/15/26 | ||||||||
| ITB No. | S-73000-00015265 | BIDDER | |||||||
| NAME: | Lee Contractors, LLC | Farline Bridge, Inc. | Wildish Standard Paving Co. | Hamilton Construction Co | HP Civil Inc. | Oregon State Bridge Construction, Inc. | DallumBuildCo LLC | ||
| Bid Closing: | January 15, 2026 2:00 pm | CITY/STATE: | |||||||
| Description: | Steel Bridge Ramp - Girder Strengthening | CCB#: | |||||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | $ 15,000.00 | $ 15,000.00 | $ 18,533.33 | $ 18,533.33 | $ 22,000.00 | $ 22,000.00 | $ 23,400.00 | $ 23,400.00 | $ 25,955.55 | $ 25,955.55 | $ 36,300.00 | $ 36,300.00 | $ 22,000.00 | $ 22,000.00 |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | 1 | LS | $ 30,000.00 | $ 30,000.00 | $ 18,000.00 | $ 18,000.00 | $ 20,000.00 | $ 20,000.00 | $ 35,000.00 | $ 35,000.00 | $ 75,000.00 | $ 75,000.00 | $ 122,500.00 | $ 122,500.00 | $ 45,000.00 | $ 45,000.00 |
| 3 | POLLUTION CONTROL PLAN | 1 | LS | $ 500.00 | $ 500.00 | $ 500.00 | $ 500.00 | $ 111.00 | $ 111.00 | $ 1,500.00 | $ 1,500.00 | $ 250.00 | $ 250.00 | $ 7,000.00 | $ 7,000.00 | $ 13,000.00 | $ 13,000.00 |
| 4 | INTERNAL SHEAR ANCHORS, TOP | 224 | EACH | $ 450.00 | $ 100,800.00 | $ 575.00 | $ 128,800.00 | $ 750.00 | $ 168,000.00 | $ 735.00 | $ 164,640.00 | $ 650.00 | $ 145,600.00 | $ 747.00 | $ 167,328.00 | $ 1,200.00 | $ 268,800.00 |
| 5 | INJECT AND SEAL CRACKS | 150 | FOOT | $ 180.00 | $ 27,000.00 | $ 130.00 | $ 19,500.00 | $ 125.00 | $ 18,750.00 | $ 65.00 | $ 9,750.00 | $ 85.00 | $ 12,750.00 | $ 200.00 | $ 30,000.00 | $ 750.00 | $ 112,500.00 |
| TOTAL | $ 173,300.00 | $ 185,333.33 | $ 228,861.00 | $ 234,290.00 | $ 259,555.55 | $ 363,128.00 | $ 461,300.00 |