Prelim Bid Results~87.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
ITB - Condon Pedestrian Access Project
Solicitation number
S-73000-00007424
Issued by
Deschutes County, Corvallis City, Oregon

About this file

This document is a Preliminary Bid Results spreadsheet for the Condon Pedestrian Access Project ITB in the state of Oregon. The project involves constructing sidewalks, driveways, and curb ramps on North Main Street and Frazer Street in the City of Condon for the benefit of ODOT. The scope of work includes all labor, materials, transportation, equipment, and services required to complete the construction. The bid results show the unit prices and total bid amounts from three contractors: Brown Contracting, Inc., Cascade Civil Corp, and HP Civil Inc. The bid items include mobilization, traffic control, erosion control, contaminated soil disposal, construction survey work, concrete flatwork, curb and gutter, and signage.

The pricing details show a range of unit prices across the various bid items. The lowest total bid price is $444,888 from Brown Contracting, Inc., while the highest is $555,445.77 from HP Civil Inc. There are no indications of any set-asides, incumbent contractors, or specific funding requirements in the provided information.

View the file

Other files

File Type Posted
35722 Special Provisions.pdf PDF
Bid Pricing Form~19.xlsx XLSX spreadsheet
35722 Invitation to Bid.docx DOCX document
ATTACHMENT 4 Budget Proposal.pdf PDF
35722 Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00007424 Condon Pedestrian Access Project
PRELIMINARY BID RESULTSBrown Contracting, Inc.Cascade Civil CorpHP Civil Inc.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1MOBILIZATION1LS$ 44,000.00$ 44,000.00$ 36,500.00$ 36,500.00$55,544.57$ 55,544.57$ - 0
2TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC1LS$ 6,000.00$ 6,000.00$ 12,000.00$ 12,000.00$55,000.00$ 55,000.00$ - 0
3TEMPORARY SIGNS515SQFT$ 18.00$ 9,270.00$ 7.00$ 3,605.00$1.00$ 515.00$ - 0
4FLAGGERS100HOUR$ 1.00$ 100.00$ 70.00$ 7,000.00$60.00$ 6,000.00$ - 0
5TEMPORARY BARRICADES, TYPE II8EACH$ 85.00$ 680.00$ 110.00$ 880.00$100.00$ 800.00$ - 0
6PEDESTRIAN CHANNELIZING DEVICES130FOOT$ 25.00$ 3,250.00$ 6.00$ 780.00$23.00$ 2,990.00$ - 0
7EROSION CONTROL1LS$ 4,000.00$ 4,000.00$ 2,200.00$ 2,200.00$7,500.00$ 7,500.00$ - 0
8INLET PROTECTION, TYPE 72EACH$ 300.00$ 600.00$ 260.00$ 520.00$250.00$ 500.00$ - 0
9POLLUTION CONTROL PLAN1LS$ 2,000.00$ 2,000.00$ 1,200.00$ 1,200.00$3,100.00$ 3,100.00$ - 0
10HEALTH AND SAFETY PLAN1LS$ 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$3,100.00$ 3,100.00$ - 0
11LEAD COMPLIANCE PLAN1LS$ 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$3,100.00$ 3,100.00$ - 0
12CONTAMINATED SOIL DISPOSAL133TON$ 115.00$ 15,295.00$ 250.00$ 33,250.00$90.00$ 11,970.00$ - 0
13SEGREGATE AND STOCKPILE CONTAMINATED SOIL1LS$ 5,000.00$ 5,000.00$ 50,000.00$ 50,000.00$25,000.00$ 25,000.00$ - 0
14SOIL SAMPLE COLLECTION AND ANALYTICAL TESTING2EACH$ 3,500.00$ 7,000.00$ 4,000.00$ 8,000.00$2,000.00$ 4,000.00$ - 0
15CONSTRUCTION SURVEY WORK1LS$ 12,000.00$ 12,000.00$ 7,400.00$ 7,400.00$25,000.00$ 25,000.00$ - 0
16REMOVAL OF STRUCTURES AND OBSTRUCTIONS1LS$ 43,000.00$ 43,000.00$ 24,000.00$ 24,000.00$20,000.00$ 20,000.00$ - 0
17GENERAL EXCAVATION1LS$ 32,125.00$ 32,125.00$ 57,000.00$ 57,000.00$75,000.00$ 75,000.00$ - 0
18ADJUSTING BOXES8EACH$ 600.00$ 4,800.00$ 95.00$ 760.00$800.00$ 6,400.00$ - 0
19AGGREGATE BASE314TON$ 120.00$ 37,680.00$ 145.00$ 45,530.00$80.00$ 25,120.00$ - 0
20CONCRETE CURBS, CURB AND GUTTER668FOOT$ 120.00$ 80,160.00$ 61.00$ 40,748.00$74.00$ 49,432.00$ - 0
21CONCRETE CURBS, STANDARD CURB18FOOT$ 160.00$ 2,880.00$ 48.00$ 864.00$76.00$ 1,368.00$ - 0
22CONCRETE DRIVEWAYS1443SQFT$ 20.00$ 28,860.00$ 15.00$ 21,645.00$23.00$ 33,189.00$ - 0
23CONCRETE DRIVEWAYS, REINFORCED776SQFT$ 26.00$ 20,176.00$ 17.00$ 13,192.00$26.50$ 20,564.00$ - 0
24CONCRETE WALKS4964SQFT$ 13.00$ 64,532.00$ 12.00$ 59,568.00$ 18.80$ 93,323.20$ - 0
25EXTRA FOR CURB RAMPS6EACH$ 800.00$ 4,800.00$ 1,100.00$ 6,600.00$ 2,500.00$ 15,000.00$ - 0
26TRUNCATED DOMES ON NEW SURFACES60SQFT$ 82.00$ 4,920.00$ 55.00$ 3,300.00$ 52.00$ 3,120.00$ - 0
27REMOVE EXISTING SIGNS1LS$ 1,200.00$ 1,200.00$ 1,100.00$ 1,100.00$ 1,500.00$ 1,500.00$ - 0
28SIGN SUPPORT FOOTINGS1LS$ 2,000.00$ 2,000.00$ 2,300.00$ 2,300.00$ 3,000.00$ 3,000.00$ - 0
29PERFORATED STEEL SQUARE TUBE SLIP BASE SIGN SUPPORTS1LS$ 2,400.00$ 2,400.00$ 1,100.00$ 1,100.00$ 3,500.00$ 3,500.00$ - 0
30SIGNS, STANDARD SHEETING, PLYWOOD27SQFT$ 80.00$ 2,160.00$ 44.00$ 1,188.00$ 30.00$ 810.00$ - 0
TOTAL$ 444,888.00$ 449,230.00$ 555,445.77$ - 0